Appellant / Complainant
U.P. State Industrial Development Authority
Respondent
Tulsi Das Gupta
₹42,39,507
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126010002024 by U.P. State Industrial Development Authority against Tulsi Das Gupta before up_rera.
Delay condonation
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, upholding the Regulatory Authority's order for a refund of deposit with interest to the allottee due to inordinate project delays.
Delay condonation
The Tribunal granted a request from the appellant's counsel to adjourn the matter and rescheduled the appeal for hearing on 06.01.2025.
Delay condonation
The Tribunal noted that advocates were abstaining from judicial work due to a Bar Council resolution and subsequently ordered the appeal to be listed on 05.12.2024.
Defect Removal
The Tribunal noted the appellant's deposit of Rs. 64,46,637/- in compliance with Section 43(5) and issued notice to the respondent for the appeal and application for condonation of delay, scheduled for hearing on 04.11.2024.
Defect Removal
The Tribunal granted the appellant three days to rectify procedural defects identified by the Registry and scheduled the matter for orders on 24.09.2024.
Defect Removal
The Tribunal directed the appellant to rectify defects regarding annexures 1, 4, and the CA certificate within one week and scheduled the matter for orders on 18.09.2024.
Tribunal Order #0901126010002024-06-01-2025
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, upholding the Regulatory Authority's order for a refund of deposit with interest to the allottee due to inordinate project delays.
Tribunal Order #0901126010002024-24-09-2024
The Tribunal noted the appellant's deposit of Rs. 64,46,637/- in compliance with Section 43(5) and issued notice to the respondent for the appeal and application for condonation of delay, scheduled for hearing on 04.11.2024.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, upholding the Regulatory Authority's order for a refund of deposit with interest to the allottee due to inordinate project delays. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, upholding the Regulatory Authority's order for a refund of deposit with interest to the allottee due to inordinate project delays.
Ruling Awarded To
Respondent
Interest Period
till the date of payment
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Kartikey Dubey
Respondent Advocate(s)
- Shivam Agarwal
Official RERA Tribunal Orders (2)
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, upholding the Regulatory Authority's order for a refund of deposit with interest to the allottee due to inordinate project delays.
The Tribunal noted the appellant's deposit of Rs. 64,46,637/- in compliance with Section 43(5) and issued notice to the respondent for the appeal and application for condonation of delay, scheduled for hearing on 04.11.2024.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.