up_reraStatus: Completed
CASE ID: 0901126010062025

Appellant / Complainant

Narendra Dev Infra Pvt. Ltd.

VS

Respondent

U.P. Real Estate Regulatory Authority

Developer Firm

narendra dev infra pvt. ltd.

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Jurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

7 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126010062025 by Narendra Dev Infra Pvt. Ltd. against U.P. Real Estate Regulatory Authority before up_rera.

Jurisdiction & Maintainability
2
Stage 123/07/2025

for delivery of Judgment/Order

The Tribunal set aside the U.P. Real Estate Regulatory Authority's rejection of the project registration for 'RLDA KANHA SHYAM,' ruling that RLDA is the competent authority to approve maps on Railway land and that the project is deemed registered due to the Authority's failure to decide within the mandatory 30-day period.

3
Stage 229/05/2025

Defect Removal

The Tribunal heard arguments from both the appellant and respondent regarding the appeal and its objections, subsequently reserving the judgment for future pronouncement.

4
Stage 308/05/2025

Defect Removal

The Tribunal granted the respondent 10 days to file objections regarding the condonation of delay and grounds of appeal, with a subsequent week allowed for the appellant to file a rejoinder.

5
Stage 415/04/2025

Defect Removal

The Tribunal has admitted the appeal within the limitation period and issued notice to the respondent, scheduling the matter for hearing on 08.05.2025.

6
Stage 5Final Ruling Order

Tribunal Order #0901126010062025-23-07-2025

The Tribunal set aside the U.P. Real Estate Regulatory Authority's rejection of the project registration for 'RLDA KANHA SHYAM,' ruling that RLDA is the competent authority to approve maps on Railway land and that the project is deemed registered due to the Authority's failure to decide within the mandatory 30-day period.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the U.P. Real Estate Regulatory Authority's rejection of the project registration for 'RLDA KANHA SHYAM,' ruling that RLDA is the competent authority to approve maps on Railway land and that the project is deemed registered due to the Authority's failure to decide within the mandatory 30-day period. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the U.P. Real Estate Regulatory Authority's rejection of the project registration for 'RLDA KANHA SHYAM,' ruling that RLDA is the competent authority to approve maps on Railway land and that the project is deemed registered due to the Authority's failure to decide within the mandatory 30-day period.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Saurabh Misra
  • Krishna Kumar Singh

Respondent Advocate(s)

  • Shobhit Mohan Shukla

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126010062025-23-07-2025

The Tribunal set aside the U.P. Real Estate Regulatory Authority's rejection of the project registration for 'RLDA KANHA SHYAM,' ruling that RLDA is the competent authority to approve maps on Railway land and that the project is deemed registered due to the Authority's failure to decide within the mandatory 30-day period.

TathyaGrid RERA Intelligence AI