Appellant / Complainant
U.P. State Industrial Development Authority
Respondent
Ambuja Pandey
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126009882024 by U.P. State Industrial Development Authority against Ambuja Pandey before up_rera.
Delay condonation
The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later.
Delay condonation
The Tribunal noted the filing of the rejoinder affidavit and scheduled the appeal for final hearing on 15.07.2025.
Delay condonation
The Tribunal granted an adjournment application from the appellant and provided a seven-day window for filing a rejoinder to the respondent's objections, scheduling the next hearing for May 19, 2025.
Delay condonation
The appeal was adjourned to 28.04.2025 because lawyers were abstaining from judicial work following a resolution by the Real Estate Bar Association, Lucknow.
Delay condonation
The court adjourned the appeal to 28.03.2025 due to counsels abstaining from judicial work following a U.P. Bar Council resolution.
Delay condonation
The Tribunal noted the absence of the appellant's counsel and ordered the appeal to be listed on 25.02.2025 along with the records of Appeal No. D 393/2024.
Delay condonation
The Tribunal granted a request for adjournment on behalf of the respondent's counsel and rescheduled the appeal for hearing on 04.02.2025.
Delay condonation
The Tribunal granted a request for adjournment made by the appellant's counsel and scheduled the appeal for orders on 16.01.2025.
Delay condonation
The Tribunal has scheduled the appeal for hearing/orders on 16.12.2024 to coincide with the listing of a cross-appeal.
Delay condonation
The Tribunal granted an adjournment requested by the respondent and scheduled the appeal for hearing on 09.12.2024, while noting that no further opportunities will be given to the respondent to file objections to the application for condonation of delay.
Delay condonation
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the appeal, with a subsequent timeline for the appellant to file a reply.
Delay condonation
The Tribunal accepted proof of service upon the respondent and directed the respondent to file an objection within 10 days, with the matter listed for hearing on 26.09.2024.
Defect Removal
The Tribunal issued notice to the respondent regarding the appeal and application for condonation of delay, while noting the appellant's compliance with the mandatory pre-deposit requirement under Section 43(5) of the Act.
Tribunal Order #0901126009882024-15-07-2025
The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later.
Tribunal Order #0901126009882024-22-07-2024
The Tribunal issued notice to the respondent regarding the appeal and application for condonation of delay, while noting the appellant's compliance with the mandatory pre-deposit requirement under Section 43(5) of the Act.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Interest Period
from 01.01.2017 till receipt of development certificate/completion certificate or till handing over the possession, whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Kartikey Dubey
Respondent Advocate(s)
- Deepak Dwivedi
Official RERA Tribunal Orders (2)
The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later.
The Tribunal issued notice to the respondent regarding the appeal and application for condonation of delay, while noting the appellant's compliance with the mandatory pre-deposit requirement under Section 43(5) of the Act.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.