up_reraStatus: Completed
CASE ID: 0901126014692022

Appellant / Complainant

Uppal Chadha Hi-Tech Developers Pvt. Ltd.

VS

Respondent

Anita Rathee

Developer Firm

uppal chadha hi-tech developers pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

21 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126014692022 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Anita Rathee before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 108/01/2025

Delay condonation

The Tribunal dismissed the appeal filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., ruling that 'farmers' agitation' does not constitute a 'force majeure' event under the RERA Act 2016 and upholding the Regulatory Authority's order to pay delay interest to the respondent.

3
Stage 223/11/2024

Hearing

The Tribunal granted a request for adjournment by the appellant's counsel and rescheduled the appeal for orders to 08.01.2025.

4
Stage 328/10/2024

Hearing

No text available.

5
Stage 420/09/2024

Hearing

The Tribunal noted the filing of a rejoinder by the appellant and scheduled the defective appeal for consideration of the application for condonation of delay on 28.10.2024.

6
Stage 514/08/2024

Hearing

The Tribunal granted the appellant seven days to file a reply to the respondent's objections and scheduled the next hearing for September 20, 2024.

7
Stage 619/07/2024

Hearing

The Tribunal allowed the respondent's recall application to set aside the order dated 12.04.2024 that had closed their opportunity to file objections, subsequently taking the respondent's objections on record.

8
Stage 711/07/2024

Hearing

The Tribunal granted an adjournment due to the respondent's counsel being unable to appear and scheduled the matter to be listed on 19.07.2024 alongside a connected matter.

9
Stage 814/05/2024

Hearing

The Tribunal noted the absence of the appellant's counsel and scheduled the defective appeal for a hearing on the application for condonation of delay on 11.07.2024.

10
Stage 912/04/2024

Hearing

The Tribunal closed the respondent's opportunity to file objections due to failure to comply with previous orders and scheduled the defective appeal for hearing on 14.05.2024.

11
Stage 1007/03/2024

Delay condonation

The Tribunal granted a 10-day extension to the respondent to file objections regarding the condonation of delay and grounds of appeal following an adjournment request by the appellant.

12
Stage 1101/02/2024

Delay condonation

The Tribunal ruled that service of notice to the respondent is sufficient due to multiple delivery attempts and auto-generated RERA notifications, while granting the respondent 10 days to file objections.

13
Stage 1208/01/2024

Delay condonation

The Tribunal directed the Registry to issue a fresh notice for 01.02.2024 and outlined the procedural steps for the applicant to serve the respondent via email regarding the application for condonation of delay.

14
Stage 1329/09/2023

Delay condonation

No text available.

15
Stage 1418/08/2023

Delay condonation

The Tribunal directed the issuance of fresh notice to the respondent via email due to non-compliance with previous directions regarding electronic service, and scheduled the matter for 29.09.2023.

16
Stage 1503/07/2023

Delay condonation

The Tribunal noted the appellant's deposit of Rs. 13,35,211/- in compliance with Section 43(5) and issued notice to the respondent regarding the application for condonation of delay, scheduling the matter for hearing on 18.08.2023.

17
Stage 16Final Ruling Order

Tribunal Order #0901126014692022-08-01-2025

The Tribunal dismissed the appeal filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., ruling that 'farmers' agitation' does not constitute a 'force majeure' event under the RERA Act 2016 and upholding the Regulatory Authority's order to pay delay interest to the respondent.

18
Stage 17Interim Order

Tribunal Order #0901126014692022-19-07-2024

The Tribunal allowed the respondent's recall application to set aside the order dated 12.04.2024 that had closed their opportunity to file objections, subsequently taking the respondent's objections on record.

19
Stage 18Interim Order

Tribunal Order #0901126014692022-12-04-2024

The Tribunal closed the respondent's opportunity to file objections due to failure to comply with previous orders and scheduled the defective appeal for hearing on 14.05.2024.

20
Stage 19Interim Order

Tribunal Order #0901126014692022-03-07-2023

The Tribunal noted the appellant's deposit of Rs. 13,35,211/- in compliance with Section 43(5) and issued notice to the respondent regarding the application for condonation of delay, scheduling the matter for hearing on 18.08.2023.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., ruling that 'farmers' agitation' does not constitute a 'force majeure' event under the RERA Act 2016 and upholding the Regulatory Authority's order to pay delay interest to the respondent. Awarded in favor of Respondent. Awarded interest rate: MCLR+1 percent.

Disposal Winner: RespondentInterest Rate: MCLR+1 percentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., ruling that 'farmers' agitation' does not constitute a 'force majeure' event under the RERA Act 2016 and upholding the Regulatory Authority's order to pay delay interest to the respondent.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1 percent

Interest Period

from 16.02.2015 till date of offer of possession or date of O.C./C.C., whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Bal Kishor Verma
  • Amit Yadav

Respondent Advocate(s)

  • Tushar Bahadur
  • Sachin Gupta

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126014692022-08-01-2025

The Tribunal dismissed the appeal filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., ruling that 'farmers' agitation' does not constitute a 'force majeure' event under the RERA Act 2016 and upholding the Regulatory Authority's order to pay delay interest to the respondent.

INTERIM_ORDEROrder ID: 0901126014692022-19-07-2024

The Tribunal allowed the respondent's recall application to set aside the order dated 12.04.2024 that had closed their opportunity to file objections, subsequently taking the respondent's objections on record.

INTERIM_ORDEROrder ID: 0901126014692022-12-04-2024

The Tribunal closed the respondent's opportunity to file objections due to failure to comply with previous orders and scheduled the defective appeal for hearing on 14.05.2024.

INTERIM_ORDEROrder ID: 0901126014692022-03-07-2023

The Tribunal noted the appellant's deposit of Rs. 13,35,211/- in compliance with Section 43(5) and issued notice to the respondent regarding the application for condonation of delay, scheduling the matter for hearing on 18.08.2023.

TathyaGrid RERA Intelligence AI

Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →