up_reraStatus: Completed
CASE ID: 0901126015182021

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Arpita Basu, U.P. Real Estate Regulatory Authority Lucknow

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

25 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126015182021 by Lucknow Development Authority against Arpita Basu, U.P. Real Estate Regulatory Authority Lucknow before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 131/05/2023

for delivery of Judgment/Order

The Appellate Tribunal dismissed the appeal filed by Lucknow Development Authority, upholding the Regulatory Authority's order to pay interest (MCLR+1%) to the respondent for delayed possession and directing the transfer of the appellant's pre-deposited amount to U.P. RERA for disbursement.

3
Stage 206/02/2023

Hearing

The Tribunal heard arguments regarding the jurisdiction of the Regulatory Authority over claims for possession and compensation, subsequently reserving judgment on the matter.

4
Stage 321/12/2022

For Order

The Tribunal granted a request from the respondent's counsel to adjourn the matter and rescheduled the appeal for further orders on 06.02.2023.

5
Stage 428/11/2022

For Order

No text available.

6
Stage 501/11/2022

For Order

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the case for further orders on 28.11.2022.

7
Stage 627/09/2022

Exchange of pleadings

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and directed that the reply be shared via email and uploaded to the e-portal.

8
Stage 729/08/2022

Exchange of pleadings

No text available.

9
Stage 819/07/2022

Further Order

The Tribunal directed the appellant to pay a total cost of Rs. 6000/-, split equally between the respondent and the Tribunal fund, and granted the respondent a final opportunity to file a reply.

10
Stage 909/05/2022

Further Order

The Tribunal directed the respondent to file a reply to the grounds of appeal within 20 days and scheduled the case for further orders on July 19, 2022.

11
Stage 1031/03/2022

Delay condonation

The Tribunal allowed the application for condonation of delay in filing the appeal, subject to a cost of Rs. 6,000 to be split between the Tribunal's fund and the respondent, and directed the registry to register the defective appeal as regular.

12
Stage 1110/03/2022

Delay condonation

The Tribunal granted the appellant one week to file a better affidavit for condonation of delay and directed the parties to exchange documents via email and upload them to the e-portal before the next hearing on 31.03.2022.

13
Stage 1205/01/2022

Further Order

The Tribunal directed the respondent to file an objection against the limitation application and scheduled the matter for January 27, 2022, for disposal of said application.

14
Stage 1329/11/2021

Further Order

The Tribunal issued a notice to the respondent via registered post and email and scheduled the case for its next hearing on January 5, 2022.

15
Stage 1428/10/2021

Compliance of section 43(5)

The Tribunal granted an adjournment application moved by the appellant's counsel and directed that notice be issued to the respondent via registered post and e-mail.

16
Stage 1528/09/2021

Compliance of section 43(5)

The Tribunal issued notice to the respondent regarding the application for condonation of delay and directed the appellant to serve the respondent via speed post and email.

17
Stage 1615/04/2021

Compliance of section 43(5)

No text available.

18
Stage 1701/04/2021

Compliance of section 43(5)

No text available.

19
Stage 1823/03/2021

Compliance of section 43(5)

No text available.

20
Stage 1910/03/2021

Compliance of section 43(5)

No text available.

21
Stage 2001/03/2021

Defect Removal

The Tribunal granted the appellant a one-week extension to comply with Section 43(5) of the Act, warning that failure to do so by the next hearing may result in dismissal.

22
Stage 21Final Ruling Order

Tribunal Order #0901126015182021-31-05-2023

The Appellate Tribunal dismissed the appeal filed by Lucknow Development Authority, upholding the Regulatory Authority's order to pay interest (MCLR+1%) to the respondent for delayed possession and directing the transfer of the appellant's pre-deposited amount to U.P. RERA for disbursement.

23
Stage 22Interim Order

Tribunal Order #0901126015182021-19-07-2022

The Tribunal directed the appellant to pay a total cost of Rs. 6000/-, split equally between the respondent and the Tribunal fund, and granted the respondent a final opportunity to file a reply.

24
Stage 23Interim Order

Tribunal Order #0901126015182021-31-03-2022

The Tribunal allowed the application for condonation of delay in filing the appeal, subject to a cost of Rs. 6,000 to be split between the Tribunal's fund and the respondent, and directed the registry to register the defective appeal as regular.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal dismissed the appeal filed by Lucknow Development Authority, upholding the Regulatory Authority's order to pay interest (MCLR+1%) to the respondent for delayed possession and directing the transfer of the appellant's pre-deposited amount to U.P. RERA for disbursement. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal dismissed the appeal filed by Lucknow Development Authority, upholding the Regulatory Authority's order to pay interest (MCLR+1%) to the respondent for delayed possession and directing the transfer of the appellant's pre-deposited amount to U.P. RERA for disbursement.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 20.08.2014 to 25.04.2019

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Saurabh Misra
  • N A

Respondent Advocate(s)

  • Ashok Kumar Pandey
  • Abhishek Yadav

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126015182021-31-05-2023

The Appellate Tribunal dismissed the appeal filed by Lucknow Development Authority, upholding the Regulatory Authority's order to pay interest (MCLR+1%) to the respondent for delayed possession and directing the transfer of the appellant's pre-deposited amount to U.P. RERA for disbursement.

INTERIM_ORDEROrder ID: 0901126015182021-19-07-2022

The Tribunal directed the appellant to pay a total cost of Rs. 6000/-, split equally between the respondent and the Tribunal fund, and granted the respondent a final opportunity to file a reply.

INTERIM_ORDEROrder ID: 0901126015182021-31-03-2022

The Tribunal allowed the application for condonation of delay in filing the appeal, subject to a cost of Rs. 6,000 to be split between the Tribunal's fund and the respondent, and directed the registry to register the defective appeal as regular.