Appellant / Complainant
U.P. State Industrial Development Authority
Respondent
Deepak Dwivedi
₹36,00,000
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126014992020 by U.P. State Industrial Development Authority against Deepak Dwivedi before up_rera.
for delivery of Judgment/Order
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by UPSIDA, confirming the RERA Authority's order that the Trans Ganga City project is delayed and directing the appellant to hand over possession of the plot along with interest at the rate of MCLR+1% per annum.
Re-Hearing
The court concluded the hearing of the matter and reserved the judgment for a later date.
Further Order
The Tribunal heard submissions regarding the filing of a replication against the reply to the appeal and subsequently reserved the judgment for delivery.
Hearing
The Tribunal allowed an application to delete prayer no. (ii) from the appeal and directed both parties to exchange a list of dates, events, and relied-upon judgments before the next hearing.
Further Order
The Tribunal directed the parties to file a list of dates, events, and relied-upon judgments, and scheduled the matter for arguments on 12.04.2021.
Further Order
The matter was adjourned upon the joint request of both parties and is scheduled for further hearing on 17.03.2021.
Tribunal Order #0901126014992020-30-12-2022
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by UPSIDA, confirming the RERA Authority's order that the Trans Ganga City project is delayed and directing the appellant to hand over possession of the plot along with interest at the rate of MCLR+1% per annum.
Tribunal Order #0901126014992020-13-09-2021
The Tribunal allowed an application to delete prayer no. (ii) from the appeal and directed both parties to exchange a list of dates, events, and relied-upon judgments before the next hearing.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by UPSIDA, confirming the RERA Authority's order that the Trans Ganga City project is delayed and directing the appellant to hand over possession of the plot along with interest at the rate of MCLR+1% per annum. Awarded in favor of Respondent. Awarded interest rate: MCLR+1% per annum.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by UPSIDA, confirming the RERA Authority's order that the Trans Ganga City project is delayed and directing the appellant to hand over possession of the plot along with interest at the rate of MCLR+1% per annum.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1% per annum
Interest Period
from December, 2016 till date of handing over actual possession of the plot
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Kartikey Dubey
- Ramesh Chandra Mishra
Respondent Advocate(s)
- Deepak Dwivedi
Official RERA Tribunal Orders (2)
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by UPSIDA, confirming the RERA Authority's order that the Trans Ganga City project is delayed and directing the appellant to hand over possession of the plot along with interest at the rate of MCLR+1% per annum.
The Tribunal allowed an application to delete prayer no. (ii) from the appeal and directed both parties to exchange a list of dates, events, and relied-upon judgments before the next hearing.