CASE ID: 0901126009312020

Appellant / Complainant

Neha Gaur

VS

Respondent

Greater Noida Industrial Development Authority

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

47 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126009312020 by Neha Gaur against Greater Noida Industrial Development Authority before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 106/03/2025

Hearing

The Tribunal modified the previous order to grant the appellant interest for the delay period from 19.09.2017 until the actual handing over of possession on 13.09.2020 at the rate of MCLR+1%.

3
Stage 212/02/2025

Hearing

The Tribunal has adjourned the appeal to March 6, 2025, for orders or hearing upon the joint request of both parties.

4
Stage 317/01/2025

Re-Hearing

The Tribunal has adjourned the appeal to 12.02.2025 following a joint request from both parties.

5
Stage 410/01/2025

For Order

The Tribunal granted a request from the appellant's counsel to list the appeal for orders on 17.01.2025.

6
Stage 502/09/2024

Hearing

The Tribunal heard arguments from both counsels regarding Appeal-459/2020 and reserved the judgment for further delivery.

7
Stage 631/07/2024

Hearing

No text available.

8
Stage 702/07/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for 31.07.2024.

9
Stage 808/05/2024

Hearing

The Tribunal has ordered the appeal to be listed on 02.07.2024 for orders.

10
Stage 905/04/2024

Hearing

The Tribunal granted a request for adjournment as the appellant's counsel was unprepared, rescheduling the hearing to 08.05.2024.

11
Stage 1029/02/2024

Hearing

The Tribunal has ordered the appeal to be listed for a hearing on 05.04.2024.

12
Stage 1122/01/2024

Hearing

The Tribunal noted that the respondent failed to produce the required regulations regarding OC/CC issuance and adjourned the matter to 29.02.2024.

13
Stage 1218/10/2023

Hearing

No text available.

14
Stage 1312/09/2023

Hearing

No text available.

15
Stage 1424/07/2023

Hearing

No text available.

16
Stage 1504/07/2023

Hearing

The Tribunal directed the respondent to comply with a previous order by producing specific NOCs (Fire, Electricity, Structural, and Lift) and requested GNIDA regulations to determine if the authority is empowered to issue backdated completion certificates.

17
Stage 1603/05/2023

For Order

The Tribunal adjourned the proceedings due to requests for adjournment from the respondent's counsel and rescheduled the hearing for 04.07.2023.

18
Stage 1724/03/2023

For Order

The Tribunal directed the Respondent (Greater Noida Authority) to produce four requisite certificates/NOCs (Fire, Electrical, Structural, and Lifts) and evidence of their application for an Occupation/Completion Certificate via affidavit within one week.

19
Stage 1816/02/2023

For Order

The tribunal adjourned the proceedings due to the absence of respondent's counsel and directed both parties to upload their pleadings within one week.

20
Stage 1916/01/2023

For Order

No text available.

21
Stage 2009/12/2022

For Order

The Tribunal has ordered the appeal to be listed for a hearing on 16.01.2023.

22
Stage 2115/11/2022

For Order

No text available.

23
Stage 2212/10/2022

Further Order

This document is a formal header/caption of an appeal (APPEAL-459/2020) before the U.P. Real Estate Appellate Tribunal involving Neha Gaur versus Greater Noida Industrial Development Authority, dated 12.10.2022.

24
Stage 2313/09/2022

Further Order

The Tribunal adjourned the proceedings due to a request for adjournment from the respondent's counsel on medical grounds and directed the parties to exchange pleadings in the interim.

25
Stage 2429/08/2022

Further Order

No text available.

26
Stage 2502/08/2022

Further Order

The Tribunal noted that lists of dates and events have been exchanged between the parties and scheduled the appeal for hearing on 29.08.2022.

27
Stage 2625/05/2022

Further Order

The Tribunal noted that the appellant declined to file a rejoinder affidavit and scheduled the case for hearing on 02.08.2022.

28
Stage 2722/04/2022

For Order

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the case for further orders on 25.05.2022.

29
Stage 2811/03/2022

For Order

The Tribunal directed both parties to exchange lists of dates, events, and relied-upon case law and scheduled the matter for final hearing on 22.04.2022.

30
Stage 2922/02/2022

Further Order

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the appeal for hearing on 11.03.2022.

31
Stage 3012/01/2022

Further Order

No text available.

32
Stage 3121/12/2021

Further Order

The Tribunal granted an adjournment requested by the respondent's counsel and granted the appellant a final opportunity to file a rejoinder to the respondent's reply.

33
Stage 3224/11/2021

Delay condonation

The Tribunal allowed the application for condonation of delay in filing the appeal, citing the Supreme Court's relaxation of limitation periods due to the Covid-19 pandemic, and directed the respondent to file a reply.

34
Stage 3326/10/2021

Delay condonation

The Tribunal granted the appellant permission to file a better affidavit and adjourned the matter to 24.11.2021 for the disposal of the limitation application.

35
Stage 3404/10/2021

Delay condonation

The Tribunal granted the appellant 10 days to file a better affidavit regarding the application for condonation of delay and scheduled the matter for hearing on 26.10.2021.

36
Stage 3519/04/2021

Delay condonation

No text available.

37
Stage 3626/03/2021

For Order

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the matter for April 19, 2021, to consider the application for condonation of delay.

38
Stage 3704/03/2021

For Order

The Tribunal adjourned the case to 26.03.2021 due to an ongoing strike by advocates and directed the parties to exchange pleadings in the interim.

39
Stage 3817/02/2021

For Order

The Tribunal directed the registry to record the respondent's counsel and listed the defective appeal for March 5, 2021, to consider an application for condonation of delay.

40
Stage 3928/01/2021

For Order

The Tribunal adjourned the matter to 15.02.2021 to allow the appellant's counsel to file a better affidavit regarding the application for condonation of delay.

41
Stage 4013/01/2021

Hearing

No text available.

42
Stage 4108/12/2020

Hearing

No text available.

43
Stage 42Final Ruling Order

Tribunal Order #0901126009312020-06-03-2025

The Tribunal modified the previous order to grant the appellant interest for the delay period from 19.09.2017 until the actual handing over of possession on 13.09.2020 at the rate of MCLR+1%.

44
Stage 43Interim Order

Tribunal Order #0901126009312020-04-07-2023

The Tribunal directed the respondent to comply with a previous order by producing specific NOCs (Fire, Electricity, Structural, and Lift) and requested GNIDA regulations to determine if the authority is empowered to issue backdated completion certificates.

45
Stage 44Interim Order

Tribunal Order #0901126009312020-24-11-2021

The Tribunal allowed the application for condonation of delay in filing the appeal, citing the Supreme Court's relaxation of limitation periods due to the Covid-19 pandemic, and directed the respondent to file a reply.

46
Stage 45Interim Order

Tribunal Order #0901126009312020-24-03-2023

The Tribunal directed the Respondent (Greater Noida Authority) to produce four requisite certificates/NOCs (Fire, Electrical, Structural, and Lifts) and evidence of their application for an Occupation/Completion Certificate via affidavit within one week.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal modified the previous order to grant the appellant interest for the delay period from 19.09.2017 until the actual handing over of possession on 13.09.2020 at the rate of MCLR+1%. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1%.

Disposal Winner: AppellantInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal modified the previous order to grant the appellant interest for the delay period from 19.09.2017 until the actual handing over of possession on 13.09.2020 at the rate of MCLR+1%.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1%

Interest Period

w.e.f. 19.09.2017 to 13.09.2020

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Vishwa Kant Srivastava
  • Vijay Kant Srivastava

Respondent Advocate(s)

  • Saurabh Misra
  • Ajay Kumar Gupta
  • Rishindra Vikram Singh

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126009312020-06-03-2025

The Tribunal modified the previous order to grant the appellant interest for the delay period from 19.09.2017 until the actual handing over of possession on 13.09.2020 at the rate of MCLR+1%.

INTERIM_ORDEROrder ID: 0901126009312020-04-07-2023

The Tribunal directed the respondent to comply with a previous order by producing specific NOCs (Fire, Electricity, Structural, and Lift) and requested GNIDA regulations to determine if the authority is empowered to issue backdated completion certificates.

INTERIM_ORDEROrder ID: 0901126009312020-24-11-2021

The Tribunal allowed the application for condonation of delay in filing the appeal, citing the Supreme Court's relaxation of limitation periods due to the Covid-19 pandemic, and directed the respondent to file a reply.

INTERIM_ORDEROrder ID: 0901126009312020-24-03-2023

The Tribunal directed the Respondent (Greater Noida Authority) to produce four requisite certificates/NOCs (Fire, Electrical, Structural, and Lifts) and evidence of their application for an Occupation/Completion Certificate via affidavit within one week.