Appellant / Complainant
Nandi Infratech Pvt. Ltd.
Respondent
Anshu Tyagi
nandi infratech pvt. ltd.
₹3,14,179
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126012562020 by Nandi Infratech Pvt. Ltd. against Anshu Tyagi before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal dismissed the appeal filed by M/s Nandi Infratech Pvt. Ltd., upholding the RERA order that directs the promoter to provide possession of the flat and pay delay interest at MCLR+1% to the respondent, while also directing the transfer of pre-deposited funds to U.P. RERA for disbursement.
Hearing
The Tribunal heard arguments regarding an appeal by M/S Nandi Infratech Pvt. Ltd. against a RERA order concerning possession delays and interest liability; however, the judgment has been reserved.
Final Hearing
The Tribunal heard arguments from the counsel for both parties and reserved the judgment for a later date.
Hearing
The Tribunal allowed the appellant's application to amend the prayer clause to specifically challenge the rate of interest. The appellant was also directed to file a certificate regarding compliance with Section 43(5) of the Act.
Hearing
The Tribunal granted the appellant's request for an adjournment to allow time to file an application for amending the prayer clause and rescheduled the hearing to 29.10.2021.
Hearing
Upon the joint request of the counsels for both parties, the Tribunal has adjourned the appeal and scheduled it for hearing on 29.09.2021.
Hearing
The Tribunal rejected the respondent's counsel's request for adjournment based on a complaint regarding his name not appearing in the cause list and scheduled the appeal for hearing on 12.04.2021.
For Order
The Tribunal scheduled the appeal for a hearing on 12.03.2021 and directed both parties to file a list of dates, events, and relied-upon judgments at least three days prior to the next listing.
For Order
The Tribunal granted a request for adjournment due to the respondent's counsel's illness and rescheduled the appeal for hearing on 19.02.2021.
Tribunal Order #0901126012562020-30-06-2022
The Appellate Tribunal dismissed the appeal filed by M/s Nandi Infratech Pvt. Ltd., upholding the RERA order that directs the promoter to provide possession of the flat and pay delay interest at MCLR+1% to the respondent, while also directing the transfer of pre-deposited funds to U.P. RERA for disbursement.
Tribunal Order #0901126012562020-18-05-2022
The Tribunal heard arguments regarding an appeal by M/S Nandi Infratech Pvt. Ltd. against a RERA order concerning possession delays and interest liability; however, the judgment has been reserved.
Tribunal Order #0901126012562020-29-10-2021
The Tribunal allowed the appellant's application to amend the prayer clause to specifically challenge the rate of interest. The appellant was also directed to file a certificate regarding compliance with Section 43(5) of the Act.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal dismissed the appeal filed by M/s Nandi Infratech Pvt. Ltd., upholding the RERA order that directs the promoter to provide possession of the flat and pay delay interest at MCLR+1% to the respondent, while also directing the transfer of pre-deposited funds to U.P. RERA for disbursement. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal dismissed the appeal filed by M/s Nandi Infratech Pvt. Ltd., upholding the RERA order that directs the promoter to provide possession of the flat and pay delay interest at MCLR+1% to the respondent, while also directing the transfer of pre-deposited funds to U.P. RERA for disbursement.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Interest Period
from 05.12.2018 till the date of getting OC/CC or offer of possession, whichever is later (excluding the period from 24.03.2020 to 30.09.2020)
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Vikram Sonal Singh
- Dushyant Singh
Respondent Advocate(s)
- Vinay Pandey
- Harish Pandey
Official RERA Tribunal Orders (3)
The Appellate Tribunal dismissed the appeal filed by M/s Nandi Infratech Pvt. Ltd., upholding the RERA order that directs the promoter to provide possession of the flat and pay delay interest at MCLR+1% to the respondent, while also directing the transfer of pre-deposited funds to U.P. RERA for disbursement.
The Tribunal heard arguments regarding an appeal by M/S Nandi Infratech Pvt. Ltd. against a RERA order concerning possession delays and interest liability; however, the judgment has been reserved.
The Tribunal allowed the appellant's application to amend the prayer clause to specifically challenge the rate of interest. The appellant was also directed to file a certificate regarding compliance with Section 43(5) of the Act.
Need to research all rulings for nandi infratech pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.