Appellant / Complainant
Yamuna Expressway Industrial Development Authority
Respondent
Gaurav Prasad
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126012072020 by Yamuna Expressway Industrial Development Authority against Gaurav Prasad before up_rera.
Hearing
The appeal was dismissed as 'not pressed' following an amicable settlement between the appellant and respondent. The issue regarding the release of deposited funds remains subject to a future application.
Hearing
The Tribunal granted a request made by the appellant's counsel to adjourn the matter and rescheduled the appeal for hearing on 28.02.2024.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel on health grounds and rescheduled the hearing for 26.02.2024.
Hearing
The Tribunal adjourned the proceedings due to a call by the Bar Council of Uttar Pradesh for lawyers to abstain from judicial work, rescheduling the hearing for 13.10.2023.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to his unavailability but issued a strict warning that no further adjournments will be permitted on the next hearing date.
Hearing
The Tribunal noted the appellant's compliance regarding the payment of Rs. 12,000/- in costs and directed the Registry to verify the deposit of Rs. 6,000/- into the Tribunal's account.
For Order
The Tribunal granted a request for adjournment from both counsels and rescheduled the case for orders/hearing on 10.05.2023.
Hearing
The Tribunal noted the appellant's failure to pay a previously imposed cost of Rs. 12,000 for condoning delay and directed that the issue be examined at the next hearing, while allowing the appellant an opportunity to comply before then.
Hearing
The Tribunal granted the appellant a one-week extension to deposit costs previously imposed for condonation of delay and rescheduled the hearing to 21.02.2023.
Hearing
The Tribunal granted the appellant a one-week extension to comply with the order dated 07.12.2022 regarding the deposit of costs with the Tribunal and payment to the respondent, and adjourned the hearing to 06.02.2023.
for delivery of Judgment/Order
The U.P. Real Estate Appellate Tribunal allowed the appellant's application for condonation of delay, permitting the appeal to be registered subject to a cost of Rs. 12,000 payable to the Tribunal Fund and the respondent.
Delay condonation
The Tribunal heard arguments from both parties and reserved the judgment on the point of limitation.
Delay condonation
The Tribunal granted an adjournment application filed by the counsel for the appellant and rescheduled the case for hearing on 05.01.2022.
Delay condonation
The Tribunal adjourned the case to 24.11.2021 and directed the parties to exchange pleadings and file originals in the Registry at least one week before the next hearing.
Delay condonation
The case was adjourned due to a lawyers' strike, with the matter rescheduled for 02.11.2021 and directions issued for the respondent to file objections to the delay condonation application and grounds of appeal.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel due to a scheduling conflict and directed the appellant to file a reply to the respondent's objections within 10 days.
Delay condonation
The Tribunal granted the applicant two days to file a reply to the respondent's objections and directed that copies be served via email and filed in the Registry before the next hearing on 06.04.2021.
For Order
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the matter for hearing on 12.03.2021.
Delay condonation
The Tribunal granted the appellant two weeks to reply to the respondent's objections and directed both parties to upload their filings on the e-portal before the next hearing on 17.02.2021.
Tribunal Order #0901126012072020-21-02-2023
The Tribunal noted the appellant's failure to pay a previously imposed cost of Rs. 12,000 for condoning delay and directed that the issue be examined at the next hearing, while allowing the appellant an opportunity to comply before then.
Tribunal Order #0901126012072020-09-01-2023
The Tribunal granted the appellant a one-week extension to comply with the order dated 07.12.2022 regarding the deposit of costs with the Tribunal and payment to the respondent, and adjourned the hearing to 06.02.2023.
Tribunal Order #0901126012072020-07-12-2022
The U.P. Real Estate Appellate Tribunal allowed the appellant's application for condonation of delay, permitting the appeal to be registered subject to a cost of Rs. 12,000 payable to the Tribunal Fund and the respondent.
Tribunal Order #0901126012072020-21-07-2023
The Tribunal noted the appellant's compliance regarding the payment of Rs. 12,000/- in costs and directed the Registry to verify the deposit of Rs. 6,000/- into the Tribunal's account.
Tribunal Disposal & Final Award Ruling
Dismissed as not pressed Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Dismissed as not pressed
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Prashant Kumar Singh
Respondent Advocate(s)
- Anilesh Tewari
- Pancham Srivastava
Official RERA Tribunal Orders (4)
The Tribunal noted the appellant's failure to pay a previously imposed cost of Rs. 12,000 for condoning delay and directed that the issue be examined at the next hearing, while allowing the appellant an opportunity to comply before then.
The Tribunal granted the appellant a one-week extension to comply with the order dated 07.12.2022 regarding the deposit of costs with the Tribunal and payment to the respondent, and adjourned the hearing to 06.02.2023.
The U.P. Real Estate Appellate Tribunal allowed the appellant's application for condonation of delay, permitting the appeal to be registered subject to a cost of Rs. 12,000 payable to the Tribunal Fund and the respondent.
The Tribunal noted the appellant's compliance regarding the payment of Rs. 12,000/- in costs and directed the Registry to verify the deposit of Rs. 6,000/- into the Tribunal's account.