Appellant / Complainant
Greater Noida Industrial Development Authority
Respondent
Gaurav Agarwal
₹5,18,895
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126012982020 by Greater Noida Industrial Development Authority against Gaurav Agarwal before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the RERA order for delayed possession and interest at MCLR+1%. The Tribunal further directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.
Final Hearing
The Tribunal allowed the appellant's late reply to be taken on record and proceeded to hear arguments regarding the appellant's challenge to a RERA order directing interest payments of MCLR+1%.
Final Hearing
The Tribunal granted an adjournment requested by the respondent's counsel to review the appellant's reply and scheduled the next hearing for August 3, 2022.
Final Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and scheduled the appeal for a hearing on 15.07.2022.
Final Hearing
The Tribunal allowed the application for condonation of delay by imposing a cost of Rs. 3000/- on the appellant and directed the appellant to file a replication before the next hearing date.
Final Hearing
The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the hearing for April 21, 2022.
Final Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to personal difficulty and rescheduled the hearing for consideration of the condonation of delay application to 21.01.2022.
Final Hearing
The Tribunal granted the appellant's counsel one week to prepare his brief and rescheduled the final hearing for January 6, 2022.
Hearing
The Tribunal closed the appellant's opportunity to file a reply to the respondent's objections due to failure to comply with previous directions and deadlines.
Hearing
The Tribunal granted the Appellant a two-week extension to file a reply to the Respondent's objections and scheduled the matter for hearing on 22.10.2021 regarding the application for condonation of delay.
Hearing on Appeal
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for April 9, 2021.
For Order
The appeal is adjourned to 16.03.2021 due to a lawyers' strike, with a directive for the appellant's counsel to file a reply to the respondent's objections via the e-portal.
For Order
The Tribunal granted the appellant two weeks to file a reply to the respondent's objections and directed that the reply be served via email and uploaded to the e-portal before the next hearing on 26.02.2021.
Tribunal Order #0901126012982020-08-09-2022
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the RERA order for delayed possession and interest at MCLR+1%. The Tribunal further directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.
Tribunal Order #0901126012982020-03-08-2022
The Tribunal allowed the appellant's late reply to be taken on record and proceeded to hear arguments regarding the appellant's challenge to a RERA order directing interest payments of MCLR+1%.
Tribunal Order #0901126012982020-21-04-2022
The Tribunal allowed the application for condonation of delay by imposing a cost of Rs. 3000/- on the appellant and directed the appellant to file a replication before the next hearing date.
Tribunal Order #0901126012982020-22-10-2021
The Tribunal closed the appellant's opportunity to file a reply to the respondent's objections due to failure to comply with previous directions and deadlines.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the RERA order for delayed possession and interest at MCLR+1%. The Tribunal further directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the RERA order for delayed possession and interest at MCLR+1%. The Tribunal further directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Interest Period
from 30.01.2017 till the date of offer of possession
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Rajesh Chadha
Respondent Advocate(s)
- Gaurav Agarwal
- Nirmit Srivastav
Official RERA Tribunal Orders (4)
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the RERA order for delayed possession and interest at MCLR+1%. The Tribunal further directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.
The Tribunal allowed the appellant's late reply to be taken on record and proceeded to hear arguments regarding the appellant's challenge to a RERA order directing interest payments of MCLR+1%.
The Tribunal allowed the application for condonation of delay by imposing a cost of Rs. 3000/- on the appellant and directed the appellant to file a replication before the next hearing date.
The Tribunal closed the appellant's opportunity to file a reply to the respondent's objections due to failure to comply with previous directions and deadlines.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.