up_reraStatus: Completed
CASE ID: 0901126010002024

Appellant / Complainant

U.P. State Industrial Development Authority

VS

Respondent

Tulsi Das Gupta

Disputed Amount

42,39,507

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

10 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126010002024 by U.P. State Industrial Development Authority against Tulsi Das Gupta before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / Interest
2
Stage 106/01/2025

Delay condonation

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, upholding the Regulatory Authority's order for a refund of deposit with interest to the allottee due to inordinate project delays.

3
Stage 205/12/2024

Delay condonation

The Tribunal granted a request from the appellant's counsel to adjourn the matter and rescheduled the appeal for hearing on 06.01.2025.

4
Stage 304/11/2024

Delay condonation

The Tribunal noted that advocates were abstaining from judicial work due to a Bar Council resolution and subsequently ordered the appeal to be listed on 05.12.2024.

5
Stage 424/09/2024

Defect Removal

The Tribunal noted the appellant's deposit of Rs. 64,46,637/- in compliance with Section 43(5) and issued notice to the respondent for the appeal and application for condonation of delay, scheduled for hearing on 04.11.2024.

6
Stage 518/09/2024

Defect Removal

The Tribunal granted the appellant three days to rectify procedural defects identified by the Registry and scheduled the matter for orders on 24.09.2024.

7
Stage 602/09/2024

Defect Removal

The Tribunal directed the appellant to rectify defects regarding annexures 1, 4, and the CA certificate within one week and scheduled the matter for orders on 18.09.2024.

8
Stage 7Final Ruling Order

Tribunal Order #0901126010002024-06-01-2025

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, upholding the Regulatory Authority's order for a refund of deposit with interest to the allottee due to inordinate project delays.

9
Stage 8Interim Order

Tribunal Order #0901126010002024-24-09-2024

The Tribunal noted the appellant's deposit of Rs. 64,46,637/- in compliance with Section 43(5) and issued notice to the respondent for the appeal and application for condonation of delay, scheduled for hearing on 04.11.2024.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, upholding the Regulatory Authority's order for a refund of deposit with interest to the allottee due to inordinate project delays. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, upholding the Regulatory Authority's order for a refund of deposit with interest to the allottee due to inordinate project delays.

Ruling Awarded To

Respondent

Interest Period

till the date of payment

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Kartikey Dubey

Respondent Advocate(s)

  • Shivam Agarwal

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126010002024-06-01-2025

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, upholding the Regulatory Authority's order for a refund of deposit with interest to the allottee due to inordinate project delays.

INTERIM_ORDEROrder ID: 0901126010002024-24-09-2024

The Tribunal noted the appellant's deposit of Rs. 64,46,637/- in compliance with Section 43(5) and issued notice to the respondent for the appeal and application for condonation of delay, scheduled for hearing on 04.11.2024.