up_reraStatus: Completed
CASE ID: 0901126009212020

Appellant / Complainant

Akshat Agarwal, Ghaziabad Development Authority

VS

Respondent

Ghaziabad Development Authority

Disputed Amount

8,63,000

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferMaintenance & Utility Disputes

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

28 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126009212020 by Akshat Agarwal, Ghaziabad Development Authority against Ghaziabad Development Authority before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferMaintenance & Utility Disputes
2
Stage 107/05/2024

for delivery of Judgment/Order

The Appellate Tribunal partially allowed the appeal, modifying the Regulatory Authority's order to extend the interest period for delayed possession from 31.03.2018 to 03.06.2017, while upholding the legality of the developer's demand for payment regarding the enhanced area of the unit.

3
Stage 230/01/2024

Hearing

The appellant is challenging the Regulatory Authority's order regarding the commencement date for interest on delayed possession and directions related to clearing dues. The court heard arguments concerning whether a reasonable three-year period for completion should be applied from the original allotment or the alternate unit offer.

4
Stage 331/10/2023

Hearing

No text available.

5
Stage 420/09/2023

Hearing

The Tribunal granted the appellant a three-day extension to comply with a previous order by providing an amended copy of the appeal to the respondent via email.

6
Stage 503/08/2023

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the appeal for a hearing on 20.09.2023.

7
Stage 623/05/2023

Hearing

The Tribunal allowed the appellant's application to amend the relief clause regarding the interest rate from '3.5%' to 'MCLR+1%' and directed the filing of an amended appeal within three days.

8
Stage 717/04/2023

Hearing

The Tribunal adjourned the proceedings because the respondent's counsel was out of station and scheduled the matter for May 23, 2023, to consider the appellant's application for amendment regarding interest rates.

9
Stage 817/03/2023

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the appeal for a hearing on 17.04.2023.

10
Stage 908/02/2023

Hearing

No text available.

11
Stage 1009/01/2023

Further Order

The Tribunal directed the Registry to correct the counsel's name in the cause list and reiterated a previous order condoning delay subject to a cost of Rs. 8,000, while setting timelines for filing replies and objections.

12
Stage 1107/12/2022

for delivery of Judgment/Order

The U.P. Real Estate Appellate Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 8,000/- to be split between the Tribunal's Fund and the respondent.

13
Stage 1208/12/2021

Further Order

The Tribunal heard arguments regarding a limitation application and reserved its judgment on the issue of limitation.

14
Stage 1316/11/2021

Delay condonation

The Tribunal directed the parties to appear on the next date for the disposal of a limitation application and its objections, scheduling the matter for 08.12.2021.

15
Stage 1422/10/2021

Delay condonation

The Tribunal noted the change in counsel for the applicant and scheduled the matter for 16.11.2021 to decide on the limitation application.

16
Stage 1528/09/2021

Delay condonation

The Tribunal adjourned the matter to 22.10.2021 for consideration of an application for condonation of delay and directed the parties to exchange objections and pleadings via email and the e-portal.

17
Stage 1608/09/2021

Delay condonation

The Tribunal granted an adjournment request made by the respondent's counsel due to illness and rescheduled the case for 28.09.2021.

18
Stage 1726/04/2021

Delay condonation

No text available.

19
Stage 1801/04/2021

Delay condonation

No text available.

20
Stage 1910/03/2021

Delay condonation

No text available.

21
Stage 2024/02/2021

For Order

The case is adjourned because lawyers are abstaining from work due to a call by the Oudh Bar Association; the matter is rescheduled for 10.03.2021.

22
Stage 2102/02/2021

Hearing

The Tribunal granted a request for adjournment and rescheduled the case to 24.02.2021 for consideration of an application for condonation of delay.

23
Stage 2215/01/2021

Hearing

No text available.

24
Stage 23Final Ruling Order

Tribunal Order #0901126009212020-07-05-2024

The Appellate Tribunal partially allowed the appeal, modifying the Regulatory Authority's order to extend the interest period for delayed possession from 31.03.2018 to 03.06.2017, while upholding the legality of the developer's demand for payment regarding the enhanced area of the unit.

25
Stage 24Interim Order

Tribunal Order #0901126009212020-30-01-2024

The appellant is challenging the Regulatory Authority's order regarding the commencement date for interest on delayed possession and directions related to clearing dues. The court heard arguments concerning whether a reasonable three-year period for completion should be applied from the original allotment or the alternate unit offer.

26
Stage 25Interim Order

Tribunal Order #0901126009212020-07-12-2022

The U.P. Real Estate Appellate Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 8,000/- to be split between the Tribunal's Fund and the respondent.

27
Stage 26Interim Order

Tribunal Order #0901126009212020-09-01-2023

The Tribunal directed the Registry to correct the counsel's name in the cause list and reiterated a previous order condoning delay subject to a cost of Rs. 8,000, while setting timelines for filing replies and objections.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal partially allowed the appeal, modifying the Regulatory Authority's order to extend the interest period for delayed possession from 31.03.2018 to 03.06.2017, while upholding the legality of the developer's demand for payment regarding the enhanced area of the unit. Awarded in favor of Partial. Awarded interest rate: MCLR+1% per annum.

Disposal Winner: PartialInterest Rate: MCLR+1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal partially allowed the appeal, modifying the Regulatory Authority's order to extend the interest period for delayed possession from 31.03.2018 to 03.06.2017, while upholding the legality of the developer's demand for payment regarding the enhanced area of the unit.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR+1% per annum

Interest Period

from 03.06.2017 to 04.02.2019

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 11(4)(d)Section 19(6)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rajesh Chadha

Respondent Advocate(s)

  • Rishabh Raj

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126009212020-07-05-2024

The Appellate Tribunal partially allowed the appeal, modifying the Regulatory Authority's order to extend the interest period for delayed possession from 31.03.2018 to 03.06.2017, while upholding the legality of the developer's demand for payment regarding the enhanced area of the unit.

INTERIM_ORDEROrder ID: 0901126009212020-30-01-2024

The appellant is challenging the Regulatory Authority's order regarding the commencement date for interest on delayed possession and directions related to clearing dues. The court heard arguments concerning whether a reasonable three-year period for completion should be applied from the original allotment or the alternate unit offer.

INTERIM_ORDEROrder ID: 0901126009212020-07-12-2022

The U.P. Real Estate Appellate Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 8,000/- to be split between the Tribunal's Fund and the respondent.

INTERIM_ORDEROrder ID: 0901126009212020-09-01-2023

The Tribunal directed the Registry to correct the counsel's name in the cause list and reiterated a previous order condoning delay subject to a cost of Rs. 8,000, while setting timelines for filing replies and objections.