Appellant / Complainant
Saurabh Mundhra, Suhani Jhanwar Mundhra
Respondent
Supertech Ltd., Dweep Infra Project Private Limited
supertech ltd.
₹33,56,687
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126011132020 by Saurabh Mundhra, Suhani Jhanwar Mundhra against Supertech Ltd., Dweep Infra Project Private Limited before up_rera.
Delay condonation
The Tribunal permitted the appellant to withdraw the defective appeal with liberty to approach RERA for the execution of direction no. 3 of the original order, which mandates a refund if possession was not provided by 31.12.2020.
Delay condonation
The Tribunal granted the respondent two days to serve objections regarding the condonation of delay and directed the appellant to file a reply within a week, scheduling the next hearing for October 5, 2021.
Defect Removal
The case was adjourned due to a lawyers' strike, with the tribunal directing parties to exchange pleadings and rescheduling the hearing for April 1, 2021.
For Order
The Tribunal granted the appellant one week to file a reply to the respondent's objection regarding the application for condonation of delay and scheduled the matter for hearing on 05.03.2021.
Tribunal Order #0901126011132020-05-10-2021
The Tribunal permitted the appellant to withdraw the defective appeal with liberty to approach RERA for the execution of direction no. 3 of the original order, which mandates a refund if possession was not provided by 31.12.2020.
Tribunal Disposal & Final Award Ruling
The Tribunal permitted the appellant to withdraw the defective appeal with liberty to approach RERA for the execution of direction no. 3 of the original order, which mandates a refund if possession was not provided by 31.12.2020. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1 percent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal permitted the appellant to withdraw the defective appeal with liberty to approach RERA for the execution of direction no. 3 of the original order, which mandates a refund if possession was not provided by 31.12.2020.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR + 1 percent
Interest Period
from the date of respective payment till recovery
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Ram Kumar Verma
Respondent Advocate(s)
- Rahul Tripathi
- Aparna Pandey
- Appurva Gupta
Official RERA Tribunal Orders (1)
The Tribunal permitted the appellant to withdraw the defective appeal with liberty to approach RERA for the execution of direction no. 3 of the original order, which mandates a refund if possession was not provided by 31.12.2020.
Need to research all rulings for supertech ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.