Appellant / Complainant
Sanjay Kumar, Smriti Singh
Respondent
Eldeco Infrastructure and Properties Limited, Eldeco Infrastructure Properties Ltd.
eldeco infrastructure and properties limited
₹7,36,350
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126011002024 by Sanjay Kumar, Smriti Singh against Eldeco Infrastructure and Properties Limited, Eldeco Infrastructure Properties Ltd. before up_rera.
Further Hearing
The Tribunal ruled that the appellant is entitled to 16% interest on deposits until actual physical possession and directed the respondent to offer possession with a full statement of account within 45 days, followed by execution of the deed and handing over of the unit.
Delay condonation
The Tribunal recalled a Rs. 10,000 cost imposed on the respondent's counsel due to personal difficulty and directed the respondent to file a computation statement regarding the appellant's installment defaults.
Delay condonation
The Tribunal adjourned the appeal to 24.03.2025 and imposed a cost of Rs. 10,000/- on the respondent for seeking repeated adjournments.
Delay condonation
The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the appeal for hearing on March 3, 2025.
Delay condonation
The Tribunal granted the appellant's request to forgo filing a rejoinder affidavit and scheduled the case for a final hearing on February 5, 2025.
Delay condonation
The Tribunal adjourned the appeal to 09.01.2025 and granted the respondent 15 days to file objections, with the appellant permitted to reply within one week thereafter.
Delay condonation
The Tribunal condoned a one-day delay in filing the appeal due to technical issues with the Registry and directed the conversion of the defective appeal into a regular appeal, scheduling the merit hearing for November 27, 2024.
Delay condonation
The Tribunal granted a request for time to allow the respondent to upload signed objections and listed the appeal for orders on 22.10.2024.
Delay condonation
The Tribunal granted the respondent a final 7-day extension to file their objection and scheduled the appeal for hearing on 16.08.2024.
Delay condonation
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with the matter listed for hearing on 22.07.2024.
Delay condonation
The Tribunal issued notice to the respondent regarding the application for condonation of delay and the grounds of appeal, scheduling the matter for hearing on 22.05.2024.
Tribunal Order #0901126011002024-24-04-2025
The Tribunal ruled that the appellant is entitled to 16% interest on deposits until actual physical possession and directed the respondent to offer possession with a full statement of account within 45 days, followed by execution of the deed and handing over of the unit.
Tribunal Order #0901126011002024-24-03-2025
The Tribunal recalled a Rs. 10,000 cost imposed on the respondent's counsel due to personal difficulty and directed the respondent to file a computation statement regarding the appellant's installment defaults.
Tribunal Order #0901126011002024-22-04-2024
The Tribunal issued notice to the respondent regarding the application for condonation of delay and the grounds of appeal, scheduling the matter for hearing on 22.05.2024.
Tribunal Order #0901126011002024-03-03-2025
The Tribunal adjourned the appeal to 24.03.2025 and imposed a cost of Rs. 10,000/- on the respondent for seeking repeated adjournments.
Tribunal Order #0901126011002024-22-10-2024
The Tribunal condoned a one-day delay in filing the appeal due to technical issues with the Registry and directed the conversion of the defective appeal into a regular appeal, scheduling the merit hearing for November 27, 2024.
Tribunal Disposal & Final Award Ruling
The Tribunal ruled that the appellant is entitled to 16% interest on deposits until actual physical possession and directed the respondent to offer possession with a full statement of account within 45 days, followed by execution of the deed and handing over of the unit. Awarded in favor of Appellant. Awarded interest rate: 16 percent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal ruled that the appellant is entitled to 16% interest on deposits until actual physical possession and directed the respondent to offer possession with a full statement of account within 45 days, followed by execution of the deed and handing over of the unit.
Ruling Awarded To
Appellant
Awarded Interest Rate
16 percent
Interest Period
w.e.f. 31.12.2018 till the date of handing over possession of the unit
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Dileep Singh
Respondent Advocate(s)
- Anurag Singh
Official RERA Tribunal Orders (5)
The Tribunal ruled that the appellant is entitled to 16% interest on deposits until actual physical possession and directed the respondent to offer possession with a full statement of account within 45 days, followed by execution of the deed and handing over of the unit.
The Tribunal recalled a Rs. 10,000 cost imposed on the respondent's counsel due to personal difficulty and directed the respondent to file a computation statement regarding the appellant's installment defaults.
The Tribunal issued notice to the respondent regarding the application for condonation of delay and the grounds of appeal, scheduling the matter for hearing on 22.05.2024.
The Tribunal adjourned the appeal to 24.03.2025 and imposed a cost of Rs. 10,000/- on the respondent for seeking repeated adjournments.
The Tribunal condoned a one-day delay in filing the appeal due to technical issues with the Registry and directed the conversion of the defective appeal into a regular appeal, scheduling the merit hearing for November 27, 2024.