up_reraStatus: Completed
CASE ID: 0901126013732024

Appellant / Complainant

Uppal Chadha Hi-Tech Developers Pvt. Ltd.

VS

Respondent

Asha Gupta

Developer Firm

uppal chadha hi-tech developers pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

6 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126013732024 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Asha Gupta before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer
2
Stage 124/05/2024

Delay condonation

The Tribunal rejected the applications for condonation of delay in nine appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all said appeals. Additionally, the Tribunal directed that the pre-deposited amounts under Section 43(5) of the Act be transferred to the U.P. RERA for distribution to allottees during execution proceedings.

3
Stage 225/04/2024

Delay condonation

The Tribunal provisionally accepted the appellant's compliance with Section 43(5) of the Act 2016 following a deposit of Rs 2,45,887.00 and issued notices to the respondent regarding the application for condonation of delay and grounds of appeal.

4
Stage 3Final Ruling Order

Tribunal Order #0901126013732024-24-05-2024

The Tribunal rejected the applications for condonation of delay in nine appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all said appeals. Additionally, the Tribunal directed that the pre-deposited amounts under Section 43(5) of the Act be transferred to the U.P. RERA for distribution to allottees during execution proceedings.

5
Stage 4Interim Order

Tribunal Order #0901126013732024-25-04-2024

The Tribunal provisionally accepted the appellant's compliance with Section 43(5) of the Act 2016 following a deposit of Rs 2,45,887.00 and issued notices to the respondent regarding the application for condonation of delay and grounds of appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the applications for condonation of delay in nine appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all said appeals. Additionally, the Tribunal directed that the pre-deposited amounts under Section 43(5) of the Act be transferred to the U.P. RERA for distribution to allottees during execution proceedings. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1%.

Disposal Winner: RespondentInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the applications for condonation of delay in nine appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all said appeals. Additionally, the Tribunal directed that the pre-deposited amounts under Section 43(5) of the Act be transferred to the U.P. RERA for distribution to allottees during execution proceedings.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1%

Interest Period

from 08.12.2016 to date of getting OC/CC or to the date when possession of plot was offered whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Naveen Kumar Tiwari

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126013732024-24-05-2024

The Tribunal rejected the applications for condonation of delay in nine appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all said appeals. Additionally, the Tribunal directed that the pre-deposited amounts under Section 43(5) of the Act be transferred to the U.P. RERA for distribution to allottees during execution proceedings.

INTERIM_ORDEROrder ID: 0901126013732024-25-04-2024

The Tribunal provisionally accepted the appellant's compliance with Section 43(5) of the Act 2016 following a deposit of Rs 2,45,887.00 and issued notices to the respondent regarding the application for condonation of delay and grounds of appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →