Appellant / Complainant
Pankaj Awasthi
Respondent
Sunshine Infrawell Pvt. Ltd.
sunshine infrawell pvt. ltd.
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126009752020 by Pankaj Awasthi against Sunshine Infrawell Pvt. Ltd. before up_rera.
Hearing
Following a High Court remand, the Tribunal restored the appellant's complaint to its original status and directed U.P. RERA to decide the dispute on its merits within three months.
Hearing
The Tribunal has adjourned the appeal to a new hearing date of April 4, 2025, upon the request of the counsel for both parties.
Hearing
The Tribunal has scheduled the case for orders on March 10, 2025.
Hearing
The Tribunal granted a request to list the appeal for orders on 14.02.2025 due to the absence of the respondent's counsel.
Hearing
The Tribunal has scheduled the matter for orders on January 23, 2025.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the appeal for hearing on 17.01.2025.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing/orders on 29.11.2024.
Hearing
The Tribunal has adjourned the appeal to 24.10.2024 for final hearing following a joint request from the counsels for both parties.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for September 13, 2024.
Final Hearing
The Tribunal dismissed the appeal against the RERA order, ruling that because the real estate project was completed prior to the notification of the Rules and was not registered under the Act, it does not qualify as an 'ongoing project' and thus falls outside RERA's jurisdiction.
Final Hearing
The Tribunal accepted the filing of a vakalatnama for the appellant and adjourned the matter to 03.01.2022 following an adjournment request from the respondent's counsel due to illness.
Final Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to a personal emergency and directed the appellant's counsel to file his Vakalatnama before the next hearing on 15.12.2021.
Final Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the appeal for a final hearing on November 29, 2021.
Hearing
The Tribunal granted ten days for the new counsel for the appellant to file a Vakalatnama and a reply to the respondent's objection, subject to obtaining a 'No Objection' from previous counsel.
Hearing
The Tribunal granted a request for adjournment due to the resumption of work following the COVID-19 pandemic and rescheduled the matter for 28.10.2021.
Hearing
The Tribunal granted the respondent one week to file the CC/OC certificate and scheduled the next hearing for 15.04.2021.
Hearing
The Tribunal adjourned the appeal to 24.03.2021 and directed the respondent's counsel to ensure compliance with the previous order dated 20.01.2021.
For Order
The Tribunal granted an adjournment request from the respondent's counsel and directed respondent no. 2 to comply with a previous order dated 20.01.2021.
For Order
The Tribunal granted respondent no. 1 one week's time to file a supplementary affidavit containing the OC/CC certificate and scheduled the next hearing for February 10, 2021.
Tribunal Order #0901126009752020-04-04-2025
Following a High Court remand, the Tribunal restored the appellant's complaint to its original status and directed U.P. RERA to decide the dispute on its merits within three months.
Tribunal Order #0901126009752020-03-01-2022
The Tribunal dismissed the appeal against the RERA order, ruling that because the real estate project was completed prior to the notification of the Rules and was not registered under the Act, it does not qualify as an 'ongoing project' and thus falls outside RERA's jurisdiction.
Tribunal Order #0901126009752020-03-03-2021
The Tribunal adjourned the appeal to 24.03.2021 and directed the respondent's counsel to ensure compliance with the previous order dated 20.01.2021.
Tribunal Disposal & Final Award Ruling
Following a High Court remand, the Tribunal restored the appellant's complaint to its original status and directed U.P. RERA to decide the dispute on its merits within three months. The Tribunal dismissed the appeal against the RERA order, ruling that because the real estate project was completed prior to the notification of the Rules and was not registered under the Act, it does not qualify as an 'ongoing project' and thus falls outside RERA's jurisdiction. Awarded in favor of Appellant.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Following a High Court remand, the Tribunal restored the appellant's complaint to its original status and directed U.P. RERA to decide the dispute on its merits within three months. The Tribunal dismissed the appeal against the RERA order, ruling that because the real estate project was completed prior to the notification of the Rules and was not registered under the Act, it does not qualify as an 'ongoing project' and thus falls outside RERA's jurisdiction.
Ruling Awarded To
Appellant
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Amit Yadav
Respondent Advocate(s)
- Siddharth Nandwani
- Shobhit Mohan Shukla
Official RERA Tribunal Orders (3)
Following a High Court remand, the Tribunal restored the appellant's complaint to its original status and directed U.P. RERA to decide the dispute on its merits within three months.
The Tribunal dismissed the appeal against the RERA order, ruling that because the real estate project was completed prior to the notification of the Rules and was not registered under the Act, it does not qualify as an 'ongoing project' and thus falls outside RERA's jurisdiction.
The Tribunal adjourned the appeal to 24.03.2021 and directed the respondent's counsel to ensure compliance with the previous order dated 20.01.2021.
Need to research all rulings for sunshine infrawell pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.