Appellant / Complainant
Greater Noida Industrial Development Authority
Respondent
Kamal Singh
₹25,25,700
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126012672020 by Greater Noida Industrial Development Authority against Kamal Singh before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal dismissed the appeals filed by the Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order for interest payments due to project delays and directing the transfer of the promoter's pre-deposited funds to U.P. RERA for disbursement to the allottees.
Hearing
The Tribunal heard arguments regarding an appeal by GNIDA against a Regulatory Authority order that mandated possession and interest payments to the respondent; however, the judgment has been reserved.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to travel difficulties and rescheduled the hearing for 04.07.2023, with a strict directive that no further adjournments will be permitted.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to medical exigency and directed the respondent to file objections in the proper folder within one week, scheduling the hearing for 22.03.2023.
Final Hearing
This text represents the header information of an appeal (APPEAL-332/2020) before the U.P. Real Estate Appellate Tribunal, listing the parties and counsel involved, but contains no substantive ruling or directive.
Final Hearing
The Tribunal granted a request from both parties' counsels to reschedule the hearing of Appeal-332/2020 to 20.12.2022.
Hearing
The Tribunal granted the appellant a final opportunity to file a replication/rejoinder and scheduled the next hearing for September 15, 2022.
Hearing
The Tribunal directed the appellant to file a replication/rejoinder against the respondent's reply and scheduled the case for hearing on 18.08.2022.
Hearing
The Tribunal noted that the respondent has not filed a reply to the appeal and scheduled the matter for hearing on 08.07.2022.
Hearing
The Tribunal directed the respondent to file a reply to the grounds of appeal via email and scheduled the case for hearing on 28.04.2022.
Delay condonation
The Tribunal ruled that there was no delay in filing the appeal based on the web upload date and directed the Registry to convert the defective appeal into a regular appeal following the appellant's compliance with Section 43(5) deposit requirements.
Delay condonation
The Tribunal granted an adjournment requested by the applicant and rescheduled the case to 12.01.2022 to consider the application for condonation of delay and its objections.
Delay condonation
The Tribunal adjourned the matter to 21.12.2021 for the disposal of a limitation application and its objection, noting that while notice was served on the respondent, no one appeared on their behalf.
Delay condonation
The Tribunal granted an adjournment requested by the parties and scheduled the case for 24.11.2021 to address the limitation application and objections.
Delay condonation
The Tribunal directed the parties to exchange pleadings and file originals with the Registry at least one week before the next hearing date, which is scheduled for 26.10.2021.
For Order
The Tribunal adjourned the defective appeal due to an advocate strike by the Oudh Bar Association and directed the parties to exchange pleadings before the next hearing on 16.03.2021.
Tribunal Order #0901126012672020-22-02-2022
The Tribunal ruled that there was no delay in filing the appeal based on the web upload date and directed the Registry to convert the defective appeal into a regular appeal following the appellant's compliance with Section 43(5) deposit requirements.
Tribunal Order #0901126012672020-17-07-2023
The Appellate Tribunal dismissed the appeals filed by the Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order for interest payments due to project delays and directing the transfer of the promoter's pre-deposited funds to U.P. RERA for disbursement to the allottees.
Tribunal Order #0901126012672020-04-07-2023
The Tribunal heard arguments regarding an appeal by GNIDA against a Regulatory Authority order that mandated possession and interest payments to the respondent; however, the judgment has been reserved.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal dismissed the appeals filed by the Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order for interest payments due to project delays and directing the transfer of the promoter's pre-deposited funds to U.P. RERA for disbursement to the allottees. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal dismissed the appeals filed by the Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order for interest payments due to project delays and directing the transfer of the promoter's pre-deposited funds to U.P. RERA for disbursement to the allottees.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Interest Period
from 30.01.2017 till the date of offer of possession i.e. 21.06.2019
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Ajay Kumar Gupta
- Rishindra Vikram Singh
Respondent Advocate(s)
- Ankit Raj Chaudhary
Official RERA Tribunal Orders (3)
The Tribunal ruled that there was no delay in filing the appeal based on the web upload date and directed the Registry to convert the defective appeal into a regular appeal following the appellant's compliance with Section 43(5) deposit requirements.
The Appellate Tribunal dismissed the appeals filed by the Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order for interest payments due to project delays and directing the transfer of the promoter's pre-deposited funds to U.P. RERA for disbursement to the allottees.
The Tribunal heard arguments regarding an appeal by GNIDA against a Regulatory Authority order that mandated possession and interest payments to the respondent; however, the judgment has been reserved.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.