up_reraStatus: Active
CASE ID: 0901126013732020

Appellant / Complainant

Greater Noida Industrial Development Authority

VS

Respondent

Kanya Lal Bhat

Disputed Amount

2,62,220

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

43 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126013732020 by Greater Noida Industrial Development Authority against Kanya Lal Bhat before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer
2
Stage 115/05/2024

for delivery of Judgment/Order

The Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order for the payment of delay interest at MCLR+1% to the respondent and directing the transfer of the appellant's pre-deposited amount to U.P. RERA for disbursement.

3
Stage 208/05/2024

Further Hearing

The Tribunal condoned the delay in filing the appeal based on Supreme Court extension orders, accepted the deposited amount as sufficient compliance under Section 43(5), and converted the defective appeal into a regular appeal to proceed with arguments regarding interest calculations.

4
Stage 305/04/2024

Further Hearing

Upon the joint request of the counsels for both parties, the court has ordered that the Misc. Case regarding the application for condonation of delay be listed for hearing/orders on 08.05.2024.

5
Stage 401/03/2024

Further Hearing

The Tribunal has ordered the appeal to be listed for a hearing on 05.04.2024.

6
Stage 529/01/2024

Further Hearing

The Tribunal adjourned the matter to 01.03.2024 because the respondent's counsel was reported to be ill.

7
Stage 630/10/2023

Further Hearing

No text available.

8
Stage 718/09/2023

Further Hearing

The Tribunal directed the Appellant (GNIDA) to produce records regarding the application for and issuance of the Occupancy/Completion Certificate (OC/CC), specifically addressing whether certificates can be issued with backdated effective dates.

9
Stage 828/07/2023

Further Hearing

No text available.

10
Stage 917/05/2023

Further Hearing

No text available.

11
Stage 1021/04/2023

Further Hearing

The case is adjourned to 17.05.2023 for orders/hearing due to the illness of the respondent's counsel.

12
Stage 1115/03/2023

Delay condonation

The Tribunal granted the applicant 10 days to file a reply to the respondent's objections and directed them to provide a soft copy of said reply via email. The matter is scheduled for orders on 21.04.2023.

13
Stage 1207/02/2023

Delay condonation

The Tribunal granted an adjournment request from the appellant's counsel due to medical reasons and rescheduled the matter for hearing on 15.03.2023.

14
Stage 1309/01/2023

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for consideration of the application for condonation of delay to 07.02.2023.

15
Stage 1402/12/2022

Delay condonation

The Tribunal adjourned the matter and scheduled the case for further orders on January 9, 2023.

16
Stage 1502/11/2022

Delay condonation

The Tribunal granted the respondent a last opportunity to file objections regarding the amount deposited under Section 43(5) of the Act, warning that failure to do so will result in proceeding according to the provisions of the Act.

17
Stage 1623/09/2022

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel and directed the appellant to file a replication/rejoinder before the next hearing date of 02.11.2022.

18
Stage 1725/08/2022

Delay condonation

The Tribunal directed the applicant to deposit the remaining amount required under Section 43(5) of the Act and submit necessary NOCs from various departments, including Fire Safety and Electricity, before the next hearing.

19
Stage 1811/07/2022

Hearing

The Tribunal directed the Greater Noida Industrial Development Authority to file a valid Occupancy Certificate/Completion Certificate (OC/CC) as per Section 43(5) of the Act, along with an affidavit from a concerned officer, because the previously submitted documents were deemed insufficient.

20
Stage 1929/04/2022

Hearing

The Tribunal directed the appellant to submit the Occupancy Certificate (OC) or Completion Certificate (CC) within 10 days, noting that the determination of the deposit amount required under Section 43(5) of the Act is contingent upon the submission of these documents.

21
Stage 2023/03/2022

Hearing

The Tribunal granted the applicant a final opportunity to deposit the remaining amount required under Section 43(5) of the Act along with a revised CA certificate.

22
Stage 2122/02/2022

Delay condonation

The Tribunal addressed a dispute regarding the calculation period for interest under Section 43(5) of the Act, specifically whether an offer of possession without OC/CC is legally valid, and granted the applicant 10 days to examine the issue.

23
Stage 2212/01/2022

Delay condonation

No text available.

24
Stage 2321/12/2021

Delay condonation

The Tribunal scheduled the case for 12.01.2022 to consider an application for condonation of delay and the respondent's objection thereto.

25
Stage 2424/11/2021

Delay condonation

The Tribunal has scheduled the case for 21.12.2021 to address and dispose of the limitation application and any filed objections.

26
Stage 2526/10/2021

Delay condonation

The Tribunal granted an application for adjournment and rescheduled the case to 24.11.2021 for the disposal of a limitation application and objections.

27
Stage 2624/09/2021

Delay condonation

The Tribunal adjourned the case to 26.10.2021 and directed the parties to exchange pleadings and file originals in the Registry at least one week before the next hearing.

28
Stage 2712/04/2021

Delay condonation

No text available.

29
Stage 2816/03/2021

Delay condonation

No text available.

30
Stage 2926/02/2021

For Order

The Tribunal adjourned the defective appeal due to an advocates' strike by the Oudh Bar Association and directed the parties to exchange pleadings before the next hearing on 16.03.2021.

31
Stage 3029/01/2021

Compliance of section 43(5)

No text available.

32
Stage 3106/01/2021

Hearing

No text available.

33
Stage 3214/12/2020

Hearing

No text available.

34
Stage 33Final Ruling Order

Tribunal Order #0901126013732020-15-05-2024

The Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order for the payment of delay interest at MCLR+1% to the respondent and directing the transfer of the appellant's pre-deposited amount to U.P. RERA for disbursement.

35
Stage 34Interim Order

Tribunal Order #0901126013732020-08-05-2024

The Tribunal condoned the delay in filing the appeal based on Supreme Court extension orders, accepted the deposited amount as sufficient compliance under Section 43(5), and converted the defective appeal into a regular appeal to proceed with arguments regarding interest calculations.

36
Stage 35Interim Order

Tribunal Order #0901126013732020-02-11-2022

The Tribunal granted the respondent a last opportunity to file objections regarding the amount deposited under Section 43(5) of the Act, warning that failure to do so will result in proceeding according to the provisions of the Act.

37
Stage 36Interim Order

Tribunal Order #0901126013732020-11-07-2022

The Tribunal directed the Greater Noida Industrial Development Authority to file a valid Occupancy Certificate/Completion Certificate (OC/CC) as per Section 43(5) of the Act, along with an affidavit from a concerned officer, because the previously submitted documents were deemed insufficient.

38
Stage 37Interim Order

Tribunal Order #0901126013732020-23-03-2022

The Tribunal granted the applicant a final opportunity to deposit the remaining amount required under Section 43(5) of the Act along with a revised CA certificate.

39
Stage 38Interim Order

Tribunal Order #0901126013732020-18-09-2023

The Tribunal directed the Appellant (GNIDA) to produce records regarding the application for and issuance of the Occupancy/Completion Certificate (OC/CC), specifically addressing whether certificates can be issued with backdated effective dates.

40
Stage 39Interim Order

Tribunal Order #0901126013732020-25-08-2022

The Tribunal directed the applicant to deposit the remaining amount required under Section 43(5) of the Act and submit necessary NOCs from various departments, including Fire Safety and Electricity, before the next hearing.

41
Stage 40Interim Order

Tribunal Order #0901126013732020-29-04-2022

The Tribunal directed the appellant to submit the Occupancy Certificate (OC) or Completion Certificate (CC) within 10 days, noting that the determination of the deposit amount required under Section 43(5) of the Act is contingent upon the submission of these documents.

42
Stage 41Interim Order

Tribunal Order #0901126013732020-22-02-2022

The Tribunal addressed a dispute regarding the calculation period for interest under Section 43(5) of the Act, specifically whether an offer of possession without OC/CC is legally valid, and granted the applicant 10 days to examine the issue.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order for the payment of delay interest at MCLR+1% to the respondent and directing the transfer of the appellant's pre-deposited amount to U.P. RERA for disbursement. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1%.

Disposal Winner: RespondentInterest Rate: MCLR + 1%Status: Active

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order for the payment of delay interest at MCLR+1% to the respondent and directing the transfer of the appellant's pre-deposited amount to U.P. RERA for disbursement.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1%

Interest Period

from 30.01.2017 till OC/CC or date of offer of possession, whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Ajay Kumar Gupta
  • Rishindra Vikram Singh

Respondent Advocate(s)

  • Tushar Bahadur

Official RERA Tribunal Orders (9)

FINAL_ORDEROrder ID: 0901126013732020-15-05-2024

The Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order for the payment of delay interest at MCLR+1% to the respondent and directing the transfer of the appellant's pre-deposited amount to U.P. RERA for disbursement.

INTERIM_ORDEROrder ID: 0901126013732020-08-05-2024

The Tribunal condoned the delay in filing the appeal based on Supreme Court extension orders, accepted the deposited amount as sufficient compliance under Section 43(5), and converted the defective appeal into a regular appeal to proceed with arguments regarding interest calculations.

INTERIM_ORDEROrder ID: 0901126013732020-02-11-2022

The Tribunal granted the respondent a last opportunity to file objections regarding the amount deposited under Section 43(5) of the Act, warning that failure to do so will result in proceeding according to the provisions of the Act.

INTERIM_ORDEROrder ID: 0901126013732020-11-07-2022

The Tribunal directed the Greater Noida Industrial Development Authority to file a valid Occupancy Certificate/Completion Certificate (OC/CC) as per Section 43(5) of the Act, along with an affidavit from a concerned officer, because the previously submitted documents were deemed insufficient.

INTERIM_ORDEROrder ID: 0901126013732020-23-03-2022

The Tribunal granted the applicant a final opportunity to deposit the remaining amount required under Section 43(5) of the Act along with a revised CA certificate.

INTERIM_ORDEROrder ID: 0901126013732020-18-09-2023

The Tribunal directed the Appellant (GNIDA) to produce records regarding the application for and issuance of the Occupancy/Completion Certificate (OC/CC), specifically addressing whether certificates can be issued with backdated effective dates.

INTERIM_ORDEROrder ID: 0901126013732020-25-08-2022

The Tribunal directed the applicant to deposit the remaining amount required under Section 43(5) of the Act and submit necessary NOCs from various departments, including Fire Safety and Electricity, before the next hearing.

INTERIM_ORDEROrder ID: 0901126013732020-29-04-2022

The Tribunal directed the appellant to submit the Occupancy Certificate (OC) or Completion Certificate (CC) within 10 days, noting that the determination of the deposit amount required under Section 43(5) of the Act is contingent upon the submission of these documents.

INTERIM_ORDEROrder ID: 0901126013732020-22-02-2022

The Tribunal addressed a dispute regarding the calculation period for interest under Section 43(5) of the Act, specifically whether an offer of possession without OC/CC is legally valid, and granted the applicant 10 days to examine the issue.