up_reraStatus: Completed
CASE ID: 0901126010522020

Appellant / Complainant

Naved Ahmad Siddique

VS

Respondent

SVP Builders India Limited

Developer Firm

svp builders india limited

Disputed Amount

15,59,000

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestPromotional Misrepresentation

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

15 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126010522020 by Naved Ahmad Siddique against SVP Builders India Limited before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestPromotional Misrepresentation
2
Stage 105/10/2021

for delivery of Judgment/Order

The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's deposited amount of Rs. 15,59,000 along with interest at the rate of MCLR+1% per annum from the date of deposit until the actual refund.

3
Stage 220/09/2021

Hearing

The court heard arguments from both parties and reserved the judgment for a later date.

4
Stage 307/09/2021

Hearing

The Tribunal granted a one-week extension to the respondent's counsel to prepare his brief and rescheduled the appeal hearing for 20.09.2021.

5
Stage 431/08/2021

Hearing

The appeal was adjourned to 07.09.2021 because the appellant's counsel was inaudible during the video conferencing session.

6
Stage 512/08/2021

Hearing

The Tribunal granted an adjournment to the respondent to allow time to review the appellant's reply and listed the appeal for hearing on 31.08.2021.

7
Stage 624/03/2021

Hearing

The U.P. Real Estate Appellate Tribunal dismissed the appeal due to non-prosecution as the appellant and their counsel failed to appear for the hearing.

8
Stage 703/03/2021

Hearing

The Tribunal has scheduled the appeal for a hearing on 24.03.2021 due to advocates abstaining from judicial work in support of a call by the Oudh Bar Association.

9
Stage 808/02/2021

For Order

The tribunal granted an adjournment requested by the appellant's counsel due to medical reasons and rescheduled the hearing for March 3, 2021.

10
Stage 922/01/2021

Final Hearing

The Tribunal granted a request by the respondent's counsel to summon the RERA records from Complaint No. NCR145/05/1101/2019 to investigate allegations that the appeal was filed on false grounds.

11
Stage 1005/01/2021

Final Hearing

No text available.

12
Stage 11Interim Order

Tribunal Order #0901126010522020-24-03-2021

The U.P. Real Estate Appellate Tribunal dismissed the appeal due to non-prosecution as the appellant and their counsel failed to appear for the hearing.

13
Stage 12Interim Order

Tribunal Order #0901126010522020-22-01-2021

The Tribunal granted a request by the respondent's counsel to summon the RERA records from Complaint No. NCR145/05/1101/2019 to investigate allegations that the appeal was filed on false grounds.

14
Stage 13Final Ruling Order

Tribunal Order #0901126010522020-05-10-2021

The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's deposited amount of Rs. 15,59,000 along with interest at the rate of MCLR+1% per annum from the date of deposit until the actual refund.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's deposited amount of Rs. 15,59,000 along with interest at the rate of MCLR+1% per annum from the date of deposit until the actual refund. Awarded in favor of Appellant. Awarded interest rate: MCLR+1% per annum.

Disposal Winner: AppellantInterest Rate: MCLR+1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's deposited amount of Rs. 15,59,000 along with interest at the rate of MCLR+1% per annum from the date of deposit until the actual refund.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1% per annum

Interest Period

from the date of deposit till the refund of the amount

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 12

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Saghar Mehdi

Respondent Advocate(s)

  • Azhar Ikram
  • Manish Singh

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126010522020-24-03-2021

The U.P. Real Estate Appellate Tribunal dismissed the appeal due to non-prosecution as the appellant and their counsel failed to appear for the hearing.

INTERIM_ORDEROrder ID: 0901126010522020-22-01-2021

The Tribunal granted a request by the respondent's counsel to summon the RERA records from Complaint No. NCR145/05/1101/2019 to investigate allegations that the appeal was filed on false grounds.

FINAL_ORDEROrder ID: 0901126010522020-05-10-2021

The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's deposited amount of Rs. 15,59,000 along with interest at the rate of MCLR+1% per annum from the date of deposit until the actual refund.

TathyaGrid RERA Intelligence AI

Need to research all rulings for svp builders india limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →