Appellant / Complainant
Greater Noida Industrial Development Authority
Respondent
Gorav Khosla
₹25,25,700
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126012992020 by Greater Noida Industrial Development Authority against Gorav Khosla before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the RERA order to refund the respondent's deposited amount with interest at MCLR+1% due to project delays. The Tribunal further directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.
Hearing
The Tribunal heard arguments from the counsel for both parties and reserved the judgment for a later date.
to file objections and its reply
The Tribunal adjourned the matter to 20.05.2022 to allow the appellant's counsel to produce the Occupancy Certificate (OC) or Completion Certificate (CC) for the project in question.
to file objections and its reply
The Tribunal directed the appellant's counsel to re-upload a reply to the respondent's objections into the correct folder and adjourned the matter to 16.05.2022.
Further Order
The Tribunal rejected the respondent's objection to a filing extension and granted the appellant a final 10-day period to file a reply to objections, while directing the immediate deposit of previously imposed costs.
Final Hearing
The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the hearing for March 5, 2022.
Final Hearing
The Tribunal adjourned the matter to 21.01.2022 for consideration of an application for condonation of delay and a subsequent hearing.
Final Hearing
The Tribunal granted the appellant's counsel one week to prepare his brief and rescheduled the final hearing for January 6, 2022.
Hearing
The Tribunal closed the appellant's opportunity to file a reply to the respondent's objections due to failure to comply with previous directions and deadlines.
Hearing
The Tribunal granted the appellant a two-week extension to file a reply to the respondent's objections and scheduled the matter for hearing on 22.10.2021.
Hearing on Appeal
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for 09.04.2021.
For Order
The appeal is adjourned to 16.03.2021 due to a lawyers' strike; the appellant's counsel is directed to file a reply to the respondent's objections via the e-portal in the interim.
For Order
The Tribunal noted the exchange of pleadings and directed that the appellant's reply to objections be uploaded on the e-portal and filed in the Registry before the next hearing. The matter is scheduled for hearing on 26.02.2021.
Tribunal Order #0901126012992020-30-06-2022
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the RERA order to refund the respondent's deposited amount with interest at MCLR+1% due to project delays. The Tribunal further directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.
Tribunal Order #0901126012992020-22-04-2022
The Tribunal rejected the respondent's objection to a filing extension and granted the appellant a final 10-day period to file a reply to objections, while directing the immediate deposit of previously imposed costs.
Tribunal Order #0901126012992020-22-10-2021
The Tribunal closed the appellant's opportunity to file a reply to the respondent's objections due to failure to comply with previous directions and deadlines.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the RERA order to refund the respondent's deposited amount with interest at MCLR+1% due to project delays. The Tribunal further directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the RERA order to refund the respondent's deposited amount with interest at MCLR+1% due to project delays. The Tribunal further directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Interest Period
w.e.f. 30.01.2017
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Rajesh Chadha
Respondent Advocate(s)
- Arvind Kumar Shukla
Official RERA Tribunal Orders (3)
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the RERA order to refund the respondent's deposited amount with interest at MCLR+1% due to project delays. The Tribunal further directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.
The Tribunal rejected the respondent's objection to a filing extension and granted the appellant a final 10-day period to file a reply to objections, while directing the immediate deposit of previously imposed costs.
The Tribunal closed the appellant's opportunity to file a reply to the respondent's objections due to failure to comply with previous directions and deadlines.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.