up_reraStatus: Completed
CASE ID: 0901126009882024

Appellant / Complainant

U.P. State Industrial Development Authority

VS

Respondent

Ambuja Pandey

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

17 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126009882024 by U.P. State Industrial Development Authority against Ambuja Pandey before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 115/07/2025

Delay condonation

The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later.

3
Stage 219/05/2025

Delay condonation

The Tribunal noted the filing of the rejoinder affidavit and scheduled the appeal for final hearing on 15.07.2025.

4
Stage 328/04/2025

Delay condonation

The Tribunal granted an adjournment application from the appellant and provided a seven-day window for filing a rejoinder to the respondent's objections, scheduling the next hearing for May 19, 2025.

5
Stage 428/03/2025

Delay condonation

The appeal was adjourned to 28.04.2025 because lawyers were abstaining from judicial work following a resolution by the Real Estate Bar Association, Lucknow.

6
Stage 525/02/2025

Delay condonation

The court adjourned the appeal to 28.03.2025 due to counsels abstaining from judicial work following a U.P. Bar Council resolution.

7
Stage 604/02/2025

Delay condonation

The Tribunal noted the absence of the appellant's counsel and ordered the appeal to be listed on 25.02.2025 along with the records of Appeal No. D 393/2024.

8
Stage 716/01/2025

Delay condonation

The Tribunal granted a request for adjournment on behalf of the respondent's counsel and rescheduled the appeal for hearing on 04.02.2025.

9
Stage 816/12/2024

Delay condonation

The Tribunal granted a request for adjournment made by the appellant's counsel and scheduled the appeal for orders on 16.01.2025.

10
Stage 909/12/2024

Delay condonation

The Tribunal has scheduled the appeal for hearing/orders on 16.12.2024 to coincide with the listing of a cross-appeal.

11
Stage 1006/11/2024

Delay condonation

The Tribunal granted an adjournment requested by the respondent and scheduled the appeal for hearing on 09.12.2024, while noting that no further opportunities will be given to the respondent to file objections to the application for condonation of delay.

12
Stage 1126/09/2024

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the appeal, with a subsequent timeline for the appellant to file a reply.

13
Stage 1223/08/2024

Delay condonation

The Tribunal accepted proof of service upon the respondent and directed the respondent to file an objection within 10 days, with the matter listed for hearing on 26.09.2024.

14
Stage 1322/07/2024

Defect Removal

The Tribunal issued notice to the respondent regarding the appeal and application for condonation of delay, while noting the appellant's compliance with the mandatory pre-deposit requirement under Section 43(5) of the Act.

15
Stage 14Final Ruling Order

Tribunal Order #0901126009882024-15-07-2025

The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later.

16
Stage 15Interim Order

Tribunal Order #0901126009882024-22-07-2024

The Tribunal issued notice to the respondent regarding the appeal and application for condonation of delay, while noting the appellant's compliance with the mandatory pre-deposit requirement under Section 43(5) of the Act.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 01.01.2017 till receipt of development certificate/completion certificate or till handing over the possession, whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Kartikey Dubey

Respondent Advocate(s)

  • Deepak Dwivedi

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126009882024-15-07-2025

The Tribunal dismissed the appeal filed by the U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay delay interest to the allottee from January 1, 2017, until the receipt of the completion certificate or handing over of possession, whichever is later.

INTERIM_ORDEROrder ID: 0901126009882024-22-07-2024

The Tribunal issued notice to the respondent regarding the appeal and application for condonation of delay, while noting the appellant's compliance with the mandatory pre-deposit requirement under Section 43(5) of the Act.