Appellant / Complainant
U.P. State Industrial Development Authority
Respondent
Gyan Prakash Mishra
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126010022024 by U.P. State Industrial Development Authority against Gyan Prakash Mishra before up_rera.
Delay condonation
The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later.
Delay condonation
Upon the joint request of the counsels for both parties, the Tribunal has adjourned the appeal to be listed for orders or hearing on 15.07.2025.
Delay condonation
The Tribunal granted the appellant a one-week extension to file a rejoinder affidavit and scheduled the case for orders on 27.05.2025.
Delay condonation
The Tribunal granted the respondent ten days to file objections and allowed the appellant seven days thereafter to file a rejoinder, with the case scheduled for hearing on May 2, 2025.
Delay condonation
The case is adjourned to 27.03.2025 due to a strike by the Bar Council of Uttar Pradesh.
Delay condonation
The Tribunal has scheduled the case for orders on February 25, 2025.
Delay condonation
The Tribunal has listed the defective appeal along with the cross-appeal for hearing on February 6, 2025, to consider the application for condonation of delay.
Delay condonation
The Tribunal granted an adjournment requested by the respondent's counsel due to him being out of station and rescheduled the matter for 22.01.2025.
Delay condonation
The Tribunal has scheduled the appeal for hearing/orders on 09.01.2025 to coincide with the listing of a cross-appeal.
Delay condonation
The Tribunal granted an adjournment requested by the respondent and scheduled the appeal for hearing on 09.12.2024, while noting that no further opportunity will be given to the respondent to file objections to the application for condonation of delay.
Delay condonation
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the appeal, with a subsequent one-week deadline for the appellant to file a reply, and scheduled the next hearing for 06.11.2024.
Delay condonation
The Tribunal accepted proof of service upon the respondent and directed the respondent to file an objection within 10 days, with the matter listed for hearing on 26.09.2024.
Defect Removal
The Tribunal issued notice to the respondent regarding the appeal and application for condonation of delay, directing the applicant to serve the notice and setting the next hearing for 23.08.2024.
Tribunal Order #0901126010022024-15-07-2025
The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Interest Period
from 01.01.2017 till receipt of development certificate/completion certificate or till handing over the possession, whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Kartikey Dubey
Respondent Advocate(s)
- Deepak Dwivedi
Official RERA Tribunal Orders (1)
The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.