CASE ID: 0901126010422020

Appellant / Complainant

Pyramid Townships Pvt. Ltd.

VS

Respondent

Manoj Kumar Sharma

Developer Firm

pyramid townships pvt. ltd.

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

11 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126010422020 by Pyramid Townships Pvt. Ltd. against Manoj Kumar Sharma before up_rera.

2
Stage 128/09/2021

Hearing

The Tribunal disposed of the appeal following an out-of-court settlement between the parties and directed that the amount deposited under Section 43(5) of the Act be released to the appellant, M/s Pyramid Townships Pvt. Ltd., via RTGS.

3
Stage 229/04/2021

Hearing

No text available.

4
Stage 301/04/2021

Further Order

No text available.

5
Stage 405/03/2021

For Order

The appeal was adjourned due to a Bar Association strike, with the matter rescheduled for hearing on 01.04.2021.

6
Stage 508/02/2021

For Order

The Tribunal noted a potential settlement between the parties and adjourned the matter to 05.03.2021 for further orders.

7
Stage 629/01/2021

Notice

The Tribunal has ordered the application for recall of the order dated 10.07.2020 to be listed before Bench No. 2 on 08.02.2021.

8
Stage 706/01/2021

Hearing on Recall App

No text available.

9
Stage 807/12/2020

Hearing on Recall App

No text available.

10
Stage 9Final Ruling Order

Tribunal Order #0901126010422020-28-09-2021

The Tribunal disposed of the appeal following an out-of-court settlement between the parties and directed that the amount deposited under Section 43(5) of the Act be released to the appellant, M/s Pyramid Townships Pvt. Ltd., via RTGS.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal disposed of the appeal following an out-of-court settlement between the parties and directed that the amount deposited under Section 43(5) of the Act be released to the appellant, M/s Pyramid Townships Pvt. Ltd., via RTGS. Awarded in favor of Partial.

Disposal Winner: PartialStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal disposed of the appeal following an out-of-court settlement between the parties and directed that the amount deposited under Section 43(5) of the Act be released to the appellant, M/s Pyramid Townships Pvt. Ltd., via RTGS.

Ruling Awarded To

Partial

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Anubhav Singh

Respondent Advocate(s)

  • Surendra Kumar Mishra

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126010422020-28-09-2021

The Tribunal disposed of the appeal following an out-of-court settlement between the parties and directed that the amount deposited under Section 43(5) of the Act be released to the appellant, M/s Pyramid Townships Pvt. Ltd., via RTGS.

TathyaGrid RERA Intelligence AI

Need to research all rulings for pyramid townships pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →