up_reraStatus: Completed
CASE ID: 0901126013002020

Appellant / Complainant

Greater Noida Industrial Development Authority

VS

Respondent

Mahipal Yadav

Disputed Amount

31,66,140

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestSale Deed & Title Transfer

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

27 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126013002020 by Greater Noida Industrial Development Authority against Mahipal Yadav before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestSale Deed & Title Transfer
2
Stage 127/09/2022

for delivery of Judgment/Order

The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest at MCLR+1% for delayed possession and directing the transfer of pre-deposited funds to U.P. RERA for execution.

3
Stage 221/09/2022

Final Hearing

The Tribunal heard arguments regarding an appeal by Greater Noida Industrial Development Authority against a RERA order directing the grant of interest for delayed possession and the delivery of a unit by 31.01.2020; judgment has been reserved.

4
Stage 324/08/2022

Final Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for 21.09.2022.

5
Stage 428/07/2022

Final Hearing

No text available.

6
Stage 514/07/2022

Final Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for 28.07.2022.

7
Stage 624/05/2022

Final Hearing

The Tribunal adjourned the matter due to the illness of the appellant's counsel and scheduled the hearing for July 14, 2022, noting a failure to comply with Section 43(5) of the Act.

8
Stage 721/04/2022

Final Hearing

The Tribunal condoned the delay in filing the appeal subject to a cost of Rs. 1000/- and directed the appellant to comply with Section 43(5) of the Act before the next hearing.

9
Stage 804/03/2022

Final Hearing

The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the hearing for April 21, 2022.

10
Stage 921/01/2022

Final Hearing

No text available.

11
Stage 1006/01/2022

Final Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the hearing for 21.01.2022.

12
Stage 1108/12/2021

Final Hearing

The Tribunal granted the appellant's counsel a one-week extension to prepare his brief and rescheduled the final hearing for January 6, 2022.

13
Stage 1217/11/2021

Hearing

No text available.

14
Stage 1322/10/2021

Hearing

The Tribunal closed the appellant's opportunity to file a reply to the respondent's objections due to failure to comply with a previous stop order and deadline.

15
Stage 1421/09/2021

Hearing

The Tribunal granted the Appellant two weeks to file a reply to the Respondent's objections and scheduled the matter for hearing on the application for condonation of delay on 22.10.2021.

16
Stage 1503/05/2021

Hearing

No text available.

17
Stage 1609/04/2021

Hearing

No text available.

18
Stage 1716/03/2021

Hearing on Appeal

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for April 9, 2021.

19
Stage 1826/02/2021

For Order

The appeal is adjourned to 16.03.2021 due to a lawyers' strike, with a directive for the appellant's counsel to file a reply to the respondent's objections via the e-portal.

20
Stage 1904/02/2021

For Order

The Tribunal granted the appellant two weeks to file a reply to the respondent's objections and directed parties to upload their filings on the e-portal before the next hearing on 26.02.2021.

21
Stage 2005/01/2021

Hearing on Appeal

No text available.

22
Stage 2126/08/2020

Hearing on Appeal

No text available.

23
Stage 22Interim Order

Tribunal Order #0901126013002020-21-09-2022

The Tribunal heard arguments regarding an appeal by Greater Noida Industrial Development Authority against a RERA order directing the grant of interest for delayed possession and the delivery of a unit by 31.01.2020; judgment has been reserved.

24
Stage 23Interim Order

Tribunal Order #0901126013002020-21-04-2022

The Tribunal condoned the delay in filing the appeal subject to a cost of Rs. 1000/- and directed the appellant to comply with Section 43(5) of the Act before the next hearing.

25
Stage 24Interim Order

Tribunal Order #0901126013002020-22-10-2021

The Tribunal closed the appellant's opportunity to file a reply to the respondent's objections due to failure to comply with a previous stop order and deadline.

26
Stage 25Final Ruling Order

Tribunal Order #0901126013002020-27-09-2022

The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest at MCLR+1% for delayed possession and directing the transfer of pre-deposited funds to U.P. RERA for execution.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest at MCLR+1% for delayed possession and directing the transfer of pre-deposited funds to U.P. RERA for execution. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest at MCLR+1% for delayed possession and directing the transfer of pre-deposited funds to U.P. RERA for execution.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 30.01.2017 till offer of possession along with OC/CC

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rajesh Chadha

Respondent Advocate(s)

  • Abhishek Khare

Official RERA Tribunal Orders (4)

INTERIM_ORDEROrder ID: 0901126013002020-21-09-2022

The Tribunal heard arguments regarding an appeal by Greater Noida Industrial Development Authority against a RERA order directing the grant of interest for delayed possession and the delivery of a unit by 31.01.2020; judgment has been reserved.

INTERIM_ORDEROrder ID: 0901126013002020-21-04-2022

The Tribunal condoned the delay in filing the appeal subject to a cost of Rs. 1000/- and directed the appellant to comply with Section 43(5) of the Act before the next hearing.

INTERIM_ORDEROrder ID: 0901126013002020-22-10-2021

The Tribunal closed the appellant's opportunity to file a reply to the respondent's objections due to failure to comply with a previous stop order and deadline.

FINAL_ORDEROrder ID: 0901126013002020-27-09-2022

The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest at MCLR+1% for delayed possession and directing the transfer of pre-deposited funds to U.P. RERA for execution.