up_reraStatus: Completed
CASE ID: 0901126010642023

Appellant / Complainant

U.P. Awas Evam Vikas Parishad

VS

Respondent

Arun Kumar

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestStructural Defects & QualityPromotional MisrepresentationJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

17 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126010642023 by U.P. Awas Evam Vikas Parishad against Arun Kumar before up_rera.

Delay in PossessionDelay Compensation / InterestStructural Defects & QualityPromotional MisrepresentationJurisdiction & Maintainability
2
Stage 112/06/2024

for delivery of Judgment/Order

The Tribunal allowed all 24 appeals and set aside the Adjudicating Officer's orders, ruling that the officer lacked jurisdiction to award interest for delayed possession under the guise of compensation and that claims for structural defects must first be brought to the promoter's notice.

3
Stage 229/05/2024

Delay condonation

The Tribunal condoned the delay in filing 16 defective appeals by U.P. Awas Evam Vikas Parishad, ruling that since the underlying orders were prima facie passed without jurisdiction, the interest of justice requires hearing the merits rather than dismissing them on technical limitation grounds.

4
Stage 316/05/2024

Delay condonation

No text available.

5
Stage 410/05/2024

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and scheduled the defective appeal for hearing on 16.05.2024.

6
Stage 524/04/2024

Delay condonation

The Tribunal listed the defective appeal for consideration of a delay condonation application and hearing on May 10, 2024.

7
Stage 619/03/2024

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel on health grounds and scheduled the hearing for the application for condonation of delay for 24.04.2024.

8
Stage 705/03/2024

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the hearing for the defective appeal, including the application for condonation of delay, for 19.03.2024.

9
Stage 822/02/2024

Delay condonation

The Tribunal refers the parties to a previously passed order dated in Appeal No. D249/2023 for the relevant directions.

10
Stage 931/01/2024

Delay condonation

The Tribunal granted a request to list the defective appeal for consideration of the application for condonation of delay on 22.02.2024.

11
Stage 1001/11/2023

Delay condonation

No text available.

12
Stage 1119/09/2023

Delay condonation

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the matter for hearing on November 1, 2023.

13
Stage 1231/07/2023

Delay condonation

The Tribunal granted the appellant one week's time to file a reply to the respondent's objections and scheduled the next hearing for 19.09.2023.

14
Stage 1318/05/2023

Delay condonation

The Tribunal noted the appellant's compliance with Section 43(5) regarding the deposit of Rs. 3,73,849/- and granted the respondent 10 days to file objections to the condonation of delay application and grounds of appeal.

15
Stage 14Final Ruling Order

Tribunal Order #0901126010642023-12-06-2024

The Tribunal allowed all 24 appeals and set aside the Adjudicating Officer's orders, ruling that the officer lacked jurisdiction to award interest for delayed possession under the guise of compensation and that claims for structural defects must first be brought to the promoter's notice.

16
Stage 15Interim Order

Tribunal Order #0901126010642023-29-05-2024

The Tribunal condoned the delay in filing 16 defective appeals by U.P. Awas Evam Vikas Parishad, ruling that since the underlying orders were prima facie passed without jurisdiction, the interest of justice requires hearing the merits rather than dismissing them on technical limitation grounds.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed all 24 appeals and set aside the Adjudicating Officer's orders, ruling that the officer lacked jurisdiction to award interest for delayed possession under the guise of compensation and that claims for structural defects must first be brought to the promoter's notice. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed all 24 appeals and set aside the Adjudicating Officer's orders, ruling that the officer lacked jurisdiction to award interest for delayed possession under the guise of compensation and that claims for structural defects must first be brought to the promoter's notice.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 14(3)Section 12Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Anurag Singh

Respondent Advocate(s)

  • Pramod Mitra

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126010642023-12-06-2024

The Tribunal allowed all 24 appeals and set aside the Adjudicating Officer's orders, ruling that the officer lacked jurisdiction to award interest for delayed possession under the guise of compensation and that claims for structural defects must first be brought to the promoter's notice.

INTERIM_ORDEROrder ID: 0901126010642023-29-05-2024

The Tribunal condoned the delay in filing 16 defective appeals by U.P. Awas Evam Vikas Parishad, ruling that since the underlying orders were prima facie passed without jurisdiction, the interest of justice requires hearing the merits rather than dismissing them on technical limitation grounds.