Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126013782020 by Ashoka Sharma against Ashoka Sharma V/s M/s Tyagi Construction Company & Others before up_rera.
to file objections and its reply
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Ashoka Sharma against M/s Tyagi Construction Company & Others via an order dated 12.04.2022.
to file objections and its reply
The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the next hearing for April 12, 2022.
Further Order
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the appeal for hearing on 22.03.2022.
Further Order
The Tribunal granted an adjournment requested by the respondent and directed the applicant and the respondent's partner to appear in person on 26.11.2021 to attempt an amicable settlement.
Hearing
The Tribunal directed the parties to attempt an out-of-court settlement regarding disputed payments and scheduled the matter for further orders on 28.10.2021.
Hearing
The Tribunal noted an application for compromise filed by the parties, but also recorded allegations from the applicant's husband that the signatures and photograph on the settlement papers were forged. The matter is listed for 29.09.2021 to address these concerns.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to her being out of station and rescheduled the matter for April 8, 2021.
Further Hearing
The matter was adjourned to 12.03.2021 following a dispute regarding whether the parties had reached a settlement.
Tribunal Order #0901126013782020-12-04-2022
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Ashoka Sharma against M/s Tyagi Construction Company & Others via an order dated 12.04.2022.
Tribunal Order #0901126013782020-09-09-2021
The Tribunal noted an application for compromise filed by the parties, but also recorded allegations from the applicant's husband that the signatures and photograph on the settlement papers were forged. The matter is listed for 29.09.2021 to address these concerns.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Ashoka Sharma against M/s Tyagi Construction Company & Others via an order dated 12.04.2022. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Ashoka Sharma against M/s Tyagi Construction Company & Others via an order dated 12.04.2022.
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Prashant Kumar
- Fuhar Gupta
Respondent Advocate(s)
- Sanjay Kumar Srivastava
Official RERA Tribunal Orders (2)
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Ashoka Sharma against M/s Tyagi Construction Company & Others via an order dated 12.04.2022.
The Tribunal noted an application for compromise filed by the parties, but also recorded allegations from the applicant's husband that the signatures and photograph on the settlement papers were forged. The matter is listed for 29.09.2021 to address these concerns.
Need to research all rulings for tyagi construction company?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.