Appellant / Complainant
Vishali Batra
Respondent
Divine India Infrastructure Pvt. Ltd.
divine india infrastructure pvt. ltd.
₹58,51,643
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126013712020 by Vishali Batra against Divine India Infrastructure Pvt. Ltd. before up_rera.
for delivery of Judgment/Order
The Tribunal dismissed the appeal, ruling that because the project's completion certificate was issued prior to the RERA Act's application and the project was not registered, neither the original complaint nor the subsequent appeal were maintainable.
Hearing
The court has heard the arguments from both parties and has reserved its judgment regarding Appeal-788/2021.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to personal difficulties and rescheduled the hearing for 03.08.2023, noting that no further adjournments will be permitted.
Hearing
The Tribunal noted that the appeal is ripe for hearing and scheduled the matter for orders/hearing on 06.07.2023.
Hearing
The appeal is adjourned due to the absence of the respondent's counsel on sanctioned leave and is rescheduled for hearing on 09.02.2023.
Hearing
The Tribunal noted the respondent's repeated non-appearance and directed both counsels to appear at the next hearing on 03.11.2022 for final hearing, warning that the appeal will proceed regardless of appearance if they fail to attend.
Hearing
The Tribunal directed the respondent's counsel to file a list of dates and events before the next hearing and scheduled the appeal for final hearing on 29.09.2022.
Hearing
The Tribunal granted the Respondent a final opportunity to file a list of dates and events and scheduled the appeal for hearing on 31.08.2022.
Hearing
The Tribunal directed the appellant's counsel to file a list of dates and relied-upon cases at least seven days before the next hearing, scheduling the matter for 02.08.2022.
Hearing
The Tribunal directed both parties to exchange lists of dates, events, and relied-upon cases within 20 days and scheduled the matter for hearing on 25.05.2022.
Hearing
The Tribunal directed both counsels to exchange lists of dates and relied-upon documents at least seven days before the next hearing and scheduled the case for final hearing on 20.04.2022.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to the COVID-19 pandemic and rescheduled the hearing for 28.01.2022.
Hearing
The Tribunal granted the appellant one week to file a reply to the respondent's objections and directed that the reply be served via email and filed in the Registry before the next hearing on 07.01.2022.
Hearing
The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the appeal for final hearing on 09.12.2021.
Hearing
The Tribunal granted the respondent a final opportunity to file a reply to the grounds of appeal and scheduled the next hearing for November 25, 2021.
Hearing
The Tribunal adjourned the case to 27.10.2021 because the applicant's counsel was unable to attend due to illness.
Delay condonation
The case was adjourned due to a lawyers' strike called by the Oudh Bar Association and is scheduled for a new hearing on 19.03.2021.
Delay condonation
The Tribunal directed the respondent to file a reply to the grounds of appeal and provide an electronic copy to the applicant to facilitate a rejoinder. The matter is scheduled for further hearing on 02.03.2021.
Tribunal Order #0901126013712020-08-08-2023
The Tribunal dismissed the appeal, ruling that because the project's completion certificate was issued prior to the RERA Act's application and the project was not registered, neither the original complaint nor the subsequent appeal were maintainable.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal, ruling that because the project's completion certificate was issued prior to the RERA Act's application and the project was not registered, neither the original complaint nor the subsequent appeal were maintainable. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal, ruling that because the project's completion certificate was issued prior to the RERA Act's application and the project was not registered, neither the original complaint nor the subsequent appeal were maintainable.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Dhiresh Pandey
Respondent Advocate(s)
- Azhar Ikram
- Manish Singh
Official RERA Tribunal Orders (1)
The Tribunal dismissed the appeal, ruling that because the project's completion certificate was issued prior to the RERA Act's application and the project was not registered, neither the original complaint nor the subsequent appeal were maintainable.
Need to research all rulings for divine india infrastructure pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.