up_reraStatus: Completed
CASE ID: 0901126012892020

Appellant / Complainant

Hawelia Builders Pvt. Ltd.

VS

Respondent

Ranjeet Prasad, Anr.

Developer Firm

hawelia builders pvt. ltd.

Disputed Amount

42,36,750

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

33 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126012892020 by Hawelia Builders Pvt. Ltd. against Ranjeet Prasad, Anr. before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer
2
Stage 130/05/2023

for delivery of Judgment/Order

The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeals filed by Hawelia Builders Pvt. Ltd., upholding the Regulatory Authority's orders for delayed possession and interest (MCLR+1%) and directing the transfer of pre-deposited funds to UPRERA for distribution to the allottees.

3
Stage 217/02/2023

Part Heard

The Tribunal heard arguments from the counsel for both parties and reserved the judgment for a later date.

4
Stage 317/01/2023

Part Heard

No text available.

5
Stage 408/12/2022

Part Heard

The Tribunal adjourned the matter due to lack of time and scheduled the next hearing for January 17, 2023.

6
Stage 514/11/2022

Part Heard

No text available.

7
Stage 618/10/2022

Part Heard

The Tribunal outlines terms for a potential settlement regarding interest payments, directing the parties to calculate interest based on the temporary OC date and possession delays, while noting that the respondent will not pay interest on balance amounts during litigation.

8
Stage 714/09/2022

Part Heard

The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the hearing for 18.10.2022.

9
Stage 830/08/2022

Part Heard

The parties expressed an intent to settle the dispute, with specific terms regarding the Temporary Occupancy Certificate (TOC) as the cutoff date for interest calculation. The Tribunal directed both parties to file a settlement deed and appear on the next scheduled date.

10
Stage 917/08/2022

Hearing

The Tribunal noted the ongoing arguments and directed both the appellant's authorized signatory and the respondent to appear in person on the next hearing date of 30.08.2022.

11
Stage 1022/07/2022

Extension of Time

The Tribunal ordered that the appeal be listed before Bench No. 2 for further hearing on August 17, 2022.

12
Stage 1112/05/2022

Final Hearing

The Tribunal noted that parties are negotiating an out-of-court settlement and directed both counsels to exchange and file written arguments at least seven days before the next hearing on 22.07.2022.

13
Stage 1229/03/2022

Final Hearing

The Tribunal condoned the 116-day delay in filing the appeal, citing the Supreme Court's relaxation of limitation periods due to the COVID-19 pandemic, and directed the registry to register the matter as a regular appeal.

14
Stage 1314/03/2022

Final Hearing

No text available.

15
Stage 1410/01/2022

Final Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to a colleague's illness and rescheduled the final hearing for 01.02.2022.

16
Stage 1507/12/2021

Final Hearing

The Tribunal directed the appellant to address potential deficiencies regarding compliance with Section 43(5) of the Act concerning the deposit amount required up to the issuance of the Occupancy Certificate (OC).

17
Stage 1629/11/2021

Final Hearing

The Tribunal has adjourned the matter to 07.12.2021 for consideration of the application for condonation of delay and subsequent hearing, following a joint request from both parties' counsels.

18
Stage 1712/11/2021

Final Hearing

The Tribunal noted that pleadings have been exchanged and adjourned the matter to 29.11.2021 for further proceedings.

19
Stage 1810/11/2021

Final Hearing

No text available.

20
Stage 1907/10/2021

Delay condonation

The Tribunal granted an adjournment requested by the applicant's counsel due to illness and scheduled the case for a final hearing on 10.11.2021.

21
Stage 2022/04/2021

Delay condonation

No text available.

22
Stage 2105/04/2021

Delay condonation

No text available.

23
Stage 2215/03/2021

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the defective appeal for hearing on 05.04.2021.

24
Stage 2319/02/2021

Compliance of section 43(5)

No text available.

25
Stage 2405/02/2021

For Order

The Tribunal granted the appellant one week to file a reply to the respondents' objections and scheduled the matter for 19.02.2021 to consider the application for condonation of delay.

26
Stage 2520/01/2021

Hearing

No text available.

27
Stage 2608/12/2020

Hearing

No text available.

28
Stage 27Final Ruling Order

Tribunal Order #0901126012892020-30-05-2023

The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeals filed by Hawelia Builders Pvt. Ltd., upholding the Regulatory Authority's orders for delayed possession and interest (MCLR+1%) and directing the transfer of pre-deposited funds to UPRERA for distribution to the allottees.

29
Stage 28Interim Order

Tribunal Order #0901126012892020-29-03-2022

The Tribunal condoned the 116-day delay in filing the appeal, citing the Supreme Court's relaxation of limitation periods due to the COVID-19 pandemic, and directed the registry to register the matter as a regular appeal.

30
Stage 29Interim Order

Tribunal Order #0901126012892020-18-10-2022

The Tribunal outlines terms for a potential settlement regarding interest payments, directing the parties to calculate interest based on the temporary OC date and possession delays, while noting that the respondent will not pay interest on balance amounts during litigation.

31
Stage 30Interim Order

Tribunal Order #0901126012892020-30-08-2022

The parties expressed an intent to settle the dispute, with specific terms regarding the Temporary Occupancy Certificate (TOC) as the cutoff date for interest calculation. The Tribunal directed both parties to file a settlement deed and appear on the next scheduled date.

32
Stage 31Interim Order

Tribunal Order #0901126012892020-07-12-2021

The Tribunal directed the appellant to address potential deficiencies regarding compliance with Section 43(5) of the Act concerning the deposit amount required up to the issuance of the Occupancy Certificate (OC).

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeals filed by Hawelia Builders Pvt. Ltd., upholding the Regulatory Authority's orders for delayed possession and interest (MCLR+1%) and directing the transfer of pre-deposited funds to UPRERA for distribution to the allottees. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1%.

Disposal Winner: RespondentInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeals filed by Hawelia Builders Pvt. Ltd., upholding the Regulatory Authority's orders for delayed possession and interest (MCLR+1%) and directing the transfer of pre-deposited funds to UPRERA for distribution to the allottees.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1%

Interest Period

from 29.08.2017 till receipt of OC/CC or offer of possession, whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Tushar Bahadur

Respondent Advocate(s)

  • Yash Tandon
  • Nirmit Srivastav

Official RERA Tribunal Orders (5)

FINAL_ORDEROrder ID: 0901126012892020-30-05-2023

The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeals filed by Hawelia Builders Pvt. Ltd., upholding the Regulatory Authority's orders for delayed possession and interest (MCLR+1%) and directing the transfer of pre-deposited funds to UPRERA for distribution to the allottees.

INTERIM_ORDEROrder ID: 0901126012892020-29-03-2022

The Tribunal condoned the 116-day delay in filing the appeal, citing the Supreme Court's relaxation of limitation periods due to the COVID-19 pandemic, and directed the registry to register the matter as a regular appeal.

INTERIM_ORDEROrder ID: 0901126012892020-18-10-2022

The Tribunal outlines terms for a potential settlement regarding interest payments, directing the parties to calculate interest based on the temporary OC date and possession delays, while noting that the respondent will not pay interest on balance amounts during litigation.

INTERIM_ORDEROrder ID: 0901126012892020-30-08-2022

The parties expressed an intent to settle the dispute, with specific terms regarding the Temporary Occupancy Certificate (TOC) as the cutoff date for interest calculation. The Tribunal directed both parties to file a settlement deed and appear on the next scheduled date.

INTERIM_ORDEROrder ID: 0901126012892020-07-12-2021

The Tribunal directed the appellant to address potential deficiencies regarding compliance with Section 43(5) of the Act concerning the deposit amount required up to the issuance of the Occupancy Certificate (OC).

TathyaGrid RERA Intelligence AI

Need to research all rulings for hawelia builders pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →