Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

34 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126009792023 by Kulpreet Rekhi against Manya Infrabuildwell Pvt. Ltd. before up_rera.

2
Stage 111/02/2026

For Order

No text available.

3
Stage 203/02/2026

For Order

The Tribunal has ordered the appeal to be listed for hearing after the decision is rendered by a larger Bench in Appeal No. 17/2025 (Soniya Vs. Divyanka Homes Pvt. Ltd.).

4
Stage 309/01/2026

For Order

The Tribunal granted the respondent two weeks to file objections and allowed a subsequent week for a rejoinder, scheduling the next hearing for February 3, 2026.

5
Stage 404/12/2025

For Order

The respondent promoter paid the admitted amount of Rs. 3,55,000/- to the appellant via cheque, and the matter is scheduled for further orders/hearing on 09.01.2026.

6
Stage 504/11/2025

For Order

The Tribunal noted the respondent's submission regarding the payment of installments and adjourned the appeal for further orders/hearing on 04.12.2025.

7
Stage 607/10/2025

Delay condonation

The Tribunal noted the respondent's submission that the second installment has been paid to the appellant and scheduled the next hearing for November 4, 2025.

8
Stage 708/09/2025

Final Hearing

The Tribunal noted that the respondent is paying in installments and has scheduled the appeal for further orders/hearing on 07.10.2025.

9
Stage 818/08/2025

Final Hearing

The Respondent company admits a liability of Rs. 20,57,580/- and undertakes to pay the admitted amount in four installments via RTGS, with the first installment due by 04.09.2025 and final payment by 02.12.2025.

10
Stage 923/07/2025

Final Hearing

The Tribunal issued a warrant of detention against the respondent company's Director and directed the Collector of Lucknow to attach the bank account of Manya Infra Buildwell Pvt. Ltd. for Rs. 20,32,580/- due to non-compliance with previous orders.

11
Stage 1002/07/2025

Final Hearing

The Tribunal directed the respondent to comply with a previous order to refund the appellant's money within one week, failing which the managing director must appear to show cause; additionally, the respondent is ordered to pay costs of Rs. 25,000 to the appellant.

12
Stage 1130/04/2025

Final Hearing

The Tribunal directed the respondent promoter to refund Rs. 9,85,789/- with interest at MCLR+1% to the appellant on or before the next hearing date, while reserving consideration for any remaining balance.

13
Stage 1222/04/2025

For Order

The Tribunal granted the respondent three days to file objections to the appellant's affidavit and scheduled the appeal for a final hearing on 30.04.2025.

14
Stage 1326/03/2025

For Order

The Tribunal granted the appellant a final opportunity to upload documents regarding cash payments, noting that no further adjournments will be permitted for this purpose.

15
Stage 1403/03/2025

For Order

The Tribunal granted a request for adjournment submitted by the appellant and scheduled the case for orders on 26.03.2025.

16
Stage 1506/02/2025

For Order

The Appellant requested an adjournment, and the Tribunal has rescheduled the case for orders on March 3, 2025.

17
Stage 1617/01/2025

For Order

The Tribunal granted the appellant time to file documents regarding cash payments made to the erstwhile builder and noted the receipt of a Rs 20,000/- demand draft from the respondent in compliance with a previous order.

18
Stage 1706/12/2024

For Order

The Tribunal noted an application for impleadment by Kanchal Group and directed the respondent to deposit a previously imposed cost of Rs 20,000, while ordering the appellant to file a calculation chart for delay interest.

19
Stage 1802/10/2024

For Order

No text available.

20
Stage 1926/09/2023

Final Hearing

The Tribunal directed that the defective appeal be listed before a different Bench when available, noting the attitude of the appellant who appeared in person.

21
Stage 2025/09/2023

Final Hearing

The Tribunal adjourned the matter to 26.09.2023 to allow the respondent's counsel to file an affidavit confirming their verbal commitment to refund the appellant's amount within one month.

22
Stage 2108/08/2023

Final Hearing

The Tribunal noted the appellant's request for unavailability due to personal difficulties and rescheduled the hearing of the appeal to 25.09.2023.

23
Stage 2226/05/2023

For Order

No text available.

24
Stage 2318/04/2023

For Order

The Tribunal granted the respondent one week to file objections and a vakalatnama, with the matter scheduled for further hearing on 26.05.2023.

25
Stage 2403/03/2023

Admission

The Tribunal issued notice to the respondent and established a procedural timeline for service of appeal documents and filing of objections/replies before the next hearing on 18.04.2023.

26
Stage 25Interim Order

Tribunal Order #0901126009792023-23-07-2025

The Tribunal issued a warrant of detention against the respondent company's Director and directed the Collector of Lucknow to attach the bank account of Manya Infra Buildwell Pvt. Ltd. for Rs. 20,32,580/- due to non-compliance with previous orders.

27
Stage 26Interim Order

Tribunal Order #0901126009792023-30-04-2025

The Tribunal directed the respondent promoter to refund Rs. 9,85,789/- with interest at MCLR+1% to the appellant on or before the next hearing date, while reserving consideration for any remaining balance.

28
Stage 27Interim Order

Tribunal Order #0901126009792023-06-12-2024

The Tribunal noted an application for impleadment by Kanchal Group and directed the respondent to deposit a previously imposed cost of Rs 20,000, while ordering the appellant to file a calculation chart for delay interest.

29
Stage 28Interim Order

Tribunal Order #0901126009792023-04-12-2025

The respondent promoter paid the admitted amount of Rs. 3,55,000/- to the appellant via cheque, and the matter is scheduled for further orders/hearing on 09.01.2026.

30
Stage 29Interim Order

Tribunal Order #0901126009792023-18-08-2025

The Respondent company admits a liability of Rs. 20,57,580/- and undertakes to pay the admitted amount in four installments via RTGS, with the first installment due by 04.09.2025 and final payment by 02.12.2025.

31
Stage 30Interim Order

Tribunal Order #0901126009792023-02-07-2025

The Tribunal directed the respondent to comply with a previous order to refund the appellant's money within one week, failing which the managing director must appear to show cause; additionally, the respondent is ordered to pay costs of Rs. 25,000 to the appellant.

32
Stage 31Interim Order

Tribunal Order #0901126009792023-26-03-2025

The Tribunal granted the appellant a final opportunity to upload documents regarding cash payments, noting that no further adjournments will be permitted for this purpose.

33
Stage 32Interim Order

Tribunal Order #0901126009792023-17-01-2025

The Tribunal granted the appellant time to file documents regarding cash payments made to the erstwhile builder and noted the receipt of a Rs 20,000/- demand draft from the respondent in compliance with a previous order.

Disposal Phase

Tribunal Disposal & Final Award Ruling

List before another Bench (Defective Appeal) Awarded in favor of Unknown.

Disposal Winner: UnknownStatus: Active

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

List before another Bench (Defective Appeal)

Ruling Awarded To

Unknown

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Applicant/Appellant In-Person

Respondent Advocate(s)

  • Harshit Gupta

Official RERA Tribunal Orders (8)

INTERIM_ORDEROrder ID: 0901126009792023-23-07-2025

The Tribunal issued a warrant of detention against the respondent company's Director and directed the Collector of Lucknow to attach the bank account of Manya Infra Buildwell Pvt. Ltd. for Rs. 20,32,580/- due to non-compliance with previous orders.

INTERIM_ORDEROrder ID: 0901126009792023-30-04-2025

The Tribunal directed the respondent promoter to refund Rs. 9,85,789/- with interest at MCLR+1% to the appellant on or before the next hearing date, while reserving consideration for any remaining balance.

INTERIM_ORDEROrder ID: 0901126009792023-06-12-2024

The Tribunal noted an application for impleadment by Kanchal Group and directed the respondent to deposit a previously imposed cost of Rs 20,000, while ordering the appellant to file a calculation chart for delay interest.

INTERIM_ORDEROrder ID: 0901126009792023-04-12-2025

The respondent promoter paid the admitted amount of Rs. 3,55,000/- to the appellant via cheque, and the matter is scheduled for further orders/hearing on 09.01.2026.

INTERIM_ORDEROrder ID: 0901126009792023-18-08-2025

The Respondent company admits a liability of Rs. 20,57,580/- and undertakes to pay the admitted amount in four installments via RTGS, with the first installment due by 04.09.2025 and final payment by 02.12.2025.

INTERIM_ORDEROrder ID: 0901126009792023-02-07-2025

The Tribunal directed the respondent to comply with a previous order to refund the appellant's money within one week, failing which the managing director must appear to show cause; additionally, the respondent is ordered to pay costs of Rs. 25,000 to the appellant.

INTERIM_ORDEROrder ID: 0901126009792023-26-03-2025

The Tribunal granted the appellant a final opportunity to upload documents regarding cash payments, noting that no further adjournments will be permitted for this purpose.

INTERIM_ORDEROrder ID: 0901126009792023-17-01-2025

The Tribunal granted the appellant time to file documents regarding cash payments made to the erstwhile builder and noted the receipt of a Rs 20,000/- demand draft from the respondent in compliance with a previous order.

TathyaGrid RERA Intelligence AI

Need to research all rulings for manya infrabuildwell pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →