up_reraStatus: Completed
CASE ID: 0901126013432020

Appellant / Complainant

Priyanka Dubey

VS

Respondent

Lucknow Development Authority

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

28 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126013432020 by Priyanka Dubey against Lucknow Development Authority before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 130/12/2022

for delivery of Judgment/Order

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, it directed the transfer of funds deposited under Section 43(5) of the Act to the Regulatory Authority for disposal.

3
Stage 223/12/2022

Final Hearing

The Tribunal heard arguments from both parties and scheduled the appeal for the delivery of judgment on 30.12.2022.

4
Stage 330/11/2022

Final Hearing

No text available.

5
Stage 404/11/2022

Final Hearing

No text available.

6
Stage 530/09/2022

Final Hearing

The Tribunal directed the parties to exchange and submit a list of dates, events, and relied-upon judgments, and scheduled the matter for further orders on 04.11.2022.

7
Stage 601/09/2022

Final Hearing

The Tribunal directed the parties to exchange and submit a list of dates, events, and relied-upon judgments before the next hearing scheduled for September 30, 2022.

8
Stage 703/08/2022

Final Hearing

The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the hearing for September 1, 2022, to be heard alongside Cross Appeal No. 192/2021.

9
Stage 825/07/2022

Final Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and directed the respondent to file objections in the cross-appeal and serve a copy to the appellant via email.

10
Stage 911/07/2022

Final Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to unavailability and scheduled the matter for final hearing on 25.07.2022.

11
Stage 1002/05/2022

Final Hearing

The Tribunal granted the appellant time to file a list of dates and events and scheduled the matter for hearing on 11.07.2022, alongside a pending cross-appeal.

12
Stage 1112/04/2022

Final Hearing

The Tribunal directed the appellant to file a list of dates, events, and relied-upon judgments within 20 days and scheduled the next hearing for May 2, 2022.

13
Stage 1209/03/2022

Final Hearing

The Tribunal noted that pleadings are complete and directed both parties to exchange lists of dates, events, and relied-upon cases at least seven days before the next hearing scheduled for 12.04.2022.

14
Stage 1310/01/2022

Final Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the appeal to be listed alongside Appeal No. 192/2021 on 27.01.2022.

15
Stage 1422/12/2021

Final Hearing

The Tribunal has scheduled the appeal for a hearing on 10.01.2022 and directed both parties to appear on the fixed date.

16
Stage 1506/12/2021

Hearing

The Tribunal noted that the appellant's reply to objections would be filed later that day and scheduled the appeal for a hearing on 22.12.2021.

17
Stage 1618/11/2021

Hearing

The Tribunal directed the respondent to provide legible copies of its objections within 24 hours and ordered the appellant to file a reply within 10 days of receipt.

18
Stage 1727/09/2021

Hearing

The Tribunal directed the appellant's counsel to file a rejoinder affidavit, if desired, and scheduled the next hearing for November 18, 2021.

19
Stage 1807/09/2021

Hearing

The Tribunal granted the respondent one final opportunity to file a reply to the appeal and directed them to serve a copy of said reply to the applicant via email. The matter is adjourned to 27.09.2021.

20
Stage 1930/04/2021

Further Order

No text available.

21
Stage 2005/04/2021

Hearing

No text available.

22
Stage 2115/03/2021

Hearing

The Tribunal imposed a cost to be deposited into the Tribunal's fund and scheduled the matter for hearing on 05.04.2021.

23
Stage 2201/03/2021

Further Order

The appeal is adjourned because lawyers are abstaining from work due to a call by the Oudh Bar Association; the matter is rescheduled for 15.03.2021.

24
Stage 2302/02/2021

Further Order

The Tribunal granted the respondent a final opportunity to file a reply to the appeal via the e-portal and physical registry within 15 days, with the matter listed for hearing on 01.03.2021.

25
Stage 2414/12/2020

Further Order

No text available.

26
Stage 25Interim Order

Tribunal Order #0901126013432020-15-03-2021

The Tribunal imposed a cost to be deposited into the Tribunal's fund and scheduled the matter for hearing on 05.04.2021.

27
Stage 26Final Ruling Order

Tribunal Order #0901126013432020-30-12-2022

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, it directed the transfer of funds deposited under Section 43(5) of the Act to the Regulatory Authority for disposal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, it directed the transfer of funds deposited under Section 43(5) of the Act to the Regulatory Authority for disposal. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, it directed the transfer of funds deposited under Section 43(5) of the Act to the Regulatory Authority for disposal.

Ruling Awarded To

Respondent

Interest Period

from 27.04.2013 to 26.10.2016

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Ashish Chaturvedi

Respondent Advocate(s)

  • Saurabh Misra

Official RERA Tribunal Orders (2)

INTERIM_ORDEROrder ID: 0901126013432020-15-03-2021

The Tribunal imposed a cost to be deposited into the Tribunal's fund and scheduled the matter for hearing on 05.04.2021.

FINAL_ORDEROrder ID: 0901126013432020-30-12-2022

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, it directed the transfer of funds deposited under Section 43(5) of the Act to the Regulatory Authority for disposal.