up_reraStatus: Completed
CASE ID: 0901126014692020

Appellant / Complainant

Vandana Shukla, Anr.

VS

Respondent

Tulsiani Constructions and Developers Ltd.

Developer Firm

tulsiani constructions and developers ltd.

Disputed Amount

66,50,000

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestPromotional Misrepresentation

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

17 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126014692020 by Vandana Shukla, Anr. against Tulsiani Constructions and Developers Ltd. before up_rera.

Delay in PossessionDelay Compensation / InterestPromotional Misrepresentation
2
Stage 121/03/2022

for delivery of Judgment/Order

The Tribunal partially allowed the appeal and modified the Adjudicating Officer's order, directing the respondent to pay delay interest at MCLR+1% on the flat's basic price from 14.11.2017 until the date of legal possession or execution of the conveyance deed following receipt of OC/CC.

3
Stage 211/11/2021

Final Hearing

The Tribunal heard arguments regarding the respondent's failure to comply with a RERA order and the status of CC/OC applications, subsequently reserving judgment on the matter.

4
Stage 301/11/2021

Hearing

No text available.

5
Stage 405/10/2021

Hearing

The Tribunal directed the Registry to summon the case records of Complaint No. ADJ/LKO162/05/0834/2019 from the U.P. Real Estate Regulatory Authority and rescheduled the appeal hearing to 01.11.2021.

6
Stage 508/09/2021

For Order

No text available.

7
Stage 626/04/2021

Delay condonation

No text available.

8
Stage 701/04/2021

Delay condonation

No text available.

9
Stage 805/03/2021

Delay condonation

The matter was adjourned to 01.04.2021 due to a lawyers' strike, with the parties directed to exchange their pleadings in the interim.

10
Stage 904/03/2021

Delay condonation

No text available.

11
Stage 1012/02/2021

For Order

The Tribunal granted an adjournment requested by the appellant's counsel due to personal engagement and rescheduled the hearing for consideration of the condonation of delay application to 05.03.2021.

12
Stage 1122/01/2021

Hearing

The Tribunal directed the Registry to record the counsel's name for the respondent and scheduled the case for hearing on 12.02.2021 regarding the application for condonation of delay.

13
Stage 1218/12/2020

Hearing

No text available.

14
Stage 13Final Ruling Order

Tribunal Order #0901126014692020-21-03-2022

The Tribunal partially allowed the appeal and modified the Adjudicating Officer's order, directing the respondent to pay delay interest at MCLR+1% on the flat's basic price from 14.11.2017 until the date of legal possession or execution of the conveyance deed following receipt of OC/CC.

15
Stage 14Interim Order

Tribunal Order #0901126014692020-11-11-2021

The Tribunal heard arguments regarding the respondent's failure to comply with a RERA order and the status of CC/OC applications, subsequently reserving judgment on the matter.

16
Stage 15Interim Order

Tribunal Order #0901126014692020-05-10-2021

The Tribunal directed the Registry to summon the case records of Complaint No. ADJ/LKO162/05/0834/2019 from the U.P. Real Estate Regulatory Authority and rescheduled the appeal hearing to 01.11.2021.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal partially allowed the appeal and modified the Adjudicating Officer's order, directing the respondent to pay delay interest at MCLR+1% on the flat's basic price from 14.11.2017 until the date of legal possession or execution of the conveyance deed following receipt of OC/CC. Awarded in favor of Partial. Awarded interest rate: MCLR+1%.

Disposal Winner: PartialInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal partially allowed the appeal and modified the Adjudicating Officer's order, directing the respondent to pay delay interest at MCLR+1% on the flat's basic price from 14.11.2017 until the date of legal possession or execution of the conveyance deed following receipt of OC/CC.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR+1%

Interest Period

from 14.11.2017 till the date of offer of legal possession/execution of conveyance deed, whichever is earlier, after receiving OC/CC from the competent authority

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 12

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare

Respondent Advocate(s)

  • Saurabh Misra

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126014692020-21-03-2022

The Tribunal partially allowed the appeal and modified the Adjudicating Officer's order, directing the respondent to pay delay interest at MCLR+1% on the flat's basic price from 14.11.2017 until the date of legal possession or execution of the conveyance deed following receipt of OC/CC.

INTERIM_ORDEROrder ID: 0901126014692020-11-11-2021

The Tribunal heard arguments regarding the respondent's failure to comply with a RERA order and the status of CC/OC applications, subsequently reserving judgment on the matter.

INTERIM_ORDEROrder ID: 0901126014692020-05-10-2021

The Tribunal directed the Registry to summon the case records of Complaint No. ADJ/LKO162/05/0834/2019 from the U.P. Real Estate Regulatory Authority and rescheduled the appeal hearing to 01.11.2021.

TathyaGrid RERA Intelligence AI