up_reraStatus: Completed
CASE ID: 0901126012162020

Appellant / Complainant

Vinod Kumar Upadhyay, Abha

VS

Respondent

Lucknow Development Authority

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestStructural Defects & Quality

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

6 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126012162020 by Vinod Kumar Upadhyay, Abha against Lucknow Development Authority before up_rera.

Delay in PossessionDelay Compensation / InterestStructural Defects & Quality
2
Stage 117/09/2021

for delivery of Judgment/Order

The Tribunal set aside the Regulatory Authority's order and ruled that allottees are entitled to interest at the rate of MCLR + 1% for delayed possession, even after the execution of conveyance deeds and taking possession.

3
Stage 207/01/2021

Final Hearing

No text available.

4
Stage 309/12/2020

Final Hearing

No text available.

5
Stage 4Final Ruling Order

Tribunal Order #0901126012162020-17-09-2021

The Tribunal set aside the Regulatory Authority's order and ruled that allottees are entitled to interest at the rate of MCLR + 1% for delayed possession, even after the execution of conveyance deeds and taking possession.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's order and ruled that allottees are entitled to interest at the rate of MCLR + 1% for delayed possession, even after the execution of conveyance deeds and taking possession. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1 percent.

Disposal Winner: AppellantInterest Rate: MCLR + 1 percentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's order and ruled that allottees are entitled to interest at the rate of MCLR + 1% for delayed possession, even after the execution of conveyance deeds and taking possession.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1 percent

Interest Period

from the promised date of possession to the date of receipt of OC/CC from the competent authority or the actual date of possession whichever is earlier

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 14(3)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Hridesh Srivastava

Respondent Advocate(s)

  • Harish Pandey

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126012162020-17-09-2021

The Tribunal set aside the Regulatory Authority's order and ruled that allottees are entitled to interest at the rate of MCLR + 1% for delayed possession, even after the execution of conveyance deeds and taking possession.