Appellant / Complainant
U.P. Avas Evam Vikas Parishad
Respondent
Shikha Bhatnagar
₹20,88,000
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126013742021 by U.P. Avas Evam Vikas Parishad against Shikha Bhatnagar before up_rera.
for delivery of Judgment/Order
The U.P. Real Estate Appellate Tribunal dismissed nine appeals filed by U.P. Awas Evam Vikas Parishad, upholding the Adjudicating Officer's orders to pay interest (MCLR+1%) to allottees for delayed possession and directing the transfer of pre-deposited funds to the Authority for distribution.
Compliance of section 43(5)
The Tribunal heard arguments from both parties regarding the appellant's challenge to a RERA order and has reserved its judgment.
Compliance of section 43(5)
The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the next hearing for November 1, 2021.
Compliance of section 43(5)
The Tribunal granted the respondent one week to file objections to the appeal and directed both parties to upload their pleadings on the e-portal before the next hearing on 18.10.2021.
Compliance of section 43(5)
The Tribunal granted the applicant one week to comply with Section 43(5) of the Act regarding the deposit of funds, imposing a cost of Rs. 10,000 for previous delays and directing that this cost be recovered from the responsible officer.
Compliance of section 43(5)
The Tribunal granted the appellant a 10-day extension to comply with Section 43(5) of the Act, warning that failure to do so by the next hearing on 08.04.2021 may result in dismissal.
Compliance of section 43(5)
The Tribunal granted the appellant a one-week extension to remove defects and comply with Section 43(5) of the Act, noting that failure to do so by the next hearing on 25.03.2021 may result in dismissal.
Defect Removal
The Tribunal granted a final one-week extension to the appellant to remove registry defects and comply with Section 43(5) of the Act, warning that failure to do so will result in dismissal of the appeal.
Admission
The Tribunal granted the appellant three days to rectify procedural defects identified by the Registry and scheduled the matter for hearing on March 1, 2021.
Tribunal Order #0901126013742021-17-09-2021
The Tribunal granted the applicant one week to comply with Section 43(5) of the Act regarding the deposit of funds, imposing a cost of Rs. 10,000 for previous delays and directing that this cost be recovered from the responsible officer.
Tribunal Order #0901126013742021-14-03-2022
The U.P. Real Estate Appellate Tribunal dismissed nine appeals filed by U.P. Awas Evam Vikas Parishad, upholding the Adjudicating Officer's orders to pay interest (MCLR+1%) to allottees for delayed possession and directing the transfer of pre-deposited funds to the Authority for distribution.
Tribunal Order #0901126013742021-01-03-2021
The Tribunal granted a final one-week extension to the appellant to remove registry defects and comply with Section 43(5) of the Act, warning that failure to do so will result in dismissal of the appeal.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal dismissed nine appeals filed by U.P. Awas Evam Vikas Parishad, upholding the Adjudicating Officer's orders to pay interest (MCLR+1%) to allottees for delayed possession and directing the transfer of pre-deposited funds to the Authority for distribution. Awarded in favor of Respondent. Awarded interest rate: MCLR+ 1 percent p.a..
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal dismissed nine appeals filed by U.P. Awas Evam Vikas Parishad, upholding the Adjudicating Officer's orders to pay interest (MCLR+1%) to allottees for delayed possession and directing the transfer of pre-deposited funds to the Authority for distribution.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+ 1 percent p.a.
Interest Period
specified in each order
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Siddharth Vikram Asthana
- Vijay Pratap Singh Chauhan
Respondent Advocate(s)
- Azhar Ikram
- Manish Singh
Official RERA Tribunal Orders (3)
The Tribunal granted the applicant one week to comply with Section 43(5) of the Act regarding the deposit of funds, imposing a cost of Rs. 10,000 for previous delays and directing that this cost be recovered from the responsible officer.
The U.P. Real Estate Appellate Tribunal dismissed nine appeals filed by U.P. Awas Evam Vikas Parishad, upholding the Adjudicating Officer's orders to pay interest (MCLR+1%) to allottees for delayed possession and directing the transfer of pre-deposited funds to the Authority for distribution.
The Tribunal granted a final one-week extension to the appellant to remove registry defects and comply with Section 43(5) of the Act, warning that failure to do so will result in dismissal of the appeal.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.