Appellant / Complainant
Greater Noida Industrial Development Authority
Respondent
Mahipal Yadav
₹31,66,140
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126013002020 by Greater Noida Industrial Development Authority against Mahipal Yadav before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest at MCLR+1% for delayed possession and directing the transfer of pre-deposited funds to U.P. RERA for execution.
Final Hearing
The Tribunal heard arguments regarding an appeal by Greater Noida Industrial Development Authority against a RERA order directing the grant of interest for delayed possession and the delivery of a unit by 31.01.2020; judgment has been reserved.
Final Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for 21.09.2022.
Final Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for 28.07.2022.
Final Hearing
The Tribunal adjourned the matter due to the illness of the appellant's counsel and scheduled the hearing for July 14, 2022, noting a failure to comply with Section 43(5) of the Act.
Final Hearing
The Tribunal condoned the delay in filing the appeal subject to a cost of Rs. 1000/- and directed the appellant to comply with Section 43(5) of the Act before the next hearing.
Final Hearing
The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the hearing for April 21, 2022.
Final Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the hearing for 21.01.2022.
Final Hearing
The Tribunal granted the appellant's counsel a one-week extension to prepare his brief and rescheduled the final hearing for January 6, 2022.
Hearing
The Tribunal closed the appellant's opportunity to file a reply to the respondent's objections due to failure to comply with a previous stop order and deadline.
Hearing
The Tribunal granted the Appellant two weeks to file a reply to the Respondent's objections and scheduled the matter for hearing on the application for condonation of delay on 22.10.2021.
Hearing on Appeal
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for April 9, 2021.
For Order
The appeal is adjourned to 16.03.2021 due to a lawyers' strike, with a directive for the appellant's counsel to file a reply to the respondent's objections via the e-portal.
For Order
The Tribunal granted the appellant two weeks to file a reply to the respondent's objections and directed parties to upload their filings on the e-portal before the next hearing on 26.02.2021.
Tribunal Order #0901126013002020-21-09-2022
The Tribunal heard arguments regarding an appeal by Greater Noida Industrial Development Authority against a RERA order directing the grant of interest for delayed possession and the delivery of a unit by 31.01.2020; judgment has been reserved.
Tribunal Order #0901126013002020-21-04-2022
The Tribunal condoned the delay in filing the appeal subject to a cost of Rs. 1000/- and directed the appellant to comply with Section 43(5) of the Act before the next hearing.
Tribunal Order #0901126013002020-22-10-2021
The Tribunal closed the appellant's opportunity to file a reply to the respondent's objections due to failure to comply with a previous stop order and deadline.
Tribunal Order #0901126013002020-27-09-2022
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest at MCLR+1% for delayed possession and directing the transfer of pre-deposited funds to U.P. RERA for execution.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest at MCLR+1% for delayed possession and directing the transfer of pre-deposited funds to U.P. RERA for execution. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest at MCLR+1% for delayed possession and directing the transfer of pre-deposited funds to U.P. RERA for execution.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Interest Period
from 30.01.2017 till offer of possession along with OC/CC
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Rajesh Chadha
Respondent Advocate(s)
- Abhishek Khare
Official RERA Tribunal Orders (4)
The Tribunal heard arguments regarding an appeal by Greater Noida Industrial Development Authority against a RERA order directing the grant of interest for delayed possession and the delivery of a unit by 31.01.2020; judgment has been reserved.
The Tribunal condoned the delay in filing the appeal subject to a cost of Rs. 1000/- and directed the appellant to comply with Section 43(5) of the Act before the next hearing.
The Tribunal closed the appellant's opportunity to file a reply to the respondent's objections due to failure to comply with a previous stop order and deadline.
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest at MCLR+1% for delayed possession and directing the transfer of pre-deposited funds to U.P. RERA for execution.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.