up_reraStatus: Completed
CASE ID: 0901126011742022

Appellant / Complainant

Yogita Tripathi, Puneet Tripathi

VS

Respondent

Aims Rg Angel Promoters Private Limited

Developer Firm

aims rg angel promoters private limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

20 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126011742022 by Yogita Tripathi, Puneet Tripathi against Aims Rg Angel Promoters Private Limited before up_rera.

2
Stage 121/09/2023

Delay condonation

The appeal was dismissed by the Tribunal, noting that the decision had already been rendered via an order passed in Appeal No. 53/2022.

3
Stage 220/09/2023

Delay condonation

The Tribunal refers the parties to a previous order passed in Appeal No. D 71/2022 regarding the orders for this matter.

4
Stage 311/08/2023

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel and directed the parties to exchange pleadings before the next hearing on 20.09.2023.

5
Stage 430/05/2023

Delay condonation

The Tribunal has scheduled the case for 11.08.2023 to consider an application for condonation of delay and for a hearing.

6
Stage 528/04/2023

Delay condonation

The Tribunal has listed this defective appeal for orders or hearing on 30.05.2023, referencing a previous order dated 28.04.2023.

7
Stage 620/03/2023

Delay condonation

No text available.

8
Stage 709/02/2023

Delay condonation

No text available.

9
Stage 805/01/2023

Delay condonation

No text available.

10
Stage 905/12/2022

Delay condonation

No text available.

11
Stage 1004/11/2022

Delay condonation

No text available.

12
Stage 1127/09/2022

Delay condonation

No text available.

13
Stage 1207/09/2022

Delay condonation

The Tribunal granted the applicant a 10-day extension to file a reply to the respondent's objections and scheduled the case for hearing on September 27, 2022.

14
Stage 1305/08/2022

Delay condonation

The Tribunal granted the appellant ten days to file a reply to the respondent's objections and scheduled the matter for hearing on September 7, 2022, regarding the application for condonation of delay.

15
Stage 1419/07/2022

Delay condonation

The Tribunal has noted that the appeal is defective and has scheduled it for a subsequent listing on 05.08.2022.

16
Stage 1531/05/2022

Delay condonation

The Tribunal granted the respondent 10 days to file objections regarding the application for condonation of delay and directed the parties to exchange pleadings via email and upload them to the e-portal.

17
Stage 1609/05/2022

Delay condonation

The Tribunal directed the respondent to file objections to the condonation of delay application and grounds of appeal within 10 days, while also instructing the Registry to verify the vakalatnama of the respondent's counsel.

18
Stage 1711/04/2022

Defect Removal

The Tribunal granted the appellant one week to remove registry defects and directed that notice be issued to the respondent for a hearing on May 9, 2022.

19
Stage 18Interim Order

Tribunal Order #0901126011742022-09-05-2022

The Tribunal directed the respondent to file objections to the condonation of delay application and grounds of appeal within 10 days, while also instructing the Registry to verify the vakalatnama of the respondent's counsel.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Prashant Kumar
  • Fuhar Gupta

Respondent Advocate(s)

  • Azhar Ikram
  • Manish Singh

Official RERA Tribunal Orders (1)

INTERIM_ORDEROrder ID: 0901126011742022-09-05-2022

The Tribunal directed the respondent to file objections to the condonation of delay application and grounds of appeal within 10 days, while also instructing the Registry to verify the vakalatnama of the respondent's counsel.

TathyaGrid RERA Intelligence AI

Need to research all rulings for aims rg angel promoters private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →