up_reraStatus: Completed
CASE ID: 0901126012962020

Appellant / Complainant

Geotech Homz Pvt. Ltd.

VS

Respondent

Satya Prakash

Developer Firm

geotech homz pvt. ltd.

Disputed Amount

6,73,222

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

18 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126012962020 by Geotech Homz Pvt. Ltd. against Satya Prakash before up_rera.

2
Stage 128/03/2022

Final Hearing

The Tribunal disposed of the appeal following an out-of-court settlement between M/S Geotech Homz Pvt. Ltd. and the respondents, directing the release of deposited funds totaling Rs. 6,73,222 plus interest to the respondent.

3
Stage 222/03/2022

Final Hearing

The Tribunal granted a short adjournment to allow the parties to attempt an out-of-court settlement and listed the case for hearing on 28.03.2022.

4
Stage 307/03/2022

Final Hearing

The Tribunal heard arguments regarding a dispute over the refund of earnest money and has adjourned the matter to 22.03.2022 to allow the respondent's counsel to seek instructions on a settlement proposal.

5
Stage 405/01/2022

Hearing

The Tribunal adjourned the appeal for one week to allow the appellant to pursue an amicable settlement, with the next hearing scheduled for 24.01.2022.

6
Stage 514/12/2021

Hearing

The Tribunal adjourned the matter to 05.01.2022 to allow the respondent to seek instructions regarding the appellant's offer of payment for an amicable settlement.

7
Stage 626/11/2021

Hearing

The Tribunal granted an adjournment due to the unavailability of the appellant's counsel and directed the appellant to file a reply to the respondent's objections within 10 days.

8
Stage 728/10/2021

Delay condonation

The Tribunal allowed the appellant's application for condonation of delay by applying the Supreme Court's COVID-19 limitation relaxation guidelines and converted the defective appeal into a regular appeal.

9
Stage 828/09/2021

Delay condonation

The Tribunal granted the appellant one week to file a reply to the respondent's objections and directed both parties to exchange documents via email and upload them to the e-portal before the next hearing on 28.10.2021.

10
Stage 915/04/2021

Delay condonation

No text available.

11
Stage 1022/03/2021

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel due to their appearance in the HJS examination and rescheduled the hearing for 15.04.2021.

12
Stage 1104/03/2021

Delay condonation

The case was adjourned to 22.03.2021 due to a lawyer strike, with directions for the parties to exchange pleadings in the interim.

13
Stage 1211/02/2021

For Order

The Tribunal directed the respondent to file objections to the grounds of appeal via email and instructed both parties to upload their respective filings on the e-portal before the next hearing on 04.03.2021.

14
Stage 1318/01/2021

Defect Removal

No text available.

15
Stage 1409/12/2020

Defect Removal

No text available.

16
Stage 15Interim Order

Tribunal Order #0901126012962020-28-10-2021

The Tribunal allowed the appellant's application for condonation of delay by applying the Supreme Court's COVID-19 limitation relaxation guidelines and converted the defective appeal into a regular appeal.

17
Stage 16Final Ruling Order

Tribunal Order #0901126012962020-28-03-2022

The Tribunal disposed of the appeal following an out-of-court settlement between M/S Geotech Homz Pvt. Ltd. and the respondents, directing the release of deposited funds totaling Rs. 6,73,222 plus interest to the respondent.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal disposed of the appeal following an out-of-court settlement between M/S Geotech Homz Pvt. Ltd. and the respondents, directing the release of deposited funds totaling Rs. 6,73,222 plus interest to the respondent. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1%.

Disposal Winner: RespondentInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal disposed of the appeal following an out-of-court settlement between M/S Geotech Homz Pvt. Ltd. and the respondents, directing the release of deposited funds totaling Rs. 6,73,222 plus interest to the respondent.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1%

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Vinay Pandey
  • Prasoon Kumar Anjor

Respondent Advocate(s)

  • Kushagra Dikshit
  • Abhishek Srivastava

Official RERA Tribunal Orders (2)

INTERIM_ORDEROrder ID: 0901126012962020-28-10-2021

The Tribunal allowed the appellant's application for condonation of delay by applying the Supreme Court's COVID-19 limitation relaxation guidelines and converted the defective appeal into a regular appeal.

FINAL_ORDEROrder ID: 0901126012962020-28-03-2022

The Tribunal disposed of the appeal following an out-of-court settlement between M/S Geotech Homz Pvt. Ltd. and the respondents, directing the release of deposited funds totaling Rs. 6,73,222 plus interest to the respondent.

TathyaGrid RERA Intelligence AI

Need to research all rulings for geotech homz pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →