up_reraStatus: Completed
CASE ID: 0901126013822020

Appellant / Complainant

Greater Noida Industrial Development Authority

VS

Respondent

Anil Kumar Agnihotri

Disputed Amount

25,72,000

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

13 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126013822020 by Greater Noida Industrial Development Authority against Anil Kumar Agnihotri before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 116/09/2021

for delivery of Judgment/Order

The Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to refund the respondent's deposit of Rs. 25,72,000 with interest at the rate of MCLR+1% p.a. due to delayed possession.

3
Stage 218/03/2021

For Order

The Tribunal heard arguments from the counsel for the appellant and the respondent in person, subsequently reserving the judgment for a later date.

4
Stage 303/03/2021

Hearing

The respondent informed the Tribunal that he has received the principal amount via RTGS as per previous orders, and the matter is scheduled for a subsequent hearing on 18.03.2021.

5
Stage 423/02/2021

For Order

The appellant's counsel assured the tribunal that all outstanding dues would be remitted to the respondent by February 26, 2021, and the court directed the appellant to honor this commitment.

6
Stage 515/02/2021

For Order

The Tribunal granted a one-week extension to the appellant to comply with the previous order dated 21.01.2021 regarding the RTGS payment to the respondent.

7
Stage 621/01/2021

For Order

The Tribunal directed the appellant (GNIDA) to immediately transfer the respondent's deposited money plus interest as prescribed in the scheme brochure via RTGS within 10 days, while reserving the issue of the MCLR+1% interest rate for further examination.

8
Stage 705/01/2021

Further Order

No text available.

9
Stage 817/12/2020

Further Order

No text available.

10
Stage 9Interim Order

Tribunal Order #0901126013822020-23-02-2021

The appellant's counsel assured the tribunal that all outstanding dues would be remitted to the respondent by February 26, 2021, and the court directed the appellant to honor this commitment.

11
Stage 10Final Ruling Order

Tribunal Order #0901126013822020-16-09-2021

The Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to refund the respondent's deposit of Rs. 25,72,000 with interest at the rate of MCLR+1% p.a. due to delayed possession.

12
Stage 11Interim Order

Tribunal Order #0901126013822020-21-01-2021

The Tribunal directed the appellant (GNIDA) to immediately transfer the respondent's deposited money plus interest as prescribed in the scheme brochure via RTGS within 10 days, while reserving the issue of the MCLR+1% interest rate for further examination.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to refund the respondent's deposit of Rs. 25,72,000 with interest at the rate of MCLR+1% p.a. due to delayed possession. Awarded in favor of Respondent. Awarded interest rate: MCLR+1% p.a..

Disposal Winner: RespondentInterest Rate: MCLR+1% p.a.Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to refund the respondent's deposit of Rs. 25,72,000 with interest at the rate of MCLR+1% p.a. due to delayed possession.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1% p.a.

Interest Period

from the date of deposit till the date of payment

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rajesh Chadha

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126013822020-23-02-2021

The appellant's counsel assured the tribunal that all outstanding dues would be remitted to the respondent by February 26, 2021, and the court directed the appellant to honor this commitment.

FINAL_ORDEROrder ID: 0901126013822020-16-09-2021

The Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to refund the respondent's deposit of Rs. 25,72,000 with interest at the rate of MCLR+1% p.a. due to delayed possession.

INTERIM_ORDEROrder ID: 0901126013822020-21-01-2021

The Tribunal directed the appellant (GNIDA) to immediately transfer the respondent's deposited money plus interest as prescribed in the scheme brochure via RTGS within 10 days, while reserving the issue of the MCLR+1% interest rate for further examination.