up_reraStatus: Completed
CASE ID: 0901126014992023

Appellant / Complainant

U.P. Awas Evam Vikas Parishad

VS

Respondent

Amarendra Kant Pandey

Disputed Amount

30,00,000

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

16 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126014992023 by U.P. Awas Evam Vikas Parishad against Amarendra Kant Pandey before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 108/11/2024

for delivery of Judgment/Order

The Appellate Tribunal set aside several orders passed by the Adjudicating Officer that had granted interest as compensation for delayed possession, ruling that such interest is a matter of regulatory authority jurisdiction and not the adjudicating officer's power under Section 71.

3
Stage 209/08/2024

For Order

The Tribunal condoned the delay in filing the appeal, noting that since the impugned order prima facie appeared to be passed without jurisdiction, the matter must be heard on its merits to prevent a miscarriage of justice.

4
Stage 311/07/2024

For Order

The Tribunal granted a request by the appellant's counsel to list the appeal for orders or hearing on 09.08.2024.

5
Stage 414/05/2024

For Order

The Tribunal granted an adjournment requested by the appellant's counsel due to his unavailability and scheduled the defective appeal for orders on 11.07.2024.

6
Stage 512/04/2024

For Order

The Tribunal noted the filing of objections by the respondent and directed the appellant to file a reply within one week, scheduling the next hearing for 14.05.2024.

7
Stage 607/03/2024

For Order

The Tribunal granted the respondent one week to file objections to the application for condonation of delay and grounds of appeal, scheduling the next hearing for April 12, 2024.

8
Stage 701/02/2024

For Order

The Tribunal granted the respondent 10 days to file objections regarding the application for condonation of delay and scheduled the matter for hearing on March 7, 2024.

9
Stage 816/01/2024

Hearing

The Tribunal granted the appellant's counsel one week to file a reply to the respondent's objections and scheduled the defective appeal for hearing on 01.02.2024.

10
Stage 912/10/2023

Hearing

No text available.

11
Stage 1004/09/2023

Notice

The Tribunal adjourned the proceedings due to a three-day strike called by the Bar Council of Uttar Pradesh and rescheduled the matter for 12.10.2023.

12
Stage 1113/07/2023

Delay condonation

The Tribunal directed the Accounts Department to verify a deposit of Rs. 4,07,989/- made by the appellant for compliance with Section 43(5) of the Act and issued notice to the respondent regarding an application for condonation of delay.

13
Stage 12Final Ruling Order

Tribunal Order #0901126014992023-08-11-2024

The Appellate Tribunal set aside several orders passed by the Adjudicating Officer that had granted interest as compensation for delayed possession, ruling that such interest is a matter of regulatory authority jurisdiction and not the adjudicating officer's power under Section 71.

14
Stage 13Interim Order

Tribunal Order #0901126014992023-09-08-2024

The Tribunal condoned the delay in filing the appeal, noting that since the impugned order prima facie appeared to be passed without jurisdiction, the matter must be heard on its merits to prevent a miscarriage of justice.

15
Stage 14Interim Order

Tribunal Order #0901126014992023-13-07-2023

The Tribunal directed the Accounts Department to verify a deposit of Rs. 4,07,989/- made by the appellant for compliance with Section 43(5) of the Act and issued notice to the respondent regarding an application for condonation of delay.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal set aside several orders passed by the Adjudicating Officer that had granted interest as compensation for delayed possession, ruling that such interest is a matter of regulatory authority jurisdiction and not the adjudicating officer's power under Section 71. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.

Disposal Winner: AppellantInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal set aside several orders passed by the Adjudicating Officer that had granted interest as compensation for delayed possession, ruling that such interest is a matter of regulatory authority jurisdiction and not the adjudicating officer's power under Section 71.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1%

Interest Period

from 02-06-2017 to 20-11-2020

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Anurag Singh

Respondent Advocate(s)

  • Pramod Mitra

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126014992023-08-11-2024

The Appellate Tribunal set aside several orders passed by the Adjudicating Officer that had granted interest as compensation for delayed possession, ruling that such interest is a matter of regulatory authority jurisdiction and not the adjudicating officer's power under Section 71.

INTERIM_ORDEROrder ID: 0901126014992023-09-08-2024

The Tribunal condoned the delay in filing the appeal, noting that since the impugned order prima facie appeared to be passed without jurisdiction, the matter must be heard on its merits to prevent a miscarriage of justice.

INTERIM_ORDEROrder ID: 0901126014992023-13-07-2023

The Tribunal directed the Accounts Department to verify a deposit of Rs. 4,07,989/- made by the appellant for compliance with Section 43(5) of the Act and issued notice to the respondent regarding an application for condonation of delay.