up_reraStatus: Completed
CASE ID: 0901126014292022

Appellant / Complainant

Poonam Aggarwal

VS

Respondent

Sangwan Heights Pvt Ltd

Developer Firm

sangwan heights pvt ltd

Disputed Amount

14,50,000

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

30 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126014292022 by Poonam Aggarwal against Sangwan Heights Pvt Ltd before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 116/04/2025

for delivery of Judgment/Order

The Tribunal dismissed the appeal, ruling that because the project was abandoned and the allotment cancelled prior to the enforcement of the RERA Act, 2016, the appellant is not entitled to interest under the Act but may seek damages for breach of contract in another forum.

3
Stage 211/02/2025

Hearing

The Tribunal heard arguments from both parties regarding the appeal, after which the judgment was reserved for later delivery.

4
Stage 307/01/2025

Hearing

Upon the joint request of the counsel for both parties, the Tribunal has adjourned the appeal and scheduled it for a hearing on 11.02.2025.

5
Stage 423/11/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the hearing for January 7, 2025.

6
Stage 528/10/2024

Hearing

No text available.

7
Stage 620/09/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to his unavailability and rescheduled the appeal for hearing on 28.10.2024.

8
Stage 714/08/2024

Hearing

The Tribunal has adjourned the matter to 20.09.2024 for orders/hearing following a joint request from the counsels of both parties.

9
Stage 816/07/2024

Hearing

The Tribunal has adjourned the appeal to 14.08.2024 for orders/hearing following a joint request from the counsel of both parties.

10
Stage 916/05/2024

Hearing

No text available.

11
Stage 1016/04/2024

Hearing

The Tribunal granted the appellant three days to file a reply to the respondent's objections and scheduled the appeal for a hearing on May 16, 2024.

12
Stage 1112/03/2024

Hearing

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the appeal for hearing on April 16, 2024.

13
Stage 1212/02/2024

Hearing

The Tribunal granted the appellant one week's time to file a reply to the respondent's objections and scheduled the defective appeal for hearing on March 12, 2024.

14
Stage 1310/10/2023

Hearing

No text available.

15
Stage 1430/08/2023

Hearing

No text available.

16
Stage 1512/07/2023

Hearing

No text available.

17
Stage 1602/05/2023

Hearing

The Tribunal granted the respondent one week to file objections via email and scheduled the matter for hearing on 12.07.2023.

18
Stage 1721/03/2023

Hearing

No text available.

19
Stage 1810/02/2023

Hearing

No text available.

20
Stage 1923/12/2022

Hearing on Recall App

The Tribunal adjourned the appeal to 10.02.2023 because the respondent's counsel were on sanctioned leave.

21
Stage 2030/11/2022

Hearing on Recall App

No text available.

22
Stage 2104/11/2022

Hearing on Recall App

No text available.

23
Stage 2229/09/2022

Hearing on Recall App

The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the appeal for hearing on 04.11.2022.

24
Stage 2330/08/2022

Hearing on Recall App

The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the matter for hearing on 28.09.2022.

25
Stage 2401/08/2022

Hearing

The Tribunal granted the respondent 10 days to file objections to the appeal and directed both parties to exchange soft copies of their pleadings via email before uploading them to the e-portal.

26
Stage 2520/07/2022

Hearing

The Tribunal directed the Registry to coordinate with the NIC to ensure that a missing order dated 11.04.2022 is uploaded to the e-Portal and scheduled the matter for further hearing on 01.08.2022.

27
Stage 2610/05/2022

Hearing

The Tribunal adjourned the matter to 20.07.2022 due to lawyers abstaining from work following a resolution by the Oudh Bar Association.

28
Stage 2731/03/2022

Hearing on Appeal

The appeal was dismissed for want of prosecution due to the non-appearance of the appellant's counsel.

29
Stage 28Final Ruling Order

Tribunal Order #0901126014292022-16-04-2025

The Tribunal dismissed the appeal, ruling that because the project was abandoned and the allotment cancelled prior to the enforcement of the RERA Act, 2016, the appellant is not entitled to interest under the Act but may seek damages for breach of contract in another forum.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal, ruling that because the project was abandoned and the allotment cancelled prior to the enforcement of the RERA Act, 2016, the appellant is not entitled to interest under the Act but may seek damages for breach of contract in another forum. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal, ruling that because the project was abandoned and the allotment cancelled prior to the enforcement of the RERA Act, 2016, the appellant is not entitled to interest under the Act but may seek damages for breach of contract in another forum.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Yadav
  • Atul Kumar Singh

Respondent Advocate(s)

  • Azhar Ikram
  • Manish Singh

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126014292022-16-04-2025

The Tribunal dismissed the appeal, ruling that because the project was abandoned and the allotment cancelled prior to the enforcement of the RERA Act, 2016, the appellant is not entitled to interest under the Act but may seek damages for breach of contract in another forum.