Appellant / Complainant
Treadstone Limited
Respondent
U.P. Real Estate Regulatory Authority
treadstone limited
Appellant
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126009102025 by Treadstone Limited against U.P. Real Estate Regulatory Authority before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal set aside the U.P. RERA's rejection of a project registration application and ruled that the project is deemed registered under Section 5 of the RERA Act due to the Authority's failure to decide within the mandatory 30-day period.
Hearing
The Tribunal heard arguments from both the appellant and respondent regarding the appeal and its objections, subsequently reserving the judgment for a later date.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to illness, with a condition that no further adjournments will be permitted, and rescheduled the matter for final arguments on 22.05.2025.
Hearing
The Tribunal directed the respondent to upload objections today and granted the appellant leave to file a rejoinder, scheduling the final hearing for May 20, 2025.
Defect Removal
The Tribunal noted the removal of registry defects and granted the respondent a one-week extension to file objections, scheduling the matter for orders on 16.05.2025.
Defect Removal
The Tribunal granted the respondent ten days to file objections, with the appellant permitted to file a reply within one week thereafter, and scheduled the next hearing for May 6, 2025.
Defect Removal
The Tribunal noted the appearance of counsel for both parties and scheduled the case for orders on 11.04.2025, with an application for interim relief to be considered at that time.
Tribunal Order #0901126009102025-29-05-2025
The Appellate Tribunal set aside the U.P. RERA's rejection of a project registration application and ruled that the project is deemed registered under Section 5 of the RERA Act due to the Authority's failure to decide within the mandatory 30-day period.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal set aside the U.P. RERA's rejection of a project registration application and ruled that the project is deemed registered under Section 5 of the RERA Act due to the Authority's failure to decide within the mandatory 30-day period. Awarded in favor of Appellant.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal set aside the U.P. RERA's rejection of a project registration application and ruled that the project is deemed registered under Section 5 of the RERA Act due to the Authority's failure to decide within the mandatory 30-day period.
Ruling Awarded To
Appellant
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Saurabh Misra
- Krishna Kumar Singh
Respondent Advocate(s)
- Shobhit Mohan Shukla
Official RERA Tribunal Orders (1)
The Appellate Tribunal set aside the U.P. RERA's rejection of a project registration application and ruled that the project is deemed registered under Section 5 of the RERA Act due to the Authority's failure to decide within the mandatory 30-day period.
Need to research all rulings for treadstone limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.