Appellant / Complainant
Ashoka Sharma
Respondent
Tyagi Construction Company & Othres
tyagi construction company & othres
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126009222020 by Ashoka Sharma against Tyagi Construction Company & Othres before up_rera.
to file objections and its reply
The U.P. Real Estate Appellate Tribunal dismissed Appeal-530/2020, noting that it was dismissed via a prior order dated 12.04.2022 in the related case of Ashoka Sharma Vs. M/s Tyagi Construction Company & Ors.
to file objections and its reply
The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the next hearing for 12.04.2022.
Further Order
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the appeal for hearing on 22.03.2022.
Further Order
The Tribunal granted an adjournment requested by the respondent and directed the applicant and the respondent's partner to appear in person on the next date to attempt an amicable settlement.
Hearing
The Tribunal directed the parties to attempt an out-of-court settlement regarding a dispute over disputed payments and adjourned the matter to 28.10.2021.
Hearing
The Tribunal noted an application for compromise but recorded allegations from the appellant's husband regarding forged signatures and unauthorized photographs on the settlement papers. The matter is adjourned to 29.09.2021 for further orders with a direction for parties to appear in person.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to her being out of station and rescheduled the hearing for 08.04.2021.
Further Hearing
The Tribunal noted the respondent's claim of a settlement while the appellant requested an adjournment to verify this information; consequently, the matter is adjourned to 12.03.2021.
Tribunal Order #0901126009222020-12-04-2022
The U.P. Real Estate Appellate Tribunal dismissed Appeal-530/2020, noting that it was dismissed via a prior order dated 12.04.2022 in the related case of Ashoka Sharma Vs. M/s Tyagi Construction Company & Ors.
Tribunal Order #0901126009222020-09-09-2021
The Tribunal noted an application for compromise but recorded allegations from the appellant's husband regarding forged signatures and unauthorized photographs on the settlement papers. The matter is adjourned to 29.09.2021 for further orders with a direction for parties to appear in person.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal dismissed Appeal-530/2020, noting that it was dismissed via a prior order dated 12.04.2022 in the related case of Ashoka Sharma Vs. M/s Tyagi Construction Company & Ors. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal dismissed Appeal-530/2020, noting that it was dismissed via a prior order dated 12.04.2022 in the related case of Ashoka Sharma Vs. M/s Tyagi Construction Company & Ors.
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Fuhar Gupta
- Prashant Kumar Singh
Respondent Advocate(s)
- Sanjay Kumar Srivastava
Official RERA Tribunal Orders (2)
The U.P. Real Estate Appellate Tribunal dismissed Appeal-530/2020, noting that it was dismissed via a prior order dated 12.04.2022 in the related case of Ashoka Sharma Vs. M/s Tyagi Construction Company & Ors.
The Tribunal noted an application for compromise but recorded allegations from the appellant's husband regarding forged signatures and unauthorized photographs on the settlement papers. The matter is adjourned to 29.09.2021 for further orders with a direction for parties to appear in person.