up_reraStatus: Completed
CASE ID: 0901126012812024

Appellant / Complainant

Gaursons Realtech Private Limited

VS

Respondent

Atul Kumar Singh

Developer Firm

gaursons realtech private limited

Disputed Amount

35,21,116

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Refund of InvestmentNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

10 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126012812024 by Gaursons Realtech Private Limited against Atul Kumar Singh before up_rera.

Refund of InvestmentNon-Compliance & Execution
2
Stage 120/05/2025

Delay condonation

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 523-day delay, dismissed the appeal, and directed the transfer of the amount deposited by the promoter to UP RERA for release to the respondent allottee.

3
Stage 228/04/2025

Delay condonation

The Tribunal ordered that recovery proceedings for the Recovery Certificate be kept in abeyance, while scheduling the appeal for consideration of the condonation of delay on 20.05.2025.

4
Stage 301/04/2025

Delay condonation

The Tribunal has adjourned the appeal to 28.04.2025 following a joint request from the learned counsel for both parties.

5
Stage 405/03/2025

Delay condonation

The Tribunal directed the respondent to file objections to the delay condonation application and the memo of appeal within 10 days, with a subsequent rejoinder allowed within one week, and scheduled the next hearing for April 1, 2025.

6
Stage 507/02/2025

Delay condonation

The Tribunal has granted a request to list the appeal for orders or hearing on March 5, 2025.

7
Stage 606/01/2025

Delay condonation

The Tribunal issued notice to the respondent regarding the application for condonation of delay and directed the appellant to serve the notice and appeal documents via post and email, with the matter listed for hearing on 07.02.2025.

8
Stage 7Final Ruling Order

Tribunal Order #0901126012812024-20-05-2025

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 523-day delay, dismissed the appeal, and directed the transfer of the amount deposited by the promoter to UP RERA for release to the respondent allottee.

9
Stage 8Interim Order

Tribunal Order #0901126012812024-28-04-2025

The Tribunal ordered that recovery proceedings for the Recovery Certificate be kept in abeyance, while scheduling the appeal for consideration of the condonation of delay on 20.05.2025.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 523-day delay, dismissed the appeal, and directed the transfer of the amount deposited by the promoter to UP RERA for release to the respondent allottee. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 523-day delay, dismissed the appeal, and directed the transfer of the amount deposited by the promoter to UP RERA for release to the respondent allottee.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Samrat Vaish

Respondent Advocate(s)

  • Rishindra Vikram Singh

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126012812024-20-05-2025

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 523-day delay, dismissed the appeal, and directed the transfer of the amount deposited by the promoter to UP RERA for release to the respondent allottee.

INTERIM_ORDEROrder ID: 0901126012812024-28-04-2025

The Tribunal ordered that recovery proceedings for the Recovery Certificate be kept in abeyance, while scheduling the appeal for consideration of the condonation of delay on 20.05.2025.

TathyaGrid RERA Intelligence AI

Need to research all rulings for gaursons realtech private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →