up_reraStatus: Completed
CASE ID: 0901126010022024

Appellant / Complainant

U.P. State Industrial Development Authority

VS

Respondent

Gyan Prakash Mishra

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

16 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126010022024 by U.P. State Industrial Development Authority against Gyan Prakash Mishra before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 115/07/2025

Delay condonation

The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later.

3
Stage 227/05/2025

Delay condonation

Upon the joint request of the counsels for both parties, the Tribunal has adjourned the appeal to be listed for orders or hearing on 15.07.2025.

4
Stage 302/05/2025

Delay condonation

The Tribunal granted the appellant a one-week extension to file a rejoinder affidavit and scheduled the case for orders on 27.05.2025.

5
Stage 427/03/2025

Delay condonation

The Tribunal granted the respondent ten days to file objections and allowed the appellant seven days thereafter to file a rejoinder, with the case scheduled for hearing on May 2, 2025.

6
Stage 525/02/2025

Delay condonation

The case is adjourned to 27.03.2025 due to a strike by the Bar Council of Uttar Pradesh.

7
Stage 606/02/2025

Delay condonation

The Tribunal has scheduled the case for orders on February 25, 2025.

8
Stage 722/01/2025

Delay condonation

The Tribunal has listed the defective appeal along with the cross-appeal for hearing on February 6, 2025, to consider the application for condonation of delay.

9
Stage 809/01/2025

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel due to him being out of station and rescheduled the matter for 22.01.2025.

10
Stage 909/12/2024

Delay condonation

The Tribunal has scheduled the appeal for hearing/orders on 09.01.2025 to coincide with the listing of a cross-appeal.

11
Stage 1006/11/2024

Delay condonation

The Tribunal granted an adjournment requested by the respondent and scheduled the appeal for hearing on 09.12.2024, while noting that no further opportunity will be given to the respondent to file objections to the application for condonation of delay.

12
Stage 1126/09/2024

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the appeal, with a subsequent one-week deadline for the appellant to file a reply, and scheduled the next hearing for 06.11.2024.

13
Stage 1223/08/2024

Delay condonation

The Tribunal accepted proof of service upon the respondent and directed the respondent to file an objection within 10 days, with the matter listed for hearing on 26.09.2024.

14
Stage 1322/07/2024

Defect Removal

The Tribunal issued notice to the respondent regarding the appeal and application for condonation of delay, directing the applicant to serve the notice and setting the next hearing for 23.08.2024.

15
Stage 14Final Ruling Order

Tribunal Order #0901126010022024-15-07-2025

The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 01.01.2017 till receipt of development certificate/completion certificate or till handing over the possession, whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Kartikey Dubey

Respondent Advocate(s)

  • Deepak Dwivedi

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126010022024-15-07-2025

The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later.