Appellant / Complainant
Neha Gaur
Respondent
Greater Noida Industrial Development Authority
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126009312020 by Neha Gaur against Greater Noida Industrial Development Authority before up_rera.
Hearing
The Tribunal modified the previous order to grant the appellant interest for the delay period from 19.09.2017 until the actual handing over of possession on 13.09.2020 at the rate of MCLR+1%.
Hearing
The Tribunal has adjourned the appeal to March 6, 2025, for orders or hearing upon the joint request of both parties.
Re-Hearing
The Tribunal has adjourned the appeal to 12.02.2025 following a joint request from both parties.
For Order
The Tribunal granted a request from the appellant's counsel to list the appeal for orders on 17.01.2025.
Hearing
The Tribunal heard arguments from both counsels regarding Appeal-459/2020 and reserved the judgment for further delivery.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for 31.07.2024.
Hearing
The Tribunal has ordered the appeal to be listed on 02.07.2024 for orders.
Hearing
The Tribunal granted a request for adjournment as the appellant's counsel was unprepared, rescheduling the hearing to 08.05.2024.
Hearing
The Tribunal has ordered the appeal to be listed for a hearing on 05.04.2024.
Hearing
The Tribunal noted that the respondent failed to produce the required regulations regarding OC/CC issuance and adjourned the matter to 29.02.2024.
Hearing
The Tribunal directed the respondent to comply with a previous order by producing specific NOCs (Fire, Electricity, Structural, and Lift) and requested GNIDA regulations to determine if the authority is empowered to issue backdated completion certificates.
For Order
The Tribunal adjourned the proceedings due to requests for adjournment from the respondent's counsel and rescheduled the hearing for 04.07.2023.
For Order
The Tribunal directed the Respondent (Greater Noida Authority) to produce four requisite certificates/NOCs (Fire, Electrical, Structural, and Lifts) and evidence of their application for an Occupation/Completion Certificate via affidavit within one week.
For Order
The tribunal adjourned the proceedings due to the absence of respondent's counsel and directed both parties to upload their pleadings within one week.
For Order
The Tribunal has ordered the appeal to be listed for a hearing on 16.01.2023.
Further Order
This document is a formal header/caption of an appeal (APPEAL-459/2020) before the U.P. Real Estate Appellate Tribunal involving Neha Gaur versus Greater Noida Industrial Development Authority, dated 12.10.2022.
Further Order
The Tribunal adjourned the proceedings due to a request for adjournment from the respondent's counsel on medical grounds and directed the parties to exchange pleadings in the interim.
Further Order
The Tribunal noted that lists of dates and events have been exchanged between the parties and scheduled the appeal for hearing on 29.08.2022.
Further Order
The Tribunal noted that the appellant declined to file a rejoinder affidavit and scheduled the case for hearing on 02.08.2022.
For Order
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the case for further orders on 25.05.2022.
For Order
The Tribunal directed both parties to exchange lists of dates, events, and relied-upon case law and scheduled the matter for final hearing on 22.04.2022.
Further Order
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the appeal for hearing on 11.03.2022.
Further Order
The Tribunal granted an adjournment requested by the respondent's counsel and granted the appellant a final opportunity to file a rejoinder to the respondent's reply.
Delay condonation
The Tribunal allowed the application for condonation of delay in filing the appeal, citing the Supreme Court's relaxation of limitation periods due to the Covid-19 pandemic, and directed the respondent to file a reply.
Delay condonation
The Tribunal granted the appellant permission to file a better affidavit and adjourned the matter to 24.11.2021 for the disposal of the limitation application.
Delay condonation
The Tribunal granted the appellant 10 days to file a better affidavit regarding the application for condonation of delay and scheduled the matter for hearing on 26.10.2021.
For Order
The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the matter for April 19, 2021, to consider the application for condonation of delay.
For Order
The Tribunal adjourned the case to 26.03.2021 due to an ongoing strike by advocates and directed the parties to exchange pleadings in the interim.
For Order
The Tribunal directed the registry to record the respondent's counsel and listed the defective appeal for March 5, 2021, to consider an application for condonation of delay.
For Order
The Tribunal adjourned the matter to 15.02.2021 to allow the appellant's counsel to file a better affidavit regarding the application for condonation of delay.
Tribunal Order #0901126009312020-06-03-2025
The Tribunal modified the previous order to grant the appellant interest for the delay period from 19.09.2017 until the actual handing over of possession on 13.09.2020 at the rate of MCLR+1%.
Tribunal Order #0901126009312020-04-07-2023
The Tribunal directed the respondent to comply with a previous order by producing specific NOCs (Fire, Electricity, Structural, and Lift) and requested GNIDA regulations to determine if the authority is empowered to issue backdated completion certificates.
Tribunal Order #0901126009312020-24-11-2021
The Tribunal allowed the application for condonation of delay in filing the appeal, citing the Supreme Court's relaxation of limitation periods due to the Covid-19 pandemic, and directed the respondent to file a reply.
Tribunal Order #0901126009312020-24-03-2023
The Tribunal directed the Respondent (Greater Noida Authority) to produce four requisite certificates/NOCs (Fire, Electrical, Structural, and Lifts) and evidence of their application for an Occupation/Completion Certificate via affidavit within one week.
Tribunal Disposal & Final Award Ruling
The Tribunal modified the previous order to grant the appellant interest for the delay period from 19.09.2017 until the actual handing over of possession on 13.09.2020 at the rate of MCLR+1%. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal modified the previous order to grant the appellant interest for the delay period from 19.09.2017 until the actual handing over of possession on 13.09.2020 at the rate of MCLR+1%.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR + 1%
Interest Period
w.e.f. 19.09.2017 to 13.09.2020
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Vishwa Kant Srivastava
- Vijay Kant Srivastava
Respondent Advocate(s)
- Saurabh Misra
- Ajay Kumar Gupta
- Rishindra Vikram Singh
Official RERA Tribunal Orders (4)
The Tribunal modified the previous order to grant the appellant interest for the delay period from 19.09.2017 until the actual handing over of possession on 13.09.2020 at the rate of MCLR+1%.
The Tribunal directed the respondent to comply with a previous order by producing specific NOCs (Fire, Electricity, Structural, and Lift) and requested GNIDA regulations to determine if the authority is empowered to issue backdated completion certificates.
The Tribunal allowed the application for condonation of delay in filing the appeal, citing the Supreme Court's relaxation of limitation periods due to the Covid-19 pandemic, and directed the respondent to file a reply.
The Tribunal directed the Respondent (Greater Noida Authority) to produce four requisite certificates/NOCs (Fire, Electrical, Structural, and Lifts) and evidence of their application for an Occupation/Completion Certificate via affidavit within one week.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.