CASE ID: 0901126012862020

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Prem Kumari Srivastava

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

16 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126012862020 by Lucknow Development Authority against Prem Kumari Srivastava before up_rera.

2
Stage 117/11/2022

for delivery of Judgment/Order

The U.P. Real Estate Appellate Tribunal dismissed a consolidated batch of 25 appeals filed by the Lucknow Development Authority, upholding the Adjudicating Officer's order to pay interest/compensation to allottees for project delays and directing the transfer of pre-deposited amounts to the Regulatory Authority.

3
Stage 229/10/2021

Further Order

The U.P. Real Estate Appellate Tribunal heard arguments in the matter of Lucknow Development Authority vs. Prem Kumari Srivastava and subsequently reserved the judgment.

4
Stage 322/10/2021

Delay condonation

The Tribunal allowed the application for condonation of delay, citing Supreme Court guidelines regarding the COVID-19 pandemic, and directed the registry to register the miscellaneous case as a regular appeal.

5
Stage 416/09/2021

Delay condonation

The Tribunal adjourned the case to 22.10.2021 due to the absence of counsel caused by heavy rain and directed parties to exchange pleadings and file originals in the Registry prior to the next hearing.

6
Stage 530/04/2021

Delay condonation

No text available.

7
Stage 607/04/2021

Delay condonation

No text available.

8
Stage 717/03/2021

Defect Removal

The Tribunal granted a request from the counsel for both parties to adjourn the case and rescheduled the hearing for 07.04.2021.

9
Stage 825/02/2021

For Order

The case was adjourned because advocates were abstaining from work due to a call by the Oudh Bar Association; the matter is rescheduled for 17.03.2021.

10
Stage 910/02/2021

For Order

The Tribunal noted the respondent's medical condition and directed that she be informed to file objections if desired, with future hearings to be conducted via video conferencing; the matter is adjourned to 24.03.2021.

11
Stage 1025/01/2021

For Order

The Tribunal granted the applicant one week's time to file a better affidavit regarding the application for condonation of delay and scheduled the next hearing for 10.02.2021.

12
Stage 1105/01/2021

Hearing

No text available.

13
Stage 1215/12/2020

Hearing

No text available.

14
Stage 13Final Ruling Order

Tribunal Order #0901126012862020-17-11-2022

The U.P. Real Estate Appellate Tribunal dismissed a consolidated batch of 25 appeals filed by the Lucknow Development Authority, upholding the Adjudicating Officer's order to pay interest/compensation to allottees for project delays and directing the transfer of pre-deposited amounts to the Regulatory Authority.

15
Stage 14Interim Order

Tribunal Order #0901126012862020-22-10-2021

The Tribunal allowed the application for condonation of delay, citing Supreme Court guidelines regarding the COVID-19 pandemic, and directed the registry to register the miscellaneous case as a regular appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed a consolidated batch of 25 appeals filed by the Lucknow Development Authority, upholding the Adjudicating Officer's order to pay interest/compensation to allottees for project delays and directing the transfer of pre-deposited amounts to the Regulatory Authority.

Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed a consolidated batch of 25 appeals filed by the Lucknow Development Authority, upholding the Adjudicating Officer's order to pay interest/compensation to allottees for project delays and directing the transfer of pre-deposited amounts to the Regulatory Authority.

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Yadav

Respondent Advocate(s)

  • Anshul Baranwal

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126012862020-17-11-2022

The U.P. Real Estate Appellate Tribunal dismissed a consolidated batch of 25 appeals filed by the Lucknow Development Authority, upholding the Adjudicating Officer's order to pay interest/compensation to allottees for project delays and directing the transfer of pre-deposited amounts to the Regulatory Authority.

INTERIM_ORDEROrder ID: 0901126012862020-22-10-2021

The Tribunal allowed the application for condonation of delay, citing Supreme Court guidelines regarding the COVID-19 pandemic, and directed the registry to register the miscellaneous case as a regular appeal.