up_reraStatus: Completed
CASE ID: 0901126010642020

Appellant / Complainant

U.P. Avas Evam Vikas Parishad

VS

Respondent

Sanjay Kumar Gupta

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestStructural Defects & QualityPromotional MisrepresentationJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

14 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126010642020 by U.P. Avas Evam Vikas Parishad against Sanjay Kumar Gupta before up_rera.

Delay in PossessionDelay Compensation / InterestStructural Defects & QualityPromotional MisrepresentationJurisdiction & Maintainability
2
Stage 121/01/2022

for delivery of Judgment/Order

The U.P. Real Estate Appellate Tribunal dismissed 25 appeals filed by U.P. Awas Evam Vikas Parishad, upholding the Adjudicating Officer's orders for the promoter to pay interest (MCLR+1%) as compensation to allottees for delayed possession.

3
Stage 201/10/2021

Hearing

The Tribunal heard arguments from both the appellant and respondent, after which the judgment was reserved.

4
Stage 323/09/2021

Hearing

The Tribunal has adjourned the matter and directed that it be put up for hearing on 01.10.2021.

5
Stage 412/04/2021

For Order

No text available.

6
Stage 524/03/2021

For Order

The Tribunal adjourned the appeal to 12.04.2021 upon the joint request of both parties and directed them to file a list of dates and relied-upon judgments in advance.

7
Stage 603/03/2021

For Order

The case is adjourned due to a Bar Association call, with the next hearing scheduled for 24.03.2021 and a direction for parties to exchange pleadings in the interim.

8
Stage 722/02/2021

For Order

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the next hearing for March 3, 2021.

9
Stage 825/01/2021

For Order

No text available.

10
Stage 906/01/2021

Hearing on Appeal

No text available.

11
Stage 1006/11/2020

Hearing on Appeal

No text available.

12
Stage 1114/10/2020

For Order

No text available.

13
Stage 12Final Ruling Order

Tribunal Order #0901126010642020-21-01-2022

The U.P. Real Estate Appellate Tribunal dismissed 25 appeals filed by U.P. Awas Evam Vikas Parishad, upholding the Adjudicating Officer's orders for the promoter to pay interest (MCLR+1%) as compensation to allottees for delayed possession.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed 25 appeals filed by U.P. Awas Evam Vikas Parishad, upholding the Adjudicating Officer's orders for the promoter to pay interest (MCLR+1%) as compensation to allottees for delayed possession. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1 percent.

Disposal Winner: RespondentInterest Rate: MCLR + 1 percentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed 25 appeals filed by U.P. Awas Evam Vikas Parishad, upholding the Adjudicating Officer's orders for the promoter to pay interest (MCLR+1%) as compensation to allottees for delayed possession.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1 percent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 14(3)Section 12Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Vijay Pratap Singh Chauhan
  • Akhand Pratap Singh

Respondent Advocate(s)

  • Azhar Ikram
  • Manish Singh

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126010642020-21-01-2022

The U.P. Real Estate Appellate Tribunal dismissed 25 appeals filed by U.P. Awas Evam Vikas Parishad, upholding the Adjudicating Officer's orders for the promoter to pay interest (MCLR+1%) as compensation to allottees for delayed possession.