Appellant / Complainant
Yamuna Expressway Industrial Development Authority
Respondent
Sandeep Soin
₹23,28,000
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126014822020 by Yamuna Expressway Industrial Development Authority against Sandeep Soin before up_rera.
for delivery of Judgment/Order
The Tribunal partially allowed the appeal by modifying the interest rate for the delay period (2013–2016) from 6% to 4% per annum, while upholding the remaining directions of the Regulatory Authority and ordering the transfer of pre-deposited funds to U.P. RERA for disbursement.
Final Hearing
The Tribunal heard arguments regarding the applicability of interest rates for delayed possession under the 2016 Act and has reserved its judgment.
Hearing
The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on November 22, 2022.
Hearing
At the request of both parties, the Tribunal has adjourned the appeal and scheduled it for a hearing on November 2, 2022.
Hearing
The Tribunal directed the parties to exchange lists of dates, events, and relied-upon judgments and scheduled the appeal for a hearing on 28.09.2022.
Hearing
The Tribunal adjourned the appeal to 30.08.2022 because the counsel for the appellant was on sanctioned leave.
Hearing
The Tribunal directed the appellant to submit additional facts regarding a disposed Supreme Court case within 10 days and scheduled the matter for hearing on August 1, 2022.
Hearing
The Tribunal directed the respondent to file a list of dates and events at least seven days before the next hearing and scheduled the matter for 12.07.2022.
Hearing
The Tribunal directed both parties to exchange lists of dates, events, and relied-upon cases before the next hearing, which is scheduled for 24.05.2022.
Hearing
The Tribunal noted that pleadings are complete and directed both counsels to exchange and file lists of dates, events, and relied-upon cases at least seven days before the next hearing. The case is scheduled for hearing on 20.04.2022.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to COVID-19 infection and rescheduled the hearing for 20.01.2022.
Hearing
The Tribunal directed both counsels to appear on the next scheduled date and listed the appeal for hearing on 03.01.2022.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to personal difficulties and rescheduled the hearing for December 21, 2021.
Hearing
The Tribunal directed the parties to complete their pleadings and scheduled the next hearing for November 17, 2021.
Hearing
The Tribunal granted a final opportunity to the appellant to file their replication/rejoinder affidavit and directed them to serve a copy to the respondent via email before the next hearing on 22.10.2021.
Further Order
The Tribunal granted the appellant a final 15-day opportunity to file a replication or rejoinder and scheduled the next hearing for 12.04.2021.
Further Hearing
The appeal is adjourned to 17.03.2021 due to a lawyer strike, with the appellant directed to file a reply to the respondent's objections in the interim.
Further Hearing
The Tribunal noted the respondent's filing of a reply and granted the appellant permission to file a replication or rejoinder before the next hearing scheduled for 26.02.2021.
Tribunal Order #0901126014822020-09-12-2022
The Tribunal partially allowed the appeal by modifying the interest rate for the delay period (2013–2016) from 6% to 4% per annum, while upholding the remaining directions of the Regulatory Authority and ordering the transfer of pre-deposited funds to U.P. RERA for disbursement.
Tribunal Disposal & Final Award Ruling
The Tribunal partially allowed the appeal by modifying the interest rate for the delay period (2013–2016) from 6% to 4% per annum, while upholding the remaining directions of the Regulatory Authority and ordering the transfer of pre-deposited funds to U.P. RERA for disbursement. Awarded in favor of Partial. Awarded interest rate: MCLR+1% and 4% per annum.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal partially allowed the appeal by modifying the interest rate for the delay period (2013–2016) from 6% to 4% per annum, while upholding the remaining directions of the Regulatory Authority and ordering the transfer of pre-deposited funds to U.P. RERA for disbursement.
Ruling Awarded To
Partial
Awarded Interest Rate
MCLR+1% and 4% per annum
Interest Period
from 21.10.2013 to 30.04.2016 (at 4%) and from 01.05.2017 onwards (at MCLR+1%)
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Prashant Kumar
- Kushagra Dikshit
Respondent Advocate(s)
- Anurag Singh
- Harpreet Singhth
Official RERA Tribunal Orders (1)
The Tribunal partially allowed the appeal by modifying the interest rate for the delay period (2013–2016) from 6% to 4% per annum, while upholding the remaining directions of the Regulatory Authority and ordering the transfer of pre-deposited funds to U.P. RERA for disbursement.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.