Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

10 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126011172020 by Bhawana against Imperia Structures Ltd. before up_rera.

2
Stage 123/09/2021

Delay condonation

The defective appeal was dismissed for want of prosecution due to the non-appearance of the appellant and lack of any request for adjournment.

3
Stage 224/08/2021

Delay condonation

The Tribunal granted the appellant one week to provide the necessary envelope and postal stamps for service on the respondent and scheduled the next hearing for 23.09.2021.

4
Stage 323/08/2021

Delay condonation

No text available.

5
Stage 427/07/2021

Defect Removal

The Tribunal issued notice to the respondent regarding the applicant's application for condonation of delay and directed both parties to exchange documents via email and upload objections/replies before the next hearing on 23.08.2021.

6
Stage 512/07/2021

Defect Removal

The Tribunal directed the appellant to file a separate application for condonation of delay and noted that defects in the appeal have not yet been removed. The matter is scheduled for further listing on 27.07.2021.

7
Stage 608/07/2021

Defect Removal

The Tribunal noted procedural deficiencies regarding the missing application for condonation of delay and the lack of a certified copy of the impugned order, permitting the appellant to file these documents and listing the defective appeal for July 12, 2021.

8
Stage 729/06/2021

Defect Removal

The Tribunal noted the appellant's submission regarding the removal of registry defects and directed the Registry to submit a fresh report within three days, listing the matter for 08.07.2021.

9
Stage 8Final Ruling Order

Tribunal Order #0901126011172020-23-09-2021

The defective appeal was dismissed for want of prosecution due to the non-appearance of the appellant and lack of any request for adjournment.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The defective appeal was dismissed for want of prosecution due to the non-appearance of the appellant and lack of any request for adjournment. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The defective appeal was dismissed for want of prosecution due to the non-appearance of the appellant and lack of any request for adjournment.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Bhaavya Roy

Respondent Advocate(s)

  • Amit Yadav

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126011172020-23-09-2021

The defective appeal was dismissed for want of prosecution due to the non-appearance of the appellant and lack of any request for adjournment.

TathyaGrid RERA Intelligence AI

Need to research all rulings for imperia structures ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →