up_reraStatus: Completed
CASE ID: 0901126010342022

Appellant / Complainant

Uppal Chadha Hi-Tech Developers Pvt. Ltd.

VS

Respondent

Rajdeep Singh Chimni, Pushpinder Singh Chimni

Developer Firm

uppal chadha hi-tech developers pvt. ltd.

Disputed Amount

7,98,127

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Refund of Investment

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

6 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126010342022 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Rajdeep Singh Chimni, Pushpinder Singh Chimni before up_rera.

Refund of Investment
2
Stage 117/08/2023

Notice

The Tribunal allowed the withdrawal of the appeal following a settlement between the parties and directed the release of Rs. 7,98,127/- (held in fixed deposit) to the applicant via RTGS.

3
Stage 221/06/2023

Delay condonation

The Tribunal accepted the appellant's deposit of Rs 7,98,127/- in compliance with Section 43(5) of the RERA Act and issued notice to the respondents regarding the application for condonation of delay.

4
Stage 3Final Ruling Order

Tribunal Order #0901126010342022-17-08-2023

The Tribunal allowed the withdrawal of the appeal following a settlement between the parties and directed the release of Rs. 7,98,127/- (held in fixed deposit) to the applicant via RTGS.

5
Stage 4Interim Order

Tribunal Order #0901126010342022-21-06-2023

The Tribunal accepted the appellant's deposit of Rs 7,98,127/- in compliance with Section 43(5) of the RERA Act and issued notice to the respondents regarding the application for condonation of delay.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the withdrawal of the appeal following a settlement between the parties and directed the release of Rs. 7,98,127/- (held in fixed deposit) to the applicant via RTGS. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the withdrawal of the appeal following a settlement between the parties and directed the release of Rs. 7,98,127/- (held in fixed deposit) to the applicant via RTGS.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Yadav
  • Bal Kishor Verma

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126010342022-17-08-2023

The Tribunal allowed the withdrawal of the appeal following a settlement between the parties and directed the release of Rs. 7,98,127/- (held in fixed deposit) to the applicant via RTGS.

INTERIM_ORDEROrder ID: 0901126010342022-21-06-2023

The Tribunal accepted the appellant's deposit of Rs 7,98,127/- in compliance with Section 43(5) of the RERA Act and issued notice to the respondents regarding the application for condonation of delay.

TathyaGrid RERA Intelligence AI

Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →