Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

25 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126012362021 by Awdhesh Kumar Agarwal against Ansal Properties And Infrastructure Limited, Kiara Lifespaces Pvt Ltd before up_rera.

2
Stage 103/03/2023

Further Order

The appellant requested to withdraw the appeal, and upon the respondent's lack of objection, the U.P. Real Estate Appellate Tribunal dismissed the appeal as withdrawn.

3
Stage 201/02/2023

Further Order

No text available.

4
Stage 316/12/2022

Further Order

The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the appeal for hearing on 01.02.2023.

5
Stage 423/11/2022

Hearing

The Tribunal granted an adjournment application filed by the counsel for Respondent No. 2 and rescheduled the hearing for December 16, 2022.

6
Stage 501/11/2022

Hearing

The Tribunal granted a request for adjournment made by the respondent's counsel and rescheduled the case for 23.11.2022.

7
Stage 627/09/2022

Hearing

The Tribunal granted an adjournment request filed by the counsel for respondent No. 2 and rescheduled the hearing for November 1, 2022.

8
Stage 729/08/2022

Hearing

No text available.

9
Stage 819/07/2022

Hearing

The Tribunal granted a request from the counsel for both parties for a short date and scheduled the case for hearing on 29.08.2022.

10
Stage 924/05/2022

Hearing

The Tribunal directed respondent no. 2 to file a list of dates and events at least seven days before the next hearing and scheduled the case for hearing on July 19, 2022.

11
Stage 1002/05/2022

Hearing

The Tribunal noted the appellant's filing of a replication/rejoinder on the e-portal and directed that copies be emailed to the respondents. The matter is scheduled for hearing on 24.05.2022.

12
Stage 1125/03/2022

Hearing

The Tribunal directed the appellant to file a replication against the respondents' replies and scheduled the matter for hearing on 02.05.2022.

13
Stage 1207/03/2022

Further Order

The Tribunal granted the appellant two weeks to file a reply to the respondent's objections and directed that the reply be served via email and uploaded to the e-portal before the next hearing on 25.03.2022.

14
Stage 1304/01/2022

Further Order

The Tribunal granted the appellant permission to file a replication/rejoinder to the respondent's reply and adjourned the matter to 24.01.2022.

15
Stage 1429/11/2021

Further Order

The Tribunal noted the filings of the respondents and directed the appellant to file a replication or rejoinder affidavit, if desired, before the next hearing on 04.01.2022.

16
Stage 1508/11/2021

Further Order

The Tribunal directed the respondents to file their replies to the grounds of appeal before the next hearing and ordered the case to be listed on 29.11.2021.

17
Stage 1621/10/2021

Delay condonation

The Tribunal allowed the application for condonation of delay, noting the appellant's age and the COVID-19 pandemic, and directed the Registry to convert the defective appeal into a regular appeal.

18
Stage 1717/09/2021

Delay condonation

The Tribunal granted the appellant's request to issue fresh notice to the respondent due to a failure in previous service and set a schedule for the exchange of pleadings via email and speed post.

19
Stage 1823/04/2021

Defect Removal

No text available.

20
Stage 1925/03/2021

Defect Removal

The Tribunal issued notice to the respondent regarding the application for condonation of delay and directed the parties to exchange pleadings via email before the next hearing on 23.04.2021.

21
Stage 2015/03/2021

Defect Removal

The Tribunal directed the Registry to submit a report regarding the removal of defect no. 2 and scheduled the defective appeal for a hearing on 25.03.2021.

22
Stage 2124/02/2021

Defect Removal

The case was adjourned due to a lawyers' strike called by the Oudh Bar Association and is scheduled for a hearing on 15.03.2021.

23
Stage 2217/02/2021

Defect Removal

The Tribunal granted the appellant three days to rectify procedural defects in the appeal and scheduled the matter for a subsequent hearing on 24.02.2021.

24
Stage 23Interim Order

Tribunal Order #0901126012362021-21-10-2021

The Tribunal allowed the application for condonation of delay, noting the appellant's age and the COVID-19 pandemic, and directed the Registry to convert the defective appeal into a regular appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed as withdrawn Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed as withdrawn

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare
  • Aahuti Agarwal

Respondent Advocate(s)

  • Saurabh Misra

Official RERA Tribunal Orders (1)

INTERIM_ORDEROrder ID: 0901126012362021-21-10-2021

The Tribunal allowed the application for condonation of delay, noting the appellant's age and the COVID-19 pandemic, and directed the Registry to convert the defective appeal into a regular appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for ansal properties and infrastructure limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →