Appellant / Complainant
Anupam Gupta
Respondent
Lucknow Development Authority
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126012372020 by Anupam Gupta against Lucknow Development Authority before up_rera.
for delivery of Judgment/Order
The Tribunal allowed the appeals of several allottees and modified the impugned order to grant interest/compensation for the entire delayed period (12.01.2012 to 08.01.2019), ruling that farmer agitation and construction disputes do not constitute 'force majeure'.
Further Order
The Tribunal directed both parties to exchange lists of dates, events, and relied-upon case law within 15 days and reserved the judgment.
Hearing
The Tribunal has rescheduled the hearing for Appeal-291/2020 to 15.11.2021 due to the respondent's counsel being on sanctioned leave.
For Order
The Tribunal condoned the delay in filing the appeal by applying the Supreme Court's directions regarding the COVID-19 limitation extension and directed the Registry to convert the defective appeal into a Regular Appeal.
Delay condonation
The Tribunal has scheduled the defective appeal for consideration on March 25, 2021, specifically regarding an application for condonation of delay.
For Order
The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the case for March 3, 2021, to consider the application for condonation of delay.
For Order
The Tribunal directed the registry to update the counsel's name for the applicants and scheduled the matter for 12.02.2021 to consider an application for condonation of delay.
Tribunal Order #0901126012372020-28-09-2022
The Tribunal allowed the appeals of several allottees and modified the impugned order to grant interest/compensation for the entire delayed period (12.01.2012 to 08.01.2019), ruling that farmer agitation and construction disputes do not constitute 'force majeure'.
Tribunal Order #0901126012372020-25-03-2021
The Tribunal condoned the delay in filing the appeal by applying the Supreme Court's directions regarding the COVID-19 limitation extension and directed the Registry to convert the defective appeal into a Regular Appeal.
Tribunal Disposal & Final Award Ruling
The Tribunal allowed the appeals of several allottees and modified the impugned order to grant interest/compensation for the entire delayed period (12.01.2012 to 08.01.2019), ruling that farmer agitation and construction disputes do not constitute 'force majeure'. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal allowed the appeals of several allottees and modified the impugned order to grant interest/compensation for the entire delayed period (12.01.2012 to 08.01.2019), ruling that farmer agitation and construction disputes do not constitute 'force majeure'.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR+1%
Interest Period
from 12.01.2012 to 08.01.2019
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Atul Tripathi
- Vikas Kumar Verma
Respondent Advocate(s)
- Amit Yadav
Official RERA Tribunal Orders (2)
The Tribunal allowed the appeals of several allottees and modified the impugned order to grant interest/compensation for the entire delayed period (12.01.2012 to 08.01.2019), ruling that farmer agitation and construction disputes do not constitute 'force majeure'.
The Tribunal condoned the delay in filing the appeal by applying the Supreme Court's directions regarding the COVID-19 limitation extension and directed the Registry to convert the defective appeal into a Regular Appeal.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.