up_reraStatus: Completed
CASE ID: 0901126015032021

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Sanjay Kumar, Suman Saxena, U.P. Real Estate Regulatory Authority Lucknow

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

18 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126015032021 by Lucknow Development Authority against Sanjay Kumar, Suman Saxena, U.P. Real Estate Regulatory Authority Lucknow before up_rera.

Delay Compensation / Interest
2
Stage 130/12/2022

for delivery of Judgment/Order

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal.

3
Stage 222/12/2022

Further Order

The Tribunal heard arguments from both counsels and scheduled the appeal for the delivery of judgment on December 30, 2022.

4
Stage 320/12/2022

Further Order

The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the appeal for hearing on 22.12.2022.

5
Stage 416/12/2022

Further Order

Upon the request of the appellant's counsel, the tribunal adjourned the matter and scheduled the appeal for further orders on 20.12.2022.

6
Stage 514/12/2022

Further Order

The Tribunal adjourned the appeal to 16.12.2022 because the counsel for the appellant was on sanctioned leave.

7
Stage 625/11/2022

for delivery of Judgment/Order

The Tribunal allowed the appellant's application for condonation of delay, permitting the appeal to proceed on its merits subject to a cost of Rs. 10,000/- to be shared between the Tribunal Fund and the respondent.

8
Stage 729/11/2021

Further Order

The Tribunal heard arguments regarding the limitation application and reserved judgment on the point of limitation and its objection.

9
Stage 828/10/2021

Compliance of section 43(5)

The Tribunal granted an adjournment requested by the applicant and directed the respondent's counsel to file their Vakalat Nama and objections within ten days.

10
Stage 928/09/2021

Compliance of section 43(5)

The Tribunal issued notice to the respondents regarding the application for condonation of delay and provided specific procedural directions for service of notice and filing of pleadings.

11
Stage 1015/04/2021

Compliance of section 43(5)

No text available.

12
Stage 1101/04/2021

Compliance of section 43(5)

No text available.

13
Stage 1223/03/2021

Compliance of section 43(5)

No text available.

14
Stage 1310/03/2021

Compliance of section 43(5)

No text available.

15
Stage 1401/03/2021

Defect Removal

The Tribunal granted the appellant a one-week extension to comply with Section 43(5) of the Act, warning that failure to do so by the next hearing may result in dismissal.

16
Stage 15Final Ruling Order

Tribunal Order #0901126015032021-30-12-2022

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal.

17
Stage 16Interim Order

Tribunal Order #0901126015032021-25-11-2022

The Tribunal allowed the appellant's application for condonation of delay, permitting the appeal to proceed on its merits subject to a cost of Rs. 10,000/- to be shared between the Tribunal Fund and the respondent.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal.

Ruling Awarded To

Respondent

Interest Period

from 27.04.2013 to 26.10.2016

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Saurabh Misra

Respondent Advocate(s)

  • Hridesh Srivastava

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126015032021-30-12-2022

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal.

INTERIM_ORDEROrder ID: 0901126015032021-25-11-2022

The Tribunal allowed the appellant's application for condonation of delay, permitting the appeal to proceed on its merits subject to a cost of Rs. 10,000/- to be shared between the Tribunal Fund and the respondent.