up_reraStatus: Completed
CASE ID: 0901126013782020

Appellant / Complainant

Ashoka Sharma

VS

Respondent

Ashoka Sharma V/s M/s Tyagi Construction Company & Others

Developer Firm

tyagi construction company

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

19 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126013782020 by Ashoka Sharma against Ashoka Sharma V/s M/s Tyagi Construction Company & Others before up_rera.

2
Stage 112/04/2022

to file objections and its reply

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Ashoka Sharma against M/s Tyagi Construction Company & Others via an order dated 12.04.2022.

3
Stage 222/03/2022

to file objections and its reply

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the next hearing for April 12, 2022.

4
Stage 304/03/2022

Further Order

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the appeal for hearing on 22.03.2022.

5
Stage 421/01/2022

Exchange of pleadings

No text available.

6
Stage 509/12/2021

Further Order

No text available.

7
Stage 611/11/2021

Further Order

No text available.

8
Stage 728/10/2021

Further Order

The Tribunal granted an adjournment requested by the respondent and directed the applicant and the respondent's partner to appear in person on 26.11.2021 to attempt an amicable settlement.

9
Stage 804/10/2021

Hearing

The Tribunal directed the parties to attempt an out-of-court settlement regarding disputed payments and scheduled the matter for further orders on 28.10.2021.

10
Stage 909/09/2021

Hearing

The Tribunal noted an application for compromise filed by the parties, but also recorded allegations from the applicant's husband that the signatures and photograph on the settlement papers were forged. The matter is listed for 29.09.2021 to address these concerns.

11
Stage 1005/05/2021

Hearing

No text available.

12
Stage 1108/04/2021

Hearing

No text available.

13
Stage 1212/03/2021

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to her being out of station and rescheduled the matter for April 8, 2021.

14
Stage 1311/02/2021

Further Hearing

The matter was adjourned to 12.03.2021 following a dispute regarding whether the parties had reached a settlement.

15
Stage 1406/01/2021

Further Order

No text available.

16
Stage 1525/11/2020

Further Order

No text available.

17
Stage 16Final Ruling Order

Tribunal Order #0901126013782020-12-04-2022

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Ashoka Sharma against M/s Tyagi Construction Company & Others via an order dated 12.04.2022.

18
Stage 17Interim Order

Tribunal Order #0901126013782020-09-09-2021

The Tribunal noted an application for compromise filed by the parties, but also recorded allegations from the applicant's husband that the signatures and photograph on the settlement papers were forged. The matter is listed for 29.09.2021 to address these concerns.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Ashoka Sharma against M/s Tyagi Construction Company & Others via an order dated 12.04.2022. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Ashoka Sharma against M/s Tyagi Construction Company & Others via an order dated 12.04.2022.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Prashant Kumar
  • Fuhar Gupta

Respondent Advocate(s)

  • Sanjay Kumar Srivastava

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126013782020-12-04-2022

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Ashoka Sharma against M/s Tyagi Construction Company & Others via an order dated 12.04.2022.

INTERIM_ORDEROrder ID: 0901126013782020-09-09-2021

The Tribunal noted an application for compromise filed by the parties, but also recorded allegations from the applicant's husband that the signatures and photograph on the settlement papers were forged. The matter is listed for 29.09.2021 to address these concerns.

TathyaGrid RERA Intelligence AI

Need to research all rulings for tyagi construction company?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →