Appellant / Complainant
Lucknow Development Authority
Respondent
Pooja Chauhan
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126014352020 by Lucknow Development Authority against Pooja Chauhan before up_rera.
for delivery of Judgment/Order
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period from 27.04.2013 to 26.10.2016 upon request.
Hearing
The Tribunal heard arguments from both counsels and scheduled the appeal for the delivery of judgment on December 30, 2022.
Hearing
The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the hearing for November 4, 2022.
Hearing
The Tribunal scheduled the appeal for a hearing on 30.09.2022 and directed both counsels to be present, noting that arguments would proceed in their absence.
Hearing
The Tribunal noted that lists of dates and events have been exchanged between the parties and scheduled the appeal for a hearing on 01.09.2022.
Hearing
The Tribunal directed both parties to exchange and file written arguments at least seven days before the next hearing and scheduled the case for 03.08.2022.
Hearing
The Tribunal granted the appellant 20 days to file a replication/rejoinder against the respondent's reply and scheduled the next hearing for May 27, 2022.
Hearing
The Tribunal allowed the application for condonation of delay due to the COVID-19 pandemic extension period and directed that the defective appeal be registered as a Regular Appeal.
Delay condonation
The U.P. Real Estate Appellate Tribunal adjourned the case due to the absence of both parties and scheduled it for further orders on 04.02.2022.
Compliance of section 43(5)
The Tribunal noted compliance with Section 43(5) of the Act and scheduled the defective appeal for January 10, 2022, to address the limitation application and any objections.
Compliance of section 43(5)
The Tribunal directed the appellant to complete service of notice upon the respondent and scheduled the matter for further orders on 09.12.2021.
Hearing
The Tribunal issued a notice to the respondent via registered post and email and scheduled the defective appeal for further hearing on 17.11.2021.
Defect Removal
The Tribunal noted that the appellant has deposited the balance amount required under Section 43(5) of the Act and directed that notice be issued to the respondent via registered post and email.
Defect Removal
The court adjourned the hearing to 25.03.2021 due to a lawyers' strike and directed the applicant to comply with a previous order dated 08.02.2021.
Defect Removal
The Tribunal granted an adjournment following an application for personal grounds and directed the applicant to remove registry defects and deposit the balance amount required under Section 43 (5) of the Act before the next hearing on 05.03.2021.
Tribunal Order #0901126014352020-30-12-2022
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period from 27.04.2013 to 26.10.2016 upon request.
Tribunal Order #0901126014352020-21-03-2022
The Tribunal allowed the application for condonation of delay due to the COVID-19 pandemic extension period and directed that the defective appeal be registered as a Regular Appeal.
Tribunal Disposal & Final Award Ruling
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period from 27.04.2013 to 26.10.2016 upon request. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period from 27.04.2013 to 26.10.2016 upon request.
Ruling Awarded To
Respondent
Interest Period
from 27.04.2013 to 26.10.2016
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Amit Yadav
Respondent Advocate(s)
- Anand Kumar Singh
Official RERA Tribunal Orders (2)
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period from 27.04.2013 to 26.10.2016 upon request.
The Tribunal allowed the application for condonation of delay due to the COVID-19 pandemic extension period and directed that the defective appeal be registered as a Regular Appeal.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.