up_reraStatus: Completed
CASE ID: 0901126012562020

Appellant / Complainant

Nandi Infratech Pvt. Ltd.

VS

Respondent

Anshu Tyagi

Developer Firm

nandi infratech pvt. ltd.

Disputed Amount

3,14,179

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferMaintenance & Utility Disputes

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

17 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126012562020 by Nandi Infratech Pvt. Ltd. against Anshu Tyagi before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferMaintenance & Utility Disputes
2
Stage 130/06/2022

for delivery of Judgment/Order

The Appellate Tribunal dismissed the appeal filed by M/s Nandi Infratech Pvt. Ltd., upholding the RERA order that directs the promoter to provide possession of the flat and pay delay interest at MCLR+1% to the respondent, while also directing the transfer of pre-deposited funds to U.P. RERA for disbursement.

3
Stage 218/05/2022

Hearing

The Tribunal heard arguments regarding an appeal by M/S Nandi Infratech Pvt. Ltd. against a RERA order concerning possession delays and interest liability; however, the judgment has been reserved.

4
Stage 323/11/2021

Final Hearing

The Tribunal heard arguments from the counsel for both parties and reserved the judgment for a later date.

5
Stage 429/10/2021

Hearing

The Tribunal allowed the appellant's application to amend the prayer clause to specifically challenge the rate of interest. The appellant was also directed to file a certificate regarding compliance with Section 43(5) of the Act.

6
Stage 529/09/2021

Hearing

The Tribunal granted the appellant's request for an adjournment to allow time to file an application for amending the prayer clause and rescheduled the hearing to 29.10.2021.

7
Stage 623/09/2021

Hearing

Upon the joint request of the counsels for both parties, the Tribunal has adjourned the appeal and scheduled it for hearing on 29.09.2021.

8
Stage 712/04/2021

Hearing

No text available.

9
Stage 812/03/2021

Hearing

The Tribunal rejected the respondent's counsel's request for adjournment based on a complaint regarding his name not appearing in the cause list and scheduled the appeal for hearing on 12.04.2021.

10
Stage 919/02/2021

For Order

The Tribunal scheduled the appeal for a hearing on 12.03.2021 and directed both parties to file a list of dates, events, and relied-upon judgments at least three days prior to the next listing.

11
Stage 1025/01/2021

For Order

The Tribunal granted a request for adjournment due to the respondent's counsel's illness and rescheduled the appeal for hearing on 19.02.2021.

12
Stage 1106/01/2021

Compliance of section 43(5)

No text available.

13
Stage 1203/12/2020

Compliance of section 43(5)

No text available.

14
Stage 13Final Ruling Order

Tribunal Order #0901126012562020-30-06-2022

The Appellate Tribunal dismissed the appeal filed by M/s Nandi Infratech Pvt. Ltd., upholding the RERA order that directs the promoter to provide possession of the flat and pay delay interest at MCLR+1% to the respondent, while also directing the transfer of pre-deposited funds to U.P. RERA for disbursement.

15
Stage 14Interim Order

Tribunal Order #0901126012562020-18-05-2022

The Tribunal heard arguments regarding an appeal by M/S Nandi Infratech Pvt. Ltd. against a RERA order concerning possession delays and interest liability; however, the judgment has been reserved.

16
Stage 15Interim Order

Tribunal Order #0901126012562020-29-10-2021

The Tribunal allowed the appellant's application to amend the prayer clause to specifically challenge the rate of interest. The appellant was also directed to file a certificate regarding compliance with Section 43(5) of the Act.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal dismissed the appeal filed by M/s Nandi Infratech Pvt. Ltd., upholding the RERA order that directs the promoter to provide possession of the flat and pay delay interest at MCLR+1% to the respondent, while also directing the transfer of pre-deposited funds to U.P. RERA for disbursement. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal dismissed the appeal filed by M/s Nandi Infratech Pvt. Ltd., upholding the RERA order that directs the promoter to provide possession of the flat and pay delay interest at MCLR+1% to the respondent, while also directing the transfer of pre-deposited funds to U.P. RERA for disbursement.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 05.12.2018 till the date of getting OC/CC or offer of possession, whichever is later (excluding the period from 24.03.2020 to 30.09.2020)

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 11(4)(d)Section 19(6)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Vikram Sonal Singh
  • Dushyant Singh

Respondent Advocate(s)

  • Vinay Pandey
  • Harish Pandey

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126012562020-30-06-2022

The Appellate Tribunal dismissed the appeal filed by M/s Nandi Infratech Pvt. Ltd., upholding the RERA order that directs the promoter to provide possession of the flat and pay delay interest at MCLR+1% to the respondent, while also directing the transfer of pre-deposited funds to U.P. RERA for disbursement.

INTERIM_ORDEROrder ID: 0901126012562020-18-05-2022

The Tribunal heard arguments regarding an appeal by M/S Nandi Infratech Pvt. Ltd. against a RERA order concerning possession delays and interest liability; however, the judgment has been reserved.

INTERIM_ORDEROrder ID: 0901126012562020-29-10-2021

The Tribunal allowed the appellant's application to amend the prayer clause to specifically challenge the rate of interest. The appellant was also directed to file a certificate regarding compliance with Section 43(5) of the Act.