Appellant / Complainant
Alto Project & Engineering Pvt. Ltd.
Respondent
Tyagi Construction Company, Others
alto project & engineering pvt. ltd.
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126012662020 by Alto Project & Engineering Pvt. Ltd. against Tyagi Construction Company, Others before up_rera.
to file objections and its reply
The appeal is dismissed by reference to a prior order dated 12.04.2022 passed in Appeal No. 526/2020 (Ashoka Sharma Vs. M/s Tyagi Construction Company & Ors.).
to file objections and its reply
The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and rescheduled the appeal hearing for April 12, 2022.
Further Order
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the appeal for hearing on 22.03.2022.
Further Order
The Tribunal granted an adjournment request and directed the applicant to appear in person, while also ordering the respondent partner, Mr. Vijay Kumar Tyagi, to appear at the next hearing to facilitate an amicable settlement.
Hearing
The Tribunal directed the parties to attempt an out-of-court settlement regarding disputed payments and scheduled the matter for further orders on 28.10.2021.
Hearing
The Tribunal noted an application for compromise filed by the parties, but the applicant's representative alleged that the signatures and photograph on the settlement papers were forged. The matter is adjourned to 29.09.2021 for further orders.
Hearing
The Tribunal granted an adjournment request from the appellant's counsel due to her being out of station and rescheduled the matter for April 8, 2021.
Further Hearing
The Tribunal noted the respondent's claim of a settlement and, following the appellant's request for verification, adjourned the matter to 12.03.2021.
Tribunal Order #0901126012662020-28-10-2021
The Tribunal granted an adjournment request and directed the applicant to appear in person, while also ordering the respondent partner, Mr. Vijay Kumar Tyagi, to appear at the next hearing to facilitate an amicable settlement.
Tribunal Disposal & Final Award Ruling
Dismissed Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Dismissed
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Prashant Kumar
- Fuhar Gupta
Respondent Advocate(s)
- Sanjay Kumar Srivastava
Official RERA Tribunal Orders (1)
The Tribunal granted an adjournment request and directed the applicant to appear in person, while also ordering the respondent partner, Mr. Vijay Kumar Tyagi, to appear at the next hearing to facilitate an amicable settlement.
Need to research all rulings for alto project & engineering pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.