up_reraStatus: Completed
CASE ID: 0901126011172021

Appellant / Complainant

Avinash Kumar

VS

Respondent

Sunshine Infra Heights Pvt. Ltd.

Developer Firm

sunshine infra heights pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

11 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126011172021 by Avinash Kumar against Sunshine Infra Heights Pvt. Ltd. before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / Interest
2
Stage 126/11/2021

Hearing

The appellant chose to not press the appeal and instead proceed with an application before RERA for a refund as per the original directions in the impugned order; consequently, the appeal was dismissed as not pressed.

3
Stage 208/11/2021

Delay condonation

The Tribunal condoned a 21-day delay in filing the appeal by applying the Supreme Court's COVID-19 limitation extension guidelines and converted the defective appeal into a regular appeal.

4
Stage 321/10/2021

Delay condonation

The Tribunal directed the respondent to file objections to the limitation application and the memo of appeal, scheduling the matter for 08.11.2021.

5
Stage 417/09/2021

Delay condonation

The Tribunal issued fresh notice to the respondent and directed the applicant to serve the application for condonation of delay and memo of appeal via speed post and email.

6
Stage 523/04/2021

Delay condonation

No text available.

7
Stage 608/04/2021

Delay condonation

No text available.

8
Stage 712/03/2021

For Order

The Tribunal granted the appellant one week to take fresh steps for service upon the respondent after a failed postal delivery and scheduled the matter for 08.04.2021.

9
Stage 818/02/2021

Defect Removal

The Tribunal issued notice to the respondent regarding the application for condonation of delay and directed the parties to exchange documents via email and upload objections/replies on the e-portal before the next hearing on 12.03.2021.

10
Stage 9Interim Order

Tribunal Order #0901126011172021-08-11-2021

The Tribunal condoned a 21-day delay in filing the appeal by applying the Supreme Court's COVID-19 limitation extension guidelines and converted the defective appeal into a regular appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed as not pressed Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed as not pressed

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 03.05.2018 till receipt of CC/OC or offer of possession whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Vibhanshu Srivastava

Official RERA Tribunal Orders (1)

INTERIM_ORDEROrder ID: 0901126011172021-08-11-2021

The Tribunal condoned a 21-day delay in filing the appeal by applying the Supreme Court's COVID-19 limitation extension guidelines and converted the defective appeal into a regular appeal.

TathyaGrid RERA Intelligence AI